Bertram Field Phase 2 Improvements - February 20, 20191
Captain John Bertram Athletic Field
Phase 2 Improvements
Design Development Manual
February 20, 2019
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN2
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN 3
Bertram Field Phase 2 Improvements
Schematic Design Report
Section 1
Section 2
Section 3
Section 4
Section 5
Section 6
Executive Report
Criteria Sheets, Site Evaluation, & Preliminary
Concepts
Stakeholders Meetings & Proposed Options
Program
Schematic Design of Option 4 & Parking
Analysis
Cost Estimate
Appendix
Plumbing Variance & Associated Application
The LEED Scorecard and Evaluation
The Mechanical Schematic Narrative
The Plumbing Schematic Narrative
The Structural Narrative
The Civil Narrative
Operation & Maintenance Recommendations
Municipal & State Agency Review
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN4
PARTICIPANTS
City of Salem - Client
• Jenna Ide phone: (978) 619-5699 email: jide@salem.com
Director of Capital Projects & Muncipal Operations
• Trish O’Brien phone: (978) 744-0180 x43001 email: pobrien@Salem.com
Executive Director
• Deborah Duhamel phone: (978) 619-5661 email: dduhamel@Salem.com
Assistant City Engineer
• Ryan Monk phone: (978) 619-5661 email: dduhamel@Salem.com
Director of Buildings and Grounds
Beacon Architectural Associates - Architect
• J. Michael Sullivan phone: (617) 01-3840 email: jmsullivan@beaconarch.com
Project Architect & Principal in Charge
• Richard Ryan phone: (617) 357-7171 email: rryan@beaconarch.com
Senior Project Manager
Leftfield - Owners Project Manager
• David Saindon phone: (617) 737-6400 email:dsaindon@leftfieldpm.com
Project Executive
• Adam Keane phone: (617) 593-9539 email: akeane@leftfieldpm.com
Senior Project Manager
Weston & Sampson - HVAC and Plumbing Engineers
• Scott Henriques phone:(978) 532-1900 email: henriquess@wseinc.com
Toole Design Landscape Architects and Circulation Consultants
• Karen Fitzgerald phone: (617) 619-9910 email: kfitzgerald@tooledesign.com
• Lyndia Hausle phone: (617) 619-9910 email: lhausle@tooledesign.com
Owl Engineering - Electrical Engineers
• Judith O’Brien phone: (978) 621-2319 email: jobrien@owlengineers.com
nv5 Engineers - Sustainability
• Dana Etherington phone: (857) 221-5928 email: detherington@nv5.com
• Marcus Hazelwood phone: (857) 221-5934 email: Marcus.Hazelwood@nv5.com
Weston and Sampon- Civil Engineers
• James Pearson phone: (78) 532-1900 email: personj@wse.com
Hastings Consulting - Code Consultants
• Kevin Hastings phone: (508) 397-8417 email: kevin@hastings-consulting.com
PM&C - Cost Estimators
• Peter Bradley phone: (781) 740-8007 email: peterbradley@pmc.ma.com
• Maria McKenna phone: (781) 740-8007 email: mariamckenna@pmc.ma.com
Welch & Associates Land Surveyors, Inc. - Surveying
• Pamela Welch phone: (508) 580-4696 email: pwelch@welchinc.com
• Kraig Kilpatrick phone: (508) 580-4696 email: kkilpatrick@welchinc.com
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN 5
OVERVIEW
Purpose and Goals
The purpose of this report is to provide recommendations regarding facility improvements
to the Bertram Athletic Field. Support buildings address four distinct areas: concessions,
public amenities, locker facilities for athletic participants, and barrier-free access to the
press box. This study recommends the priorities, budgets, and overall schedule within
which to achieve the goal of a state-of-the-art athletic facility for the City of Salem.
Methodology
The methodology to arrive at this schematic design incorporated public meetings, regular
design progress meetings, and meetings with Salem police, fire, and plumbing officials. The
design team visited nearby facilities in Danvers and Lynn, and met with other various field
managers to learn from their operations and experiences.
A series of meetings were held with key administrative staff and interested members of
the public (see section on Stakeholder Meetings). The initial meeting sought to confirm the
actual programming needs. The following meeting introduced recommendations and com-
ments which allowed the design team to refine the preferred design option represented in
the schematic design.
Vision
The Bertram Athletic Field has been and always will be an icon for the City of Salem. The
field has generated unforgettable memories for thousands of Salemites and their neigh-
bors. Phase 1 improvements addressed the athletic surface and the lighting. This study
focuses in on the additional improvements to the Bertram Field facility.
Bertram Field will be a facility which will serve a variety of sports and field organizations
from Salem and the surrounding regions. The facility will provide visitors and athletes the
safety, accessibility, and comfort of a first-class municipal facility for all amateur sporting
events.
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN6
PHASE 2 SCHEMATIC DESIGN
The Bertram Athletic Field has a new turf field, but suffers from inadequate building facil-
ities. The schematic design presented in this report defines the buildings and their loca-
tions.
The overall Design Criteria for the buildings are:
• Sustainable design and Net Zero Energy facility
• Separate pedestrians from vehicle access to the entry
• Separate the athletic changing area from the public amenity spaces
• Protect visitors from inclement weather by providing semi-sheltered areas
• Provide outdoor grilling area for informal food preparation
• Improve the architecture to present a unified, thematic aspect to the entry and
the various facilities
• Provide a location for public art installations
• Provide 25 women’s toilets and 16 men’s toilets/urinals.
• The concessions stand will provide snacks and beverages. Pizza, hot dogs, and
pre-packaged foods will be served. Hot beverages will be provided.
• The athletic changing facility will provide space for teams to prepare and gather
away from the spectators.
• Provide accessibility to the press box
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN 7
Key Recommendations
Management and Operations
• Provide coordinated management and supervision within the City through
regular meetings with users and the Public Works department
• Determine the event scheduling and hours of operations
• Establish a capital improvement fund and seek resources through user’s fees,
grants, and other sources to undertake necessary improvements, repairs, and
replacements
• Maintain all facilities so that they are always clean, repaired, and free from any
debris
• Measure success by surveying visitors and modifying the operations as needed
to always be sensitive to the community’s desires for Bertram Field
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN8
CONTEXT
The Recent History of Bertram Field
Bertram Field has been providing the North Shore with a unique site for outdoor athletic
events for over one hundred years. Tent cities sprang up on the field as part of the recovery
from the Salem fire of 1914. The locker facilities were constructed in the 1930’s.
In 2012, the City Council approved funding for the renovation of the field. A complete reno-
vation of the field complex was completed in the summer of 2013, adding a new turf field, a
six-lane running track, scoreboard, and a new flag pole. The visitor’s grandstand was re-
moved. Neither the press box nor the locker rooms were renovated.
Bertram Field is used in the fall and spring by:
• The Salem High School Varsity field sports program
• The Salem High School Junior Varsity field sports program
• Salem High School Marching Band
• Salem Youth Field Sports Program
• Collins Middle School Physical Education
• Parks and Recreation Summer Programs
• Residents
There are approximately 100 events scheduled at the field during the fall and spring sea-
sons. Bertram Field is maintained and administered by the Salem School Facilities Depart-
ment (SSFD). The funding and revenue management is a collaboration between the City of
Salem and the SSFD.
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN 9
Opportunities
The strengths Bertram Field possesses were revealed during the evaluations of the site and
the discussions with the working committee. Among the most notable strengths are:
• Ability to provide pedestrians with plaza space at the entry
• Enhanced pedestrian circulation around Collins Middle School
• Ser vice entrance off of Bertuccio Avenue
• Undeveloped site to the north which could be improved for Collins Middle
School and Ber tram Field
Constraints
The constraints of the field lie primarily in the existing siting of the facility. Most of the man-
made constraints, such as the toilet facilities and lack of barrier-free access are the focus
of this report.
The Areas of Responsibility are:
1. Maintenance
• Depar tment of Public Works and the Salem School Department
2. Scheduling
• Salem School Depar tment
3. Revenue Management
• Depar tment of Parks and Recreation
4. Capital Improvements
• Depar tment of Parks and Recreation
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN10
THE PRIORITIES
Provide coordinated management and supervision with the City through regular meet-
ings with users and selected departments within city government.
The management of Bertram Field is currently the responsibility of the Salem School Facili-
ties Department. The scheduling, determination of fees, and the concession stands are du-
ties shared between the Department of Public Works, Department of Parks and Recreation,
and the School Department.
The operational responsibilities of Bertram Field need to be clearly defined by the City of
Salem. The maintenance of the facility, scheduling of events, administering revenue, and
monitoring the use of the concessions facilities are specific base line responsibilities which
need to be discussed and assigned as soon as possible.
It is important one entity be responsible for supervising the operations and scheduling of
Bertram Field. Other towns assign this responsibility to either the Parks and Recreation
Department or the Community Development office. An individual should be designated to
monitor the operations of the field on a daily basis. This is not a full-time responsibility; rath-
er ten to fifteen percent of this persons time should be allocated to Bertram Field.
The existing press box is not accessible for all.Proposed area for barrier-free access to the press
box.
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN 11
Determine the scheduling of events and the hours of operations.
The City should determine whether the School or Parks and Recreation Department will
lead scheduling of all events at the field. It is recommended that a web-based calendar be
available to confirm the event times are known to all users.
