ARCHITECT'S FIELD REPORT
PROJECT NAME: Pequot Highlands Interior Mod-Rehab
PROJECT LOCATION: 12 First Street Salem,MA United States
ARCHITECT'S PROJECT#: 16068.00 ;'= 00025
DATE: 5/14/2018
WEATHER DESCRIPTION:
TIME TEMP WIND SPEED HUMIDITY REMARKS
11:00 AM 57°F 4.6 mph 78% Overcast
EST.%COMPLETION&CONFORMANCE WITH SCHEDULE:75%Complete
PRESENT ON-SITE:
Eric Clory The Silver Street Group,LLC
Mike Swiatek Port Harbor Construction,INC.
Carpenter,Electricians,Elevator Techs,Landscapers,and
Painters
Chris Poulin Silver Street Development
Michelle King The Silver Street Group,LLC
Joan Russell WinnCompanies
TOTAL: 6
OBSERVATIONS:
ITEM CATEGORY REMARKS PHOTOS
1 Work in Landscaping to clean up construction damage is
Progress ongoing.
2 Work in Corridor painting is ongoing.Last floor of 6 story
Progress building finishing up this week.
3 Work in Corridor carpet installation is on hold.Waiting for
Progress correct carpet to be delivered to the site.
4 Work in Elevator#2 scope of work is ongoing.
Progress
5 Work in Existing office area renovation is complete.Office
Progress staff will be moving back into the office so that
community room and lobby area work can
commence.
6 Work in North Building roof replacement is ongoing.98%
Progress complete.Parapet installation is beginning.
7 Work in Bridge panel installation is ongoing.Missing area
The Architectural Team,Inc. 50 Commandant's Way at Admiral's Hill Chelsea MA 02150 T 617.889.4402 F 617.884.4329 www.archrtecturalteam.com
Page 1 of 6
ARCHITECT'S FIELD REPORT
DATE: 5/14/2018
FR: 00025
ITEM CATEGORY REMARKS PHOTOS
Progress drop closest to south facade of 12 story building.
8 Work in Window installation is ongoing on the 12 story
Progress building.
9 Work in Brick demo on north and west facade of 12 story
Progress building is ongoing.
10 Work in Pipe staging removal from the east facade of the 12
Progress story building is ongoing.
11 Work in Framing,densglass installation and AVB application
Progress on south facade of 12 story building is ongoing.
12 Items to Verify PHC must verify CoGen exhaust location complies
with engineer's response to RFI#30.
13 Observations Framing,densglass installation and AVB application
on east facade of 12 story building is complete.
14 Observations Photos
f
use
The Architectural Team,Inc. 50 Commandant's Way at Admiral's Hill Chelsea MA 02150 T 617.889.4402 F 617.884.4329 www.archltecturalteam.com
Page 2 of 6