ARCHITECT'S FIELD RPT 4/20/18 the
architectural
ARCHITECT'S FIELD REPORT tatteam
PROJECT NAME: Pequot Highlands Interior Mod-Rehab
PROJECT LOCATION: 12 First Street Salem, MA United States
ARCHITECT'S PROJECT#: 16068.00 FIELD REPORT: 00022
DATE: 4/2/2018
WEATHER DESCRIPTION:
TIME TEMP WIND SPEED HUMIDITY REMARKS
11:00 AM 30°F 3.5 mph 92% Light Snow
EST.%COMPLETION&CONFORMANCE WITH SCHEDULE:68%Complete
PRESENT ON-SITE:
Chris Poulin Silver Street Development
Carpenters,Plumbers,Electricians,Elevator Techs
Cliff Ageloff Partner Engineering and Science, Inc.
Eric Clory The Silver Street Group,LLC
Mike Swiatek Port Harbor Construction,INC.
TOTAL: 5
OBSERVATIONS:
ITEM CATEGORY REMARKS PHOTOS
1 Work in Corridor painting is ongoing.
Progress
2 Work in Corridor carpet installation is ongoing.
Progress
3 Work in South Building roof replacement ongoing.98%
Progress complete.Roof parapet installation is ongoing due
to favorable temperatures.
4 Work in North Building roof replacement is ongoing.98%
Progress complete.Cell phone equipment relocation is
ongoing.
5 Work in Elevator#2 scope of work is ongoing.
Progress
6 Work in South building lobby work is ongoing.
Progress
7 Work in Window and panel exterior trim installation is
Progress ongoing
The Architectural Team, Inc. 50 Commandants Way at Admiral s Hill Chelsea AIA 02150 T 617.889.44x)2 F 61 7.884.4329 xww.architecturaReam.com
Page 1 of 4
ARCHITECT'S FIELD REPORT
DATE: 4/212018
FR: 00022
ITEM CATEGORY REMARKS PHOTOS
8 Work in Pipe staging installation is ongoing for 12 story
Progress building on western and eastern facade.
9 Work in Swingstage work on 12 story building is ongoing.
Progress Brick demo is ongoing on the southern facade.Brick
demo has begun on the eastern facade.
10 Work in Bridge panel installation is ongoing.
Progress
11 Work in Storefront installation is ongoing throughout.
Progress
12 Work in Office renovation is ongoing.
Progress
13 Observations Unit punchlist work is complete
14 Items to Verify PHC must verify CoGen exhaust location complies
with engineer's response to RFI#30.
15 Observations Photos
X ,.h
A
The Architectural Team, Inc. 50 Commandants Way at Admiral's Hill Chelsea MA 02150 T 617.889.4402 F 617.884.4329 www-.architecturalteam.com
Page 2 of 4
ARCHITECT'S FIELD REPORT
DATE: 4/2/2018
FR: 00022
ITEM CATEGORY REMARKS PHOTOS
a
.,tea
}: 4W
'
e
Citi a
f
ATTACHMENTS:
Report By: The Architectural Team,Inc./Lamarr Rollins II
The Architectural Team, Inc. 50 Commandant's Way at Admital s Hill Chelsea MA 02150 T 617.889.4402 F 61 7.884.4329 Ha.^.w,architecturalteam.com
Page 3 of 4
M {
ARCHITECT'S FIELD REPORT
DATE: 4/212018
FR: 00022
Distribution:
Phil Renzi The Architectural Team,Inc. prenzi@architecturalteam.com
Chris Poulin Silver Street Development cpoulin@thesilverstreetgroup.com
Eric Clory The Silver Street Group,LLC eclory@thesilverstreetgroup.com
Mike Swiatek Port Harbor Construction,INC. mswiatek@portharborconstruction.co
m
The Architectural Team, Inc 50 Commandants Ways at Admirals Hill Chelsea MA 02150 T 0i7.889.=4402 F 6'17.884,4329 mw. vv.archdecturalteam,rom
Page 4 of 4