The city should consider the hours of operation. The park should not be open 24 hours,
7 days a week. Typically, facilities in neighboring communities are open from 6:00am till
dusk, unless there are scheduled evening events.
Establish a capital improvement fund and seek resources through user’s fees, grants,
and others.
The City of Salem budget for the Department of Parks and Recreation (DPR) should estab-
lish a dollar amount for the DPR to manage with. This will define the financing of mainte-
nance and upkeep. To supplement the budget, the DPR should seek alternative resources
for capital improvements and major equipment replacement, such as grants and private
corporate donations.
Setting fees for the use of the field should be considered. The concessions and ticket sales
should be managed by the DPR and the revenues from each can be shared with the respec-
tive users.
A committee of users and representatives of city departments will be assembled to
assist and monitor specific areas of operations. Suggested participants (not to exceed 8
members) of this committee are:
• Salem High School Athletic Director
• Salem High School Field Coaches
• Representatives from the Department of Public Works
• Representatives from the Parks and Recreation Department
• Representative from the Youth Sports Program
• Interested Citizens
Measure success by surveying visitors and users. Modify the operations as needed to
always be sensitive to the community’s expectations.
Monitoring the opinions of users and visitors establishes a good metric with which to decide
how to improve the care of Bertram Field. The survey should be done at the end of the fall
season.
City of Salem Project # Bertram Field, Phase 2 Feasibility Study - BUDGET TRACKINGCurrent BudgetProject Director / Manager: David Saindon / Adam KeanePeriod Ending 1/17/2018Includes Invoice Summary xxxxReimbursement Package n/aBudgetCommittedRemaining% Complete CTCAnticipated Variance Changes CostsExpended Unspent Budget(against committ'd) (beyond committed)C @ C(Under)/Over[A] [B] [C] [D] [E] [F]=[D]-[E] [G]=[C]-[D] [H]=[E]/[J] [I] [J]=[D]+[I] [K]=[J]-[C]0001 0000 Owner's Project Manager$26,766 $0 $26,766 $26,766 $20,075 $6,691 $0 $0 $26,766 $00001 0000 Feasibility Study (Leftfield, LLC) $26,766 $0 $26,766 $26,766 $20,075 $6,691 $0 75% $0 $26,766 $00002 0000 Designer$99,500 $115,410 $214,910 $211,910 $77,450 $134,460 $3,000 $3,000 $214,910 $00002 0000 Feasibility Study (Beacon Architects) $99,500 $0 $99,500 $99,500 $77,450 $22,050 $0 78% $0 $99,500 $00002 0000 Early Release DD Work (Beacon Architects) $0 $112,410 $112,410 $112,410 $0 $112,410 $0 0% $0 $112,410 $00002 0000 Parking Study at Collins site and adjacent areas (PLUG)$0 $1,500 $1,500 $0 $0 $0 $1,500 $1,500 $1,500 $00002 0000 Parking Study at Collins site (STANTEC) (PLUG) $0 $1,500 $1,500 $0 $0 $0 $1,500 $1,500 $1,500 $0.0003 0000 Environmental, Site, Other$0 $42,670 $42,670 $42,670 $0 $42,670 $0 $0 $42,670 $00003 0000 Subconsultants $0 $0 $0 $0 $0 $0 $0 $0 $0 $00003 0000 Tighe+Bond - GeoEnvironmental $0$15,200 $15,200$15,200 $0 $15,200 $0 0% $0 $15,200 $00003 0000 Tighe+Bond - GeoTechnical $0$17,700 $17,700$17,700 $0 $17,700 $0 0% $0 $17,700 $00003 0000 Tighe+Bond - ACM assessment $0$5,800 $5,800$5,800 $0 $5,800 $0 0% $0 $5,800 $00003 0000 BMC - Clean, inspect sanitary lines CCTV/JET $0 $3,360$3,360$3,360 $0 $3,360 $0 0% $0 $3,360 $00003 0000 Metro-Swift - Hydrant flow test $0 $610 $610 $610 $0 $610 $0 0%$0 $610 $00004 0000 OTHER$171,056 ($158,080) $12,976 $0 $0 $0 $12,976 $12,976 $12,976 $000040000Owner's Contingency/Other $171,056 ($158,080) $12,976 $0 $0 $0 $12,976$12,976 $12,976 $000040000Need to carry misc costs for LEED registration, other, etc. $0 $0$0$0$0$0$0 $0$0$000040000xxxx$0 $0 $0 $0 $0 $0 $0 $0 $0 $000040000xxxx$0 $0 $0 $0 $0 $0 $0 $0 $0 $0FEASIBILITY STUDY TOTALS $297,322 $0 $297,322 $281,346 $97,525 $183,821 $15,976 $15,976 $297,322 $00100 0000 ADMINISTRATION$405,000 $0 $405,000 $0 $0 $0 $405,000 $405,000 $405,000 $00101 0000 Legal Fees $25,000 $0 $25,000 $0 $0 $0 $25,000 $25,000 $25,000 $00102 0000 Owner's Project Manager $0 $0 $0 $0 $0 $0 $0 $0 $0 $00102 0400 Design Development $55,000 $0 $55,000 $0 $0 $0 $55,000 $55,000 $55,000 $00102 0500 Construction Contract Docs $55,000 $0 $55,000 $0 $0 $0 $55,000 $55,000 $55,000 $00102 0600 Bidding $30,000 $0 $30,000 $0 $0 $0 $30,000 $30,000 $30,000 $00102 0700 Construction Contract Administration $200,000 $0 $200,000 $0 $0 $0 $200,000 $200,000 $200,000 $00102 0800 Closeout $10,000 $0 $10,000 $0 $0 $0 $10,000 $10,000 $10,000 $00102 1000 Reimbursable & Other Services $0 $0 $0 $0 $0 $0 $0 $0 $0 $00102 1100 Cost Estimates $0 $0 $0 $0 $0 $0 $0 $0 $0 $00102 9900 Other Project Manager Costs $0 $0 $0 $0 $0 $0 $0 $0 $0 $00103 0000 Advertising (bidding) $5,000 $0 $5,000 $0 $0 $0 $5,000 $5,000 $5,000 $00104 0000 Permitting Fees (assumed waived) $0 $0 $0 $0 $0 $0 $0 $0 $0 $00105 0000 Owner's Insurance (Builder's Risk) $10,000 $0 $10,000 $0 $0 $0 $10,000 $10,000 $10,000 $00199 0000 Other Administrative Costs $15,000 $0 $15,000 $0 $0 $0 $15,000 $15,000 $15,000 $00200 0000 ARCHITECTURE & ENGINEERING $384,370 $0 $384,370 $0 $0 $0 $384,370 $384,370 $384,370 $00201 0000 Basic Services $0 $0 $0 $0 $0 $0 $0 $0 $0 $00400 Design Development - Early Release (carried above) $0 $0 $0 $0 $0$0$0 $0$0$00410 Survey $0 $0 $0 $0 $0 $0 $0 $0 $0 $00420 LEED Admin $0 $0 $0 $0 $0 $0 $0 $0 $0 $00430 Circulation Planning $0 $0 $0 $0 $0 $0 $0 $0 $0 $00440 Cost Estimation $0 $0 $0 $0 $0 $0 $0 $0 $0 $00450 Fund Raising $0 $0 $0 $0 $0 $0 $0 $0 $0 $00460 Landscape Archtiecture $0 $0 $0 $0 $0 $0 $0 $0 $0 $00470 Integrated Design $0 $0 $0 $0 $0 $0 $0 $0 $0 $00500 Construction Contract Documents $120,370 $0 $120,370 $0 $0 $0 $120,370 $120,370 $120,370 $00510 Life cycle assessment $11,500 $0 $11,500 $0 $0 $0 $11,500 $11,500 $11,500 $00520 Energy Modeling $3,000 $0 $3,000 $0 $0 $0 $3,000 $3,000 $3,000 $00530 Commissioning LEED $6,500 $0 $6,500 $0 $0 $0 $6,500 $6,500 $6,500 $00201 0600 Bidding $10,000 $0 $10,000 $0 $0 $0 $10,000 $10,000 $10,000 $00700 Construction Contract Administration $96,700 $0 $96,700 $0 $0 $0 $96,700 $96,700 $96,700 $00710 LEED Admin $16,300 $0 $16,300 $0 $0 $0 $16,300 $16,300 $16,300 $00201 0800 Closeout - PLUG $25,000 $0 $25,000 $0 $0 $0 $25,000 $25,000 $25,000 $00203 0000 Reimbursable and Other Services $0 $0 $0 $0 $0 $0 $0 $0 $0 $00203 0100 Construction Testing (carried below) $0 $0 $0 $0 $0 $0 $0 $0 $0$00203 0200 Printing (over minimum) $0 $0 $0 $0 $0 $0 $0 $0 $0 $00204 0000 Sub-Consultants $0 $0 $0 $0 $0 $0 $0 $0 $0 $00204 0200 Hazardous Materials (reporting and monitoring) PLUG $25,000 $0 $25,000 $0 $0 $0 $25,000 $25,000 $25,000 $00204 0300 GeoTechnical & Geo-Environmental - PLUG $50,000 $0 $50,000$0 $0 $0 $50,000 $50,000 $50,000 $0Bertram Field, Phase 2 Feasibility Study - BUDGET TRACKINGBudgetRevised Budget020102010201David:PO is for $1,000; permit fee is $390; thus commitment is $610David:Value was $98,050; value increased/decreased:- Circulation planning decreased from $6,000 to $3,000- Cost estimating included at $4,000 - Landscape archtiecture included at $4,860- Integrated design included at $8,5002/12/2019C:\Users\David\Dropbox (Leftfield)\Salem_Bertram Field\3-Budget\LF budget\Bertram Field Phase 2_budget tracking 02_12_2019Page 1 of 2
