10 BROAD STREET EXTERIOR PAINT REMOVAL VIOLATION 11-3-2022 CIT'Y OF SALEM, MASSACHUSET"TS
BOARD OF HEALTH PL1bH �1
98 WASHINGTON STREET,3'�FLOOR Prevent.Promote.Protect.
TEL. (978) 741-1800
KIMBERLEY DRISCOLL health((7salem.com
DAVID GREENBAUM,RS
MAYOR HEALTH AGENT
Exterior Paint Removal Violation
November 3, 2022
Donald &Grace Friary
10 Broad Street
Salem, MA 01970
Dear Sir and Madam,
An inspection of your property at 10 Broad Street has revealed violation(s)of the City of Salem's Board
of Health Regulation 23: Exterior Paint Removal and Abrasive Blasting. The following was discovered:
1. Operating without an exterior paint removal or abrasive blasting permit
2. Failure to enclose or curtain off that area of the building undergoing abrasive blasting
3. Visible emission of particulate matter or air contaminants outside of the area enclosed in
accordance with provisions 6.4(b)and 6.5(a)of the regulation
_4. Failure to ensure adequate precautions against ground surface contamination as required by
provisions 6.4(d)and 6.5(b)of the regulation
5. Failure to clean property in accordance with section 7 of the regulation
6. Evidence of blood lead level elevation in operator
7. Other(Please describe):
Exterior Paint Removal Contractor: 4 Yes _No
If Yes:
George Painting
2 Weston Road
Marblehead, MA 01945
781-639-1699
The inspector has taken the following action:
_A. Ordered all exterior paint removal work to cease and desist until all violations are corrected.
Owner or contractor must correct all violations indicated to continue exterior paint removal work.
_B. Ordered all exterior paint removal work to cease and desist until all violations are corrected.
Exterior paint removal work allowed to continue after all violations were corrected on site.
_C. Exterior paint removal permit revoked because of work needing to be stopped twice on the same
day due to violations.
D. Other(Please Describe): Exterior paint removal was already completed. Inspector informed
xterior paint removal contractor a permit is required to perform exterior paint removal work in the City of
Salem. Inspector also informed contractor that he and the owners of the property would receive violations
letters as warning not to do exterior paint removal work without a permit in the future.
Repeat of any violations may result in monetary fines issued to the property owner, and the contractor(if
applicable). If a contractor has been found to commit the same or similar violations.at different work sites
that contractor may be issued a monetary fine.
Should you be aggrieved by this order, you have the right to request a hearing before the Board of
Health. A request for said hearing must be received in writing in the office of the Board of Health within 7
Days of receipt of this order. At said hearing, you will be given an opportunity to be heard and to present
witness and documentary evidence as to why this order should be modified or withdrawn: You may be
represented by an attorney. Please also be informed that you have the right to inspect and obtain copies
of all relevant inspection or investigation reports, orders, and other documentary information in the
possession of this Board, and that any adverse party has the right to be present at the hearing.
Fort e B< of Health Reo y t :
David Greenbaum•.. r Barosy
Health Agent Sanitarian
Cc: Exterior Paint Removal Contractor(if applicable)