City of Salem Project # Bertram Field, Phase 2 Feasibility Study - BUDGET TRACKINGCurrent BudgetProject Director / Manager: David Saindon / Adam KeanePeriod Ending 1/17/2018Includes Invoice Summary xxxxReimbursement Package n/aBudgetCommittedRemaining% Complete CTCAnticipated Variance Changes CostsExpended Unspent Budget(against committ'd) (beyond committed)C @ C(Under)/Over[A] [B] [C] [D] [E] [F]=[D]-[E] [G]=[C]-[D] [H]=[E]/[J] [I] [J]=[D]+[I] [K]=[J]-[C]Bertram Field, Phase 2 Feasibility Study - BUDGET TRACKINGBudgetRevised Budget0204 0400 Site Survey - PLUG $10,000 $0 $10,000 $0 $0 $0 $10,000 $10,000 $10,000 $00204 0500xxxxx$10,000 $0 $10,000 $0 $0 $0 $10,000 $10,000 $10,000 $00500 0000 CONSTRUCTION CONTRACT$4,379,699 $0 $4,379,699 $0 $0 $0 $4,379,699 $4,379,699 $4,379,699 $00501 0000Pre-Construction Services (n/a)$0 $0 $0 $0 $0 $0 $0 $0 $0 $00502 0000Construction (per current estimate)$4,379,699 $0 $4,379,699 $0 $0 $0 $4,379,699 $4,379,699 $4,379,699 $00600 0000 MISCELLANEOUS PROJECT COSTS$95,000 $0 $95,000 $0 $0 $0 $95,000 $95,000 $95,000 $00601 0000 Utility Company Fees - PLUG $20,000 $0 $20,000 $0 $0 $0 $20,000 $20,000 $20,000 $0Utility Company - rebates/refunds (estimated plug) $0 $0 $0 $0 $0 $0$0 $0 $0 $00602 0000 Testing Services $50,000 $0 $50,000 $0 $0 $0 $50,000 $50,000 $50,000 $00603 0000 Swing Space/Modulars $0 $0 $0 $0 $0 $0 $0 $0 $0 $00699 0000 Other Project Costs - PLUG $25,000 $0 $25,000 $0 $0 $0 $25,000$25,000 $25,000 $00700 0000 FURNISHINGS & EQUIPMENT$40,000 $0 $40,000 $0 $0 $0 $40,000 $40,000 $40,000 $00701 0000Furnishings & Equipment (FF+E) - PLUG$30,000 $0 $30,000 $0 $0 $0 $30,000 $30,000 $30,000 $00702 0000Technology Equipment - PLUG$10,000 $0 $10,000 $0 $0 $0 $10,000 $10,000 $10,000 $00799 0000 Other Furnishings & Equipment $0 $0 $0 $0 $0 $0 $0 $0 $0 $00800 0000 OWNER'S CONTINGENCY$484,188 $0 $484,188 $0 $0 $0 $484,188 $484,189 $484,189 $10801 0000 Owner's Contingency (soft) 5% $46,219 $0 $46,219 $0 $0 $0 $46,219 $46,219 $46,219 $10507 0000 Owner's Construction Contingency (hard) 10% $437,970 $0 $437,970 $0 $0 $0 $437,970 $437,970 $437,970 $0PROJECT TOTALS $6,085,579 $0 $6,085,579 $281,346 $97,525 $183,821 $5,804,233 $5,804,234 $6,085,580 $12/12/2019C:\Users\David\Dropbox (Leftfield)\Salem_Bertram Field\3-Budget\LF budget\Bertram Field Phase 2_budget tracking 02_12_2019Page 2 of 2
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN 13
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN14 CRITERIA SHEETS, SITE EVALUATION, & PRELIMINARY CONCEPTS
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN 15
SPACE CRITERIA DOCUMENTATION
Space Criteria is the foundation of a successful space program. This documentation estab-
lishes the needs, the spaces needing to be adjacent to it, and the size of the space. Each
space was analyzed with the group and the stakeholders.
The spaces documented herein are:
Home and Visiting Team Satellite Locker Room
Officials Locker Room
Press Box
Concession Station
Public Toilets
Pedestrian Entry
First Aid / Training Facility
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN16
FUNCTION OF SPACE: Pre-Game Preparation / Half Time Conference / Post Game Review
ADJACENCIES TO OTHER SPACES: Toilets
OCCUPANCY: 60 - 70 Players
Locker Room Characteristics per 2016 Feasibility Study
• Open area
• 700 - 800 square feet
• No fixed benches
• Clothing pegs on walls
• No lockers
• Good acoustics
• Marker board
Questions / Answers Regarding the Salem Satellite Locker Rooms:
1 . How do Salem athletes prepare for a game at Bertram Field?
Players dress for games at the school locker rooms and travel to Bertram via bus. Showers are taken
in the school locker rooms. The building committee recommends perimeter seating, without lockers,
and no fixed seating.
2. What do Salem athletes leave behind in the locker room?
Backpacks with personal items. Secure storage for backpacks necessary. Athletes may bring their
own personal locks.
3. Do coaches use overhead projectors for half-time diagrams?
3 areas for whiteboard meetings should be provided. Teams split up in groups.
4. Will there be any gender-neutral sports teams?
Yes - a room should be provided in the toilet area for gender privacy changing.
5. How many toilets should be provided.
2 urinals and 3 toilets are recommended. There will be no showers.
Home and Visiting Team Satellite Locker Room
Bertram Field Improvements Phase 2
Criteria and Questions
December 11, 2018
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN 17
FUNCTION OF SPACE: Pre and Post Game Preparation for Male and Female Officials
ADJACENCIES TO OTHER SPACES: Satellite Locker Rooms
OCCUPANCY: 6 - 8 People
Officials Locker Room Characteristics per 2016 Feasibility Study
• Gender neutral. Minority gender will use
enclosed room. Room to have toilet and
lavatory. Sanitary facilities include private
changing room
• Accessible (including changing room)
• Located in concessions building, remote
from team locker rooms
Officials Locker Room
Bertram Field Improvements Phase 2
Criteria and Questions
December 11, 2018
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN18
FUNCTION OF SPACE:
• Public Address Announcer Work Station (2)
• Reporters Work Station (2)
• Home Team Assistant Coaches Work Station (2)
• Visiting Team Assistant Coaches Work Station (2)
• Score Keeper
• Home Team Camera Platform
• Visiting Team Camera Platform
OCCUPANCY: 10 - 12 People
Press Box Characteristics per 2016 Feasibility Study
• Located at center of field within grandstands
• Clothing pegs on walls
• Acoustical isolation for work station
• Markerboards
• Accessible from grandstands
• Universal access via lift for press box and the public for higher seating
• Extension of roof to shelter grandstand and provide a site for solar panels
Press Box
The 2015 IBC, section 1104.3.2 - States a press box greater than 500 sq.ft. and more than
12’-0” above grade does have to be accessible. The Bertram Field press box will be greater
than 500 square feet and more than 12’-0” above grade.
Bertram Field Improvements Phase 2
Criteria and Questions
December 11, 2018
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN 19
FUNCTION OF SPACE: Providing food and drink to visitors
ADJACENCIES TO OTHER SPACES: Home Team Grandstand
OCCUPANCY: 10 Staff
Concessions Characteristics per 2016 Feasibility Study
• Accessible serving stations
• Storage for food and beverage
• Preparation stations
• Menu board
• Cold water
• Dr y goods storage
• Refrigeration
• 3-bay sink with grease trap
Questions / Answers Regarding the Salem Concessions:
1 . What foods will be served that will not be pre-packaged?
Pizza, hot dogs, coffee, and hot chocolate.
2. Will food be cooked on-site?
A portable grill will be occasionally set up outside the concession stand. There will be no grilling or
cooking in the concession area. Water will be heated for coffee and hot chocolate.
3. Will pots, pans, or reusable cooking utensils be used that must be cleaned?
No. Cooking will not be done
4. Will concessions be managed by vendors or volunteers?
It will be managed by boosters and volunteers.
5. Will transactions be made by cash, credit/debit, or both?
Both.
Concessions Station
Bertram Field Improvements Phase 2
Criteria and Questions
December 11, 2018
FUNCTION OF SPACE: Providing Food and Drink to Visitors
ADJACENCIES TO OTHER SPACE: Home Team Grandstands
OCCUPANCY: 10 Staff
Concession Station Characteristics:
Accessible serving stations
Storage for food and beverage
Prep stations
Menu board
Cold Water
Dry good storage
Refrigeration
3 bay sink with grease trap
Questions Regarding Concession Station
1.What foods will be served that are not pre-packaged?
Pizza, hot dogs, coffee, and hot chocolate.
2.Will food be cooked on-site?
A portable grill will be occasional set up outside the concession stand. There will be no grilling in the
concession area. Water will be heated for coffee and hot chocolate.
3.Will pots, pans, or reusable cooking utensils be used that must be cleaned?
No
4.Will concessions be managed by vendors or volunteers?
Boosters and volunteers
5.How will transactions be made – Cash only? Credit?
To be determined
Space Criteria
Concessions Building
Bertram Field Improvements Phase 2
Criteria and Questions
December 11, 2018
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN20
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN 21
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN22
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN 23
Public Toilets Characteristics per 2016 Feasibility Study
• Baby changing station
• Universal accessibility
• Water efficient fixtures
• Waste water
• Indoor air quality
• Separated universal room
Toilet Fixture Calculation based on a 5,000-seat grandstand (existing). Variance has been received.
Public Toilets
The Commonwealth of Massachusetts Plumbing Code 248 CMR for A-5, Stadium occupancies requires toilets at
1:30 females and 1:60 males for the first 2,000 occupants. Above 2,000, the fixture ratios increase to 1:100 fe-
males and 1:200 men.
Bertram Field Improvements Phase 2
Criteria and Questions
December 11, 2018
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN24
Toilet Fixture Calculation based on a 4,000-seat grandstand (potential alternate).
Bertram Field Improvements Phase 2
Criteria and Questions
December 11, 2018
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN 25
Bertram Field Improvements Phase 2
Criteria and Questions
December 11, 2018
FUNCTION OF SPACE: Distribute Tickets
ADJACENCIES TO OTHER SPACE: Home Team Grandstands
OCCUPANCY: Drop-Off Area and Parking.
Entry Characteristics:
Accessible
Allow For group gathering
Display merchandise
Secure field
Public art and identity
Questions Regarding Entry
1.How many ticket booths?
2.
2.Pick-up and Drop off sequence – who gets dropped off? Where?
Buses dropping off teams, parents dropping off players, spectators being dropped off.
Space Criteria
Entry
FUNCTION OF SPACE: Distribute Tickets
ADJACENCIES TO OTHER SPACES: Home Team Grandstands
OCCUPANCY: Drop-Off Area and Parking
Entry Characteristics
• Accessible
• Allows for group gathering
• Display merchandise
• Secure field
• Public art and identity
Entry
Questions / Answers Regarding the Salem Entry:
1 . How many ticket booths are needed?
Two.
2. What is the pick-up and drop-off sequence? Who gets dropped off and where?
Buses will be dropping off teams, parents will be dropping off players, and spectators will be
dropped off.
3. What activities are visualized outside the gate?
Spectators waiting for other spectators, raffles, ticket sales, and table seating.
Bertram Field Improvements Phase 2
Criteria and Questions
December 11, 2018
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN26
FUNCTION OF SPACE: Care for Injured Players and Preparing Players for Games
ADJACENCIES TO OTHER SPACES: Satellite Locker Rooms
OCCUPANCY: 3 - 4 People
First Aid / Training Facility Characteristics
• 120 square feet
• (2) treatment tables
• Toilet facilities
• Ice machine
• EMT access
• Cabinet storage
• Visibility
First Aid / Training Facility
Bertram Field Improvements Phase 2
Criteria and Questions
December 11, 2018
FUNCTION OF SPACE: Care for Injured Players and Preparing
Players For Games
ADJACENCIES TO OTHER SPACE: Satellite Locker Rooms
OCCUPANCY: 3-4 People
AREA : 120 Sq, Ft.
First Aid/Training Facility Characteristics:
Treatment Table (2)
Toilet facilities
Ice Machine
EMT Access
Cabinet Storage
Visibility
Questions Regarding First Aid/Training Facility
1.Will facility be used for Physical Therapy?
No.
2.Will ice bath be used?
No.
Space Criteria
First Aid / Training Facility
Questions / Answers Regarding the Salem First Aid / Training Facility:
1 . Will the facility be used for Physical Therapy?
No.
2. Will an ice bath be used?
No.
Bertram Field Improvements Phase 2
Criteria and Questions
December 11, 2018
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN 27The Bertram Field SiteBertram Field has a number of feature’s worth taking note of in analyzing the site. Those feature’s have been highlighted on the site plan to provide a basis of knowledge on how these feature’s impacted design choices.The property line of Bertram Field is noted in solid black.------------The extent of the new track is noted in dashed purple.The extent of the old track is noted in dashed green.The ridge edge is noted in solid red.The location of options is designed to fit in between the property line and existing ridge edge in order to preserve the landscape conditions present on site.PREVIOUSLY BLASTED AREAPROPERTY LINE AREAS UNDERNEGOTIATIONOVERALL SITE ANALYSISAPRIL 2, 2018
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN28USABLE SPACE FOR EXTERIOR ACTIVITY AND INTERIOR DEVELOPMENTPREVIOUSLY BLASTED AREAENTRY STUDYAPRIL 2, 2018ACCESSIBLE PARKINGASSUMEDPROPERTY LINE& AREA UNDERNEGOTIATIONRIDGE EDGEBUSFIRE PUM
P
Bus: 40’ length 8’ widthFire Truck: 32’ length 8’ widthCURB RADIUS 25’TURNING RADIUS 42‘LANE WIDTH 17’EXISTING DRIVEWAY LIMITPREVIOUSLY BLASTED AREAProposedBuild AreaThe proposed build area is made up of an existing parking lot, and part of thelandscape next to the field.A new facilities building with locker rooms, ticket sales, concessions, and toilet rooms, as well as a fire lane and bus drop off adjacent to the new building is beingproposed.Entry StudyThe proposed parking plan includes a dropoff and turnaround adjacent to the building, including area for a fire lane, and accessible parking spaces near the facilities building.The dropoff would include:24’ - 60’ in center diameter60’ - 100’ in total diameter80’ available for fire pump spaceThe vehicle lane between to the drop off and accessible parking would be 12’ - 15’ wide.
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN 29CRITERIA SHEETS, SITE EVALUATION, & PRELIMINARY CONCEPTSSTAKEHOLDERS MEETINGS & PROPOSED OPTIONS
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN30
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN 31
STAKEHOLDERS MEETINGS
Two stakeholders meetings were held. The first introduced the project to interested parties,
reviewed the criteria documentation, the preliminary program, and the site constraints.
The second meeting presented four options relating to building layouts and locations. This
meeting also included a site visit to the field prior to discussing the options.
This section includes the minutes from those meetings and the associated graphics.
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN32
145 South Street, Third Floor, Boston, Massachusetts 02111
www.beaconarch.com | 617.357.7171
MEETING MINUTES
Meeting Minutes No. 1 – Stakeholders Meeting
Project Name: Bertram Field Improvements Phase 2
Project No.: 18-877
Project Location: Salem, Massachusetts
Date: 4.11.2018
Attendees:
☒J. Michael Sullivan, Beacon
☒Thomas Lassy, Beacon
☒Jenna Ide – City of Salem
☒Paul L’Heureux – Salem School Department
☒Joe Candelaria – Salem Parks Department
☐Patricia O'Brien – Salem Parks Department
☐Scott Connolly– Athletics Director
☐Kristin Shaver - Salem School Department
☐Michael Lutrzykowski - City of Salem
☒Richard Stafford – Salem Track Coach
☐Jerry L. Ryan - Stakeholder
☐Matt Bouchard - Football Coach
☒Chris Burke - Park and Recreation Commission
☐Cliff Goodman - Bertuccio Neighbor
☒Eric Papetti - Bike Committee member
☒Wally Mielcarz
☐Gary Lavoie
☒Michelle Kiley - Resident
☐Dominick Pangallo – City of Salem
☐Cynthia Napierkowski – Music Director
☐Lt. Bob Preczewski – Salem Police
☒Captain Mark Losolfo – Salem Police
☐DC Gerry Giunta – Salem Fire
☒Lisa Peterson – Ward 3 Councilor
☐Dave Knowlton – City Councilor
☐Matt Smith – Director of Traffic & Parking
☐David Angeramo - Principal Salem HS
☒Diego Fellows – stakeholder
☐Ron Miano – Football Pop Warner
☐Michael Collins - Soccer Coach
☐Steve Szpak - Ward 3 Neighbor
☐Kelly Porter - Ward 3 Neighbor
☒Chris Cantone- Sustainability & Energy Board
☒Charles O'Donnell
☒Melissa Barnes
☒Shelly Bisegna – Salem Hospital
ITEM DESCRIPTION
DATE TO BE
COMPLETED ACTION BY
01 This kick off meeting for the Bertram Field – Phase 2 focused on the
following items;
1.Discussion of various goals and visions for the project
2.Discussion of Barrier Free Access improvements
3.Establishing working objects for the next meeting.
On going ALL
02 BAA will be responsible for keeping meeting minutes On going ALL
03 Project should aim to meet universal design standards On going ALL
04 Project goal is for this to be a net zero energy project.
•PVs can be included on site/buildings
•Explore alternate option of expanded PV array
On going ALL
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN 33
145 South Street, Third Floor, Boston, Massachusetts 02111
www.beaconarch.com | 617.357.7171
MEETING MINUTES
05 Existing Conditions
•Site Constraints
1.Ledge
2.Property line
3.Existing structures (grandstands, ticket booths, field
house, fencing)
On Going INFO
06 Project/Construction Phasing
•Goal is to keep field open and operational during construction
•Due to demolition of existing facilities the field not be available for
games but has potential for practices.
•Phasing will be determined during the design process
On Going BAA
07 Precedent Studies
•Bryant University - 4,400 seats total
•North Andover High School – 4,000 Seats total
•Winchester High School – 1,200 Seats total
•City of Framingham Bowditch Field – 3.500 Seats Total
•Endicott College, Hempstead Stadium – 3,000 Seats total
•Triton Memorial Field, Byfield, MA – 1,512 seats & Capacity for an
additional standing room of up to 1,000 spectators.
•Danvers High school – 2,600 Seats Total
INFO
08 Design Considerations - Programming
Ticketing:
•Area after entry tends to get congested – design should aim to
open area after ticketing.
•Ticketing should be large enough for multiple staff members
•Adjacent to other money taking operations for security
•Separate sales and ticketing could streamline entry
Concessions:
•Estimates for warming kitchen and full kitchen
•Management of kitchen – staff vs volunteers
1.Capacity for 8+ concession workers
•Outdoor area for grills for cooking hot foods (included in warming
kitchen option)
•Adjacent to other money taking operations for security
Public Toilets:
•Code for public toilets require a significant amount of fixtures
1.Project will seek a variance
•Considerations for future capacity
Locker Rooms:
•Officials lockers
1.Include shower
•Home and visitors’ locker rooms
1.Toilet fixtures in locker room (3 toilets min)
2.Pegs and fixed benches with foot lockers area perimeter
3.Flexible seating provided (movable benches)
On going BAA
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN34
145 South Street, Third Floor, Boston, Massachusetts 02111
www.beaconarch.com | 617.357.7171
MEETING MINUTES
First Aid and Training:
•Single shared facility for both teams
•Adjacent to the home and visitor locker rooms
Press Box:
•Accessible access
•Improve facilities for staff and possibilities
•Heat & A/C – 3 season facilities
•No need for use in winter months
Entry:
•Accessible
•Area for use for congregating and boosters
•Site constraints are major considerations
•Player and spectator interaction is part of the experience
•Provide access for emergency vehicles
•Parking goal is to keep as many parking spaces as possible
•Security cameras would be benefit for security
•Pedestrian access to site for neighbors
Booster and Merchandise Sales:
•Exterior area on site
•Storage area for tables
Storage:
•Maintenance equipment
•Additional machinery
•Entry to storage from track level would be beneficial
09 Schedule
•Next meeting - TBD INFO
We believe these minutes accurately reflect the discussion of this meeting. Please notify the author if there are any
comments, corrections, or additions within three (3) days of receipt.
Sincerely,
BEACON ARCHITECTURAL ASSOCIATES
Thomas Lassy, Job Captain
Attached: site analysis and program
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN 35The Bertram Field SiteBertram Field has a number of feature’s worth taking note of in analyzing the site. Those feature’s have been highlighted on the site plan to provide a basis of knowledge on how these feature’s impacted design choices.The property line of Bertram Field is noted in solid black.The extent of the new track is noted in dashed purple.The extent of the old track is noted in dashed green.The ridge edge is noted in solid red.The location of options is designed to fit in between the property line and existing ridge edge in order to preserve the landscape conditions present on site.PREVIOUSLY BLASTED AREAPROPERTY LINE UNDER LAND SWAP AGREEMENTASSUMED PROPERTY LINEOVERALL SITE ANALYSISAPRIL 11, 2018
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN36
NAME/LOCATION CAPACITY COST
1 Bryant Uni Beirne Stadium
RI
4,400
(3,200‐seat permanent bleacher
comprises the backdrop for the
home side of the field, while 1,200
additional seats are available on
the visitor's side.)
2 Lawrence High School
Veterans Memorial Stadium
Lawrence, MA
9,000 seats
3 Roxbury Memorial High School
White Stadium
Boston, MA
10,000 seats Constructed between
1945 and 1949 for a cost
of $2 million
4 North Andover High
School Track and Field
North Andover, MA
4,000 seats
5 Winchester High School Field
MA
1,200 seats
6 Town of Framingham
Bowditch Field
MA
2,600 seats
7 Endicott College
Beverly, MA
3,000 seats
8 The Triton Regional High School
Triton Memorial Field
Byfield, MA
The stadium will seat 1,512, with
additional standing room that will
increase capacity by approximately
another 1,000 spectators.
9 Danvers High School
MA
2,600 seats
10 Beverly High School
Hurd Stadium
MA
The new stadium seating has been
reduced from 5,000 to 2,000. There
will no longer be any stands and
what was the home side of the field.
BertBertram Field, Salem, MA, Precedence Studies, 2018-03-06
BERTRAM FIELD, SALEM, MA, PRECEDENT STUDIES, 2018-03-06
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN 37
Bryant University Beirne Stadium, MA, 4400 seats
North Andover High School
Track and field
North Andover, MA, 4000 seats
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN38
Winchester High School Field
MA,1200 seats
Endicott College
Beverly,MA, 3000 seats
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN 39
Danvers High School
MA,2600 seats
Beverly High School
Hurd Stadium
MA,after renovation 2000 seats
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN40
145 South Street, Third Floor, Boston, Massachusetts 02111
www.beaconarch.com | 617.357.7171
MEETING MINUTES
Meeting Minutes No. 2 – Stakeholders Meeting
Project Name: Bertram Field Improvements Phase 2
Project No.: 18-877
Project Location: Collins Middle School
Salem, Massachusetts
Date: May 9, 2018
Attendees:
☒J. Michael Sullivan – Beacon Architectural Associates
☒Jenna Ide – City of Salem
☒Paul L’Heureux – Salem School Department
☒Ryan Monks – Salem School Department
☐Joe Candelaria – Salem Parks Department
☐Patricia O'Brien – Salem Parks Department
☒Scott Connolly– Athletics Director
☐Kristin Shaver - Salem School Department
☐Michael Lutrzykowski - City of Salem
☒Richard Stafford – Salem Track Coach
☐Jerry L. Ryan - Stakeholder
☐Matt Bouchard - Football Coach
☐Chris Burke - Park and Recreation Commission
☐Cliff Goodman - Bertuccio Neighbor
☒Eric Papetti - Bike Committee member
☒Wally Mielcarz
☐Gary Lavoie
☐Michelle Kiley - Resident
☐Dominick Pangallo – City of Salem
☐Cynthia Napierkowski – Music Director
☐Lt. Bob Preczewski – Salem Police
☒Captain Mark Losolfo – Salem Police
☐DC Gerry Giunta – Salem Fire
☒Lisa Peterson – Ward 3 Councilor
☐Dave Knowlton – City Councilor
☐Nick Dunig – Acting Director of Traffic & Parking
☐David Angeramo - Principal Salem HS
☒Diego Fellows –Stakeholder
☒Ron Miano – Football Pop Warner
☐Michael Collins - Soccer Coach
☐Steve Szpak - Ward 3 Neighbor
☐Kelly Porter - Ward 3 Neighbor
☒Chris Cantone- Sustainability & Energy Board
☒Charles O'Donnell
☐Melissa Barnes
☐Shelly Bisegna – Salem Hospital
0BITEM 1BDESCRIPTION
DATE TO BE
COMPLETED 2BACTION BY
01 Introductions were made, and then the group took a field trip to Bertram
Field. The tour focused on the approach to the field, and the critical
locations such as the area behind the grandstands, the press box, the
area east of the track, and the pedestrian’s plaza immediately in front of
the field.
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN 41
145 South Street, Third Floor, Boston, Massachusetts 02111
www.beaconarch.com | 617.357.7171
MEETING MINUTES
02 The group returned to the Collins Cafeteria, to review the various options
presented by the City and BAA and to discuss specific concerns. The specific
concerns discussed included;
•Parking
•Security
•Ledge Removal
•Emergency Access
•Storage
03 Parking
•No net loss of spaces in the Collins Middle School Area. The project
will reduce the parking in front of Bertram Field by 10 to 15 spaces.
Other spaces will be found to replace and/or to add to the existing
spaces.
•Goal is to separate spectators/users walking to the field from
vehicles.
04 Sustainability
•Similar for all buildings
•Goal is zero net energy and LEED certification
05 Security
•Cameras will have proposed at strategic locations
•Try to maintain good sight lines from the entry to the field.
•The access from Bertuccio Ave. will be improved for security and
emergency access.
•Access from Bertuccio will be secured during games, and only used
for emergency and occasional maintenance purposes
06 Ledge Removal
•Ledge will be removed to expand access roads, building sites,
and/or parking spaces.
07 Emergency Access
•Fire pump trucks will access from the main entry, ambulances will
access from both main entry and Bertuccio Ave.
08 Storage
There are two different storage needs.
1.Athletic Field Equipment
2.Maintenance Equipment
Portions of the area under the grandstands will be designated for
equipment that is resistant to weather
A storage enclosure will be in the north eastern portion of the site, with the
Option 4 athletic changing facility.
09 The City and BAA presented four options for consideration, and looked to
stakeholders for pros/cons and a consensus
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN42
145 South Street, Third Floor, Boston, Massachusetts 02111
www.beaconarch.com | 617.357.7171
MEETING MINUTES
10 Option 1- Development of the Southern Area
Pros:
•Less congestion in entrance
Cons:
•Very remote from entry, no visual connection
•More expensive
•Long utility lines
•Ledge
This is the least preferred option.
11 Option 2- Framing the Entry
Pros:
•Less utility lines
•Good visibility
•Confined construction area
•Maintains grassy area on eastern side
Cons:
•Too congested
•Requires significant ledge removal
•Use of space immediately near field
•Athletics/spectators circulation intersection
•Construction phasing will be difficult because the facilities are so
close together
This option is the third preferred option.
12 Option 3- New Building in the Grandstand
Pros:
•Separates athletes and spectators
•Enclosed elevator to press box
•Landscape development of southern area for marching band
•Improvement to area under the grandstand
•Maintains grassy area on eastern side
Cons:
•Poor visibility to entry
•Highest projected cost
•Impact of existing grandstand seating
This option is the second preferred option.
13 Option 4- Develop the Eastern Area
Pros:
•Excellent site lines to entry
•Separates athletes and spectators
•Keeps the entry plaza open
•Emergency access to Bertuccio Ave. possible
•Landscape development of southern area for marching band
On going BAA
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN 43
145 South Street, Third Floor, Boston, Massachusetts 02111
www.beaconarch.com | 617.357.7171
MEETING MINUTES
•Improvement to area under the grandstand
Cons:
•Impact of the javelin throwing area
•Potential blasting
•Impact of existing grandstand seating
This option is the preferred option.
14 Next Steps
•This project will be presented to the Park and Recreation
Committee Tuesday, May 15th
•A variance for relief from Plumbing Fixture requirements will
begin.
•The survey to be completed
•Design team to develop Option 4
•Develop Alternative Report – Option 3
•Funding for next phase of design
We believe these minutes accurately reflect the discussion of this meeting. Please notify the author if there are any
comments, corrections, or additions within three (3) days of receipt.
Sincerely,
BEACON ARCHITECTURAL ASSOCIATES
J. Michael Sullivan AIA< LEED AP BD+C
Attached: Options 1,2,3 and 4 site plans
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN44 BUILDINGS & RAMPSPEDESTRIAN SURFACEAUTOMOBILE SURFACEGAME DAY PEDESTRIAN AREATOTAL SITE: 60,945 SQ. FT.AREA UNDER THE BLEACHERSPUBLIC AMENITIESSTORAGERAMP TO PRESS BOXATHLETIC CHANGING FACILITY
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN 45BUILDINGS & RAMPSPEDESTRIAN SURFACEAUTOMOBILE SURFACEGAME DAY PEDESTRIAN AREATOTAL SITE: 51,830 SQ. FT.AREA UNDER THE BLEACHERSPUBLIC AMENITIESSTORAGERAMP TO PRESS BOXATHLETIC CHANGING FACILITY
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN46 BUILDINGS & ELEVATORSPEDESTRIAN SURFACEAUTOMOBILE SURFACEGAME DAY PEDESTRIAN AREATOTAL SITE: 62,300 SQ. FT.AREA UNDER THE BLEACHERSPUBLIC AMENITIESSTORAGEATHLETIC CHANGING FACILITY & ELEVATOR TO PRESS BOX
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN 47BUILDINGS & RAMPSPEDESTRIAN SURFACEAUTOMOBILE SURFACEGAME DAY PEDESTRIAN AREATOTAL SITE: 53,503 SQ. FT.AREA UNDER THE BLEACHERSPUBLIC AMENITIESSTORAGERAMP TO PRESS BOXATHLETIC CHANGING FACILITYJAVELIN THROW AREA
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN50
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN 51 PROGRAM
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN52
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN 53
PROGRAM
The program was derived by interviews with the user groups, coaches, and stakeholders to
the operations and maintenance of Bertram Field.
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN54
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN 55Space ProgramCity of Salem9/1/2018Population Existing S.F.Population Proposed S.F.NotesTicket Sales230Ticket Booth264Concessionsn/a06226Concessions Storagen/a0164Official's Room4200683Official's Sanitary ( changing room)175172Sheltered Arean/a0551Control Roomn/a038Electrical100114Janitor0167Men's Public Toliets7 Toilets22525 Toilets55716 provided, variance requiredWomen's Public Toilet5 Toilets 30049 Toilets129525 provided, variance requiredSheltered Arean/a0534930subtotal3765Home Team Locker Room70800780Home Team Sanitary3120146one changing room Visiting Team Locker Room70750755Visiting Team Sanitary3120146one changing room Home Coaches Room073Home Coaches Toilet & Sink049Visiting Coaches Room073Visiting Coaches Toilet & Sink1049First Aid026217902333Storage BuildingField & Sports Equipment Storage10227227(2) Camera Platforms120236Head Coach3076Visiting Coach3076Announcers3043Reporters043Entry w/ Limited Access Lift0375210849Existing Total2,9307,174Public Amenity BuildingAthletic BuildingPress BoxExistingNew Facilities703703Proposed Total11subtotal111111subtotal0Concessions BuildingPublic Amenity1subtotal1
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN56
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN 57PROGRAM SCHEMATIC DESIGN OF OPTION 4 & PARKING ANALYSIS
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN58
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN 59
ATHLETIC CHANGING FACILITY
CONCESSIONS STAND
PRESS BOX
PUBLIC AMENITY BUILDING
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN60
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN48NSMC 166 SPACESBERTRAM FIELDEXISTING: 54 SPACESPROPOSED: 49 SPACESJACKSON STREET8 DESIGNATED SPACESCOLLINS MIDDLE SCHOOL40 SPACES42 SPACESCOLLINS PARKING TABULATIONDESIGNATED PARKING SPACES JACKSON STREET PARKING LOT 08 COLLINS MIDDLE SCHOOL 82 BERTRAM FIELD 54 JACKSON STREET PARKING 45 TOTAL: 189POTENTIAL PARKING SPACES JACKSON STREET PARKING 05 BERTRAM FIELD -05 TOTAL: 00JACKSON STREETPOWDER HOUSE FIRE LANEHIGHLAND AVENUECOLLINS FIRE LANE - NO PARKINGPARKING ANALYSIS12-13-2018CITY OF SALEM, MACOLLINS FIRE LANE - NO PARKING
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN 49PARKING ANALYSIS - PHOTOSCITY OF SALEM, MAJACKSON STREET PARKING LOTPHOTO 1JACKSON STREET PARKINGPHOTO 2COLLINS MIDDLE SCHOOL FIRE LANEPHOTO 3POWDER HOUSE LANE PARKINGPHOTO 4
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN 61 COST ESTIMATE
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN62
Schematic Design Estimate
BERTRAM FIELD
IMPROVEMENTS PHASE II
Salem, MA
PM&C LLC Prepared for:
20 Downer Ave, Suite 1C
Hingham, MA 02043 Beacon Architectural Associates
(T) 781-740-8007
(F) 781-740-1012 July 18, 2018
BERTRAM FIELD
IMPROVEMENTS PHASE II 18-Jul-18
Salem, MA
Schematic Design Estimate
MAIN CONSTRUCTION COST SUMMARY
Construction
Start
Gross
Floor Area
$/sf Estimated
Construction Cost
SITE IMPROVEMENTS
Jul-19
2,540 $368.23 $935,313
2,925 $323.32 $945,703
600 $519.85 $311,908
1,400 $70.00 $98,000
1 LS $200,000
$853,589
SUB-TOTAL 7,465 $448.03 $3,344,513
4.0% $133,781
10% $334,451
SUB-TOTAL 7,465 $510.75 $3,812,745
$266,892
Incl
BONDS 1.00% $38,127
INSURANCE 1.40% $53,378
PERMIT Waived
OH+ Profit 5% $208,557
TOTAL OF ALL CONSTRUCTION 7,465 $586.70 $4,379,699
GENERAL CONDITIONS
GENERAL REQUIREMENTS
CONCESSIONS
PRESS BOX TO EXISTING GRANDSTAND
CHANGING FACILITY
TOILET BUILDING
SITEWORK
ESCALATION
DESIGN AND PRICING CONTINGENCY
METAL STORAGE SHED
Bertram Field Estimate 7.18.18 Page 2 PMC - Project Management Cost
BERTRAM FIELD
IMPROVEMENTS PHASE II 18-Jul-18
Salem, MA
Schematic Design Estimate
ITEMS NOT CONSIDERED IN THIS ESTIMATE
Items not included in this estimate are:
Land acquisition, feasibility, and financing costs
All professional fees and insurance
Site or existing conditions surveys investigations costs, including to determine
subsoil conditions
All Furnishings, Fixtures and Equipment
Items identified in the design as Not In Contract (NIC)
Items identified in the design as by others
Owner supplied and/or installed items as indicated in the estimate
Utility company back charges, including work required off-site
Work to City streets and sidewalks, (except as noted in this estimate)
Construction contingency (GMP Contingency is included)
Contaminated soils removal, other than defined
The estimate is based on prevailing wage rates for construction in this market and represents a reasonable opinion of cost. It is not a
prediction of the successful bid from a contractor as bids will vary due to fluctuating market conditions, errors and omissions,
proprietary specifications, lack or surplus of bidders, perception of risk, etc. Consequently the estimate is expected to fall within the
range of bids from a number of competitive contractors or subcontractors, however we do not warrant that bids or negotiated prices
will not vary from the final construction cost estimate.
This Schematic Design cost estimate was produced from drawings and narratives prepared by Beacon Architects Associates and
their design team dated June 14, 2018. Design and engineering changes occurring subsequent to the issue of these documents
have not been incorporated in this estimate.
This estimate includes all direct construction costs, general contractor’s overhead, fee and design contingency. Cost escalation
assumes start dates indicated.
Bidding conditions are expected to be public bidding under Chapter 149 of the Massachusetts General Laws to pre-qualified general
contractors, and pre-qualified sub-contractors, open specifications for materials and manufacturers.
Bertram Field Estimate 7.18.18 Page 3 PMC - Project Management Cost
BERTRAM FIELD 18-Jul-18
IMPROVEMENTS PHASE II
Salem, MA
Schematic Design Estimate
CONSTRUCTION COST SUMMARY
BUILDING SYSTEM TOILET CHANGING CONCESSIONS TOTAL
SITE IMPROVEMENTS
A10 FOUNDATIONS
A1010 Standard Foundations $53,789 $116,283 $23,249 $193,321
A1020 Special Foundations
A1030 Lowest Floor Construction $27,240 $31,494 $6,480 $65,214
B10 SUPERSTRUCTURE
B1010 Upper Floor Construction
B1020 Roof Construction $47,250 $54,060 $19,605 $120,915
B20 EXTERIOR CLOSURE
B2010 Exterior Walls $131,946 $154,165 $85,960 $372,071
B2020 Windows $6,210 $31,710 $630 $38,550
B2030 Exterior Doors $15,240 $22,360 $11,580 $49,180
B30 ROOFING
B3010 Roof Coverings $106,744 $124,940 $48,494 $280,178
B3020 Roof Openings
C10 INTERIOR CONSTRUCTION
C1010 Partitions $61,200 $63,470 $14,640 $139,310
C1020 Interior Doors $12,663 $4,221 $16,884
C1030 Specialties/Millwork $71,125 $39,391 $33,040 $143,556
C30 INTERIOR FINISHES
C3010 Wall Finishes $9,394 $12,338 $4,270 $26,002
C3020 Floor Finishes $3,201 $3,201 $725 $7,127
C3030 Ceiling Finishes $14,374 $31,478 $7,314 $53,166
D10 CONVEYING SYSTEMS
D1010 Elevator
D13 SPECIAL CONSTRUCTION
D1313 Special Construction
D20 PLUMBING
D20 Plumbing $209,800 $43,400 $21,700 $274,900
D30 HVAC
D30 HVAC $88,900 $102,375 $18,000 $209,275
D40 FIRE PROTECTION
D40 Fire Protection $0 $0 $0 $0
D50 ELECTRICAL
D5000 Electrical Systems $88,900 $102,375 $12,000 $203,275
TOTAL DIRECT COST (Trade Costs)$935,313 $945,703 $311,908 $2,192,924
Bertram Field Estimate 7.18.18 Page 4 PMC - Project Management Cost
BERTRAM FIELD 18-Jul-18
IMPROVEMENTS PHASE II
Salem, MA
Schematic Design Estimate GFA 2,540
CSI UNIT EST'D SUB TOTAL
CODE DESCRIPTION QTY UNIT COST COST TOTAL COST
TOILET BUILDING
1 GROSS FLOOR AREA CALCULATION
2
3 Toilet Building 2,540
4
5 TOTAL GROSS FLOOR AREA (GFA)2,540 sf
6
7
8 A10 FOUNDATIONS
9
10 A1010 STANDARD FOUNDATIONS
11
12 033000 CONCRETE
13 033000 Strip Footings to retaining wall; 3' wide x 12" deep
14 033000 Formwork 470 sf 12.00 5,640
15 033000 Re-bar 1,450 lbs. 1.32 1,914
16 033000 Concrete material; 3,000 psi 29 cy 132.00 3,828
17 033000 Placing concrete 29 cy 90.00 2,610
18 033000 Foundation wall; 16" thick
19 033000 Formwork 1,410 sf 14.00 19,740
20 033000 Re-bar 2,820 lbs. 1.32 3,722
21 033000 Concrete material; 3,000 psi 36 cy 132.00 4,752
22 033000 Placing concrete 36 cy 90.00 3,240
23
24 070001 WATERPROOFING, DAMPPROOFING AND CAULKING
25 070001 Dampproofing foundation wall and footing 1,410 sf 3.00 NR
26
27 072100 THERMAL INSULATION
28 072100 Insulation 1,410 sf 3.00 4,230
29
30 312000 EARTHWORK
31 Continuous footings
32 312000 Excavation 174 cy 10.00 1,740
33 312000 Store on site for reuse 174 cy 8.00 1,392
34 312000 Backfill with existing 109 cy 9.00 981
35 SUBTOTAL 53,789
36
37 A1020 SPECIAL FOUNDATIONS
38 No work in this section
39 SUBTOTAL
40
41 A1030 LOWEST FLOOR CONSTRUCTION
42
43 033000 CONCRETE
44 033000 New Slab on grade, 5" thick
45 033000 Rigid insulation 2,540 sf 2.25 5,715
46 033000 Vapor barrier 2,540 sf 1.00 2,540
47 033000 Mesh reinforcing 15% lap 2,921 sf 1.00 2,921
48 033000 Concrete - 5" thick; 4,000 psi 41 cy 125.00 5,125
49 033000 Placing concrete 41 cy 45.00 1,845
50 033000 Finishing and curing concrete 2,540 sf 1.50 3,810
51 033000 Control joints - saw cut 2,540 sf 0.10 254
52
53 312000 EARTHWORK
54 312000 Slab on grade
55 312000 Compacted gravel, 12"94 cy 40.00 3,760
56 312000 Compact existing sub-grade 2,540 sf 0.50 1,270
57 SUBTOTAL 27,240
58
59 TOTAL - FOUNDATIONS $81,029
60
61
62 B10 SUPERSTRUCTURE
Bertram Field Estimate 7.18.18 Page 5 PMC - Project Management Cost
BERTRAM FIELD 18-Jul-18
IMPROVEMENTS PHASE II
Salem, MA
Schematic Design Estimate GFA 2,540
CSI UNIT EST'D SUB TOTAL
CODE DESCRIPTION QTY UNIT COST COST TOTAL COST
TOILET BUILDING
63
64 B1020 ROOF CONSTRUCTION
65
66 061000 ROUGH CARPENTRY
67 61000 Engineered wood beams w/ steel posts 3,150 sf 15.00 47,250
68 SUBTOTAL 47,250
69
70 TOTAL - SUPERSTRUCTURE $47,250
71
72
73 B20 EXTERIOR CLOSURE
74
75 B2010 EXTERIOR WALLS 2,688 SF -
76
77 042000 MASONRY
78 040001 CMU, insulated, smooth face, 12", patterned/banding,
reinforced
2,210 sf 35.00 77,350
79 040001 Premium for Hall of Fame Display 86 sf 20.00 1,720
80 040001 Premium for signage/graphics 2 loc 1,000.00 2,000
81 040001 CMU back up at metal panel, insulated, 12",
reinforced
478 sf 28.00 13,384
82
83 052000 MISC. METALS
84 050001 Miscellaneous metals at CMU for lintels etc.2,688 sf 1.00 2,688
85
86 070001 WATERPROOFING, DAMPPROOFING AND CAULKING
87 070001 Air and vapor barrier 2,688 sf 5.00 NR
88 070001 AVB at window openings 63 lf 5.00 NR
89 070001 Miscellaneous sealants 2,688 sf 0.50 1,344
90
91 074200 WALL PANEL
92 074200 Insulated metal panel, Alucobond 478 sf 70.00 33,460
93 SUBTOTAL 131,946
94
95 B2020 WINDOWS 55 SF
96
97 061000 ROUGH CARPENTRY
98 061000 Wood blocking at openings 63 lf 11.00 693
99
100 070001 WATERPROOFING, DAMPPROOFING AND CAULKING
101 070001 Backer rod & double sealant 63 lf 9.00 567
102
103 080001 METAL WINDOWS 55 sf
104 080001 Clerestory 55 sf 90.00 4,950
105 SUBTOTAL 6,210
106
107 B2030 EXTERIOR DOORS
108
109 061000 ROUGH CARPENTRY
110 061000 Wood blocking at openings 102 lf 11.00 1,122
111
112 079200 JOINT SEALANTS
113 070001 Backer rod & double sealant 102 lf 9.00 918
114
115 081110 HOLLOW METAL
116 081113 HM door, frames and hardware - single 6 ea 2,000.00 12,000
117
118 090007 PAINTING
119 090007 Finish doors and frames 6 ea 200.00 1,200
120 SUBTOTAL 15,240
121
Bertram Field Estimate 7.18.18 Page 6 PMC - Project Management Cost
BERTRAM FIELD 18-Jul-18
IMPROVEMENTS PHASE II
Salem, MA
Schematic Design Estimate GFA 2,540
CSI UNIT EST'D SUB TOTAL
CODE DESCRIPTION QTY UNIT COST COST TOTAL COST
TOILET BUILDING
122 TOTAL - EXTERIOR CLOSURE $153,396
123
124
125 B30 ROOFING
126
127 B3010 ROOF COVERINGS
128
129 070002 ROOFING AND FLASHING
130 Sloped roofing
131 070002 Standing seam metal roof, insulated panel w/
perforated underside
2,340 sf 30.00 70,200
132 070002 Membrane roof 810 sf 18.00 14,580
133 Miscellaneous Roofing
134 070002 Metal fascia 221 lf 40.00 8,840
135 070002 Roof edge 170 lf 22.00 3,740
136 061000 Wood blocking at roof edge 1,564 lf 6.00 9,384
137 SUBTOTAL 106,744
138
139 TOTAL - ROOFING $106,744
140
141
142 C10 INTERIOR CONSTRUCTION
143
144 C1010 PARTITIONS
145
146 042000 MASONRY
147 040001 6" CMU 380 sf 23.00 8,740
148 040001 6" CMU, double plumbing chase 960 sf 46.00 44,160
149
150 055000 MISCELLANEOUS METALS
151 050001 Seismic clips 58 ea 120.00 6,960
152 050001 Misc. metals to CMU 1,340 sf 1.00 1,340
153 SUBTOTAL 61,200
154
155 C1030 SPECIALTIES / MILLWORK
156
157 070001 WATERPROOFING, DAMPPROOFING AND CAULKING
158 070001 Miscellaneous sealants throughout building 2,540 sf 1.25 3,175
159
160 102110 TOILET COMPARTMENTS
161 102100 ADA 4 ea 1,800.00 7,200
162 102100 Standard 32 ea 1,400.00 44,800
163 102100 Urinal screen 8 ea 650.00 5,200
164
165 102800 TOILET ACCESSORIES
166 102800 Gang bathroom 2 rms 5,000.00 10,000
167 102800 Individual bathroom 1 rm 750.00 750
168 SUBTOTAL 71,125
169
170 TOTAL - INTERIOR CONSTRUCTION $132,325
171
172
173 C30 INTERIOR FINISHES
174
175 C3010 WALL FINISHES
176
177 090007 PAINTING
178 090007 Epoxy paint to CMU 5,368 sf 1.75 9,394
179 SUBTOTAL 9,394
180
181 C3020 FLOOR FINISHES
182
Bertram Field Estimate 7.18.18 Page 7 PMC - Project Management Cost
BERTRAM FIELD 18-Jul-18
IMPROVEMENTS PHASE II
Salem, MA
Schematic Design Estimate GFA 2,540
CSI UNIT EST'D SUB TOTAL
CODE DESCRIPTION QTY UNIT COST COST TOTAL COST
TOILET BUILDING
183 033000 CONCRETE
184 033000 Sealed concrete 2,134 sf 1.50 3,201
185 SUBTOTAL 3,201
186
187 C3030 CEILING FINISHES
188
189 090007 PAINTING
190 090007 Paint to GWB ceilings 839 sf 1.00 839
191 090007 Paint to exposed structure 2,311 sf 1.50 3,467
192
193 092900 GYPSUM BOARD ASSEMBLIES
194 092900 GWB ceiling 839 sf 12.00 10,068
195 SUBTOTAL 14,374
196
197 TOTAL - INTERIOR FINISHES 26,969
198
199 D13 SPECIAL CONSTRUCTION
200
201 D1313 SPECIAL CONSTRUCTION
202 No work in this section
203 SUBTOTAL
204
205 TOTAL - SPECIAL CONSTRUCTION
206
207 D20 PLUMBING
208
209 D20 PLUMBING, GENERALLY
210
211 220000 PLUMBING
212 220000 Plumbing Fixtures & Specialties; includes all piping connections etc.
213 220000 Water closet 32 ea 3,200.00 102,400
214 220000 Water closet; handicap 5 ea 3,200.00 16,000
215 220000 Urinal 9 ea 3,100.00 27,900
216 220000 Lavatory; wall hung 20 ea 3,000.00 60,000
217 220000 Mechanical room sink 1 ea 3,500.00 3,500
218 SUBTOTAL 209,800
219
220 TOTAL - PLUMBING $209,800
221
222
223 D30 HVAC
224
225 D30 HVAC, GENERALLY
226 230000 HVAC allowance; VRF System 2,540 sf 35.00 88,900
227 SUBTOTAL 88,900
228
229 TOTAL - HVAC $88,900
230
231 D40 FIRE PROTECTION
232
233 D40 FIRE PROTECTION, GENERALLY
234 Fire Sprinkler system and misc accessories N.I.C.
235 SUBTOTAL -
236
237 TOTAL - FIRE PROTECTION
238
239
240 D50 ELECTRICAL
241
242 260000 ELECTRICAL
243 260000 Electrical systems allowance 2,540 sf 35.00 88,900
Bertram Field Estimate 7.18.18 Page 8 PMC - Project Management Cost
BERTRAM FIELD 18-Jul-18
IMPROVEMENTS PHASE II
Salem, MA
Schematic Design Estimate GFA 2,540
CSI UNIT EST'D SUB TOTAL
CODE DESCRIPTION QTY UNIT COST COST TOTAL COST
TOILET BUILDING
244 260000 SUBTOTAL 88,900
245
246 TOTAL - ELECTRICAL $88,900
247
Bertram Field Estimate 7.18.18 Page 9 PMC - Project Management Cost
BERTRAM FIELD 18-Jul-18
IMPROVEMENTS PHASE II
Salem, MA
Schematic Design Estimate GFA 2,925
CSI UNIT EST'D SUB TOTAL
CODE DESCRIPTION QTY UNIT COST COST TOTAL COST
CHANGING FACILITY
1 GROSS FLOOR AREA CALCULATION
2
3 Athletic Changing Facility 2,925
4
5 TOTAL GROSS FLOOR AREA (GFA)2,925 sf
6
7
8 A10 FOUNDATIONS
9
10 A1010 STANDARD FOUNDATIONS
11
12 033000 CONCRETE
13 033000 Strip Footings to retaining wall; 3' wide x 12" deep
14 033000 Formwork 520 sf 12.00 6,240
15 033000 Re-bar 1,600 lbs. 1.32 2,112
16 033000 Concrete material; 3,000 psi 32 cy 132.00 4,224
17 033000 Placing concrete 32 cy 90.00 2,880
18 033000 Foundation wall; 16" thick
19 033000 Formwork 1,260 sf 14.00 17,640
20 033000 Re-bar 2,520 lbs. 1.32 3,326
21 033000 Concrete material; 3,000 psi 33 cy 132.00 4,356
22 033000 Placing concrete 33 cy 90.00 2,970
23 033000 Retaining wall; 16" thick
24 033000 Formwork 1,400 sf 16.00 22,400
25 033000 Re-bar 2,800 lbs. 1.32 3,696
26 033000 Concrete material; 3,000 psi 36 cy 132.00 4,752
27 033000 Placing concrete 36 cy 90.00 3,240
28 033000 Strip Footings to exterior retaining wall; 3' wide x 12" deep
29 033000 Formwork 50 sf 12.00 600
30 033000 Re-bar 150 lbs. 1.32 198
31 033000 Concrete material; 3,000 psi 3 cy 132.00 396
32 033000 Placing concrete 3 cy 90.00 270
33 033000 Retaining wall; 16" thick
34 033000 Formwork 600 sf 16.00 9,600
35 033000 Re-bar 1,200 lbs. 1.32 1,584
36 033000 Concrete material; 3,000 psi 16 cy 132.00 2,112
37 033000 Placing concrete 16 cy 90.00 1,440
38 033000 Premium for formwork at exposed face 300 sf 10.00 3,000
39
40 070001 WATERPROOFING, DAMPPROOFING AND CAULKING
41 070001 Dampproofing foundation wall and footing 2,110 sf 3.00 NR
42 070001 Waterproofing at retaining wall and footing 800 sf 7.00 5,600
43
44 072100 THERMAL INSULATION
45 072100 Insulation 2,110 sf 3.00 6,330
46
47 312000 EARTHWORK
48 Continuous footings
49 312000 Excavation 311 cy 10.00 3,110
50 312000 Store on site for reuse 311 cy 8.00 2,488
51 312000 Backfill with existing 191 cy 9.00 1,719
52 SUBTOTAL 116,283
53
54 A1020 SPECIAL FOUNDATIONS
55 No work in this section
56 SUBTOTAL
57
58 A1030 LOWEST FLOOR CONSTRUCTION
59
60 033000 CONCRETE
61 033000 New Slab on grade, 5" thick
62 033000 Rigid insulation 2,925 sf 2.25 6,581
63 033000 Vapor barrier 2,925 sf 1.00 2,925
Bertram Field Estimate 7.18.18 Page 10 PMC - Project Management Cost
BERTRAM FIELD 18-Jul-18
IMPROVEMENTS PHASE II
Salem, MA
Schematic Design Estimate GFA 2,925
CSI UNIT EST'D SUB TOTAL
CODE DESCRIPTION QTY UNIT COST COST TOTAL COST
CHANGING FACILITY
64 033000 Mesh reinforcing 15% lap 3,364 sf 1.00 3,364
65 033000 Concrete - 5" thick; 4,000 psi 48 cy 125.00 6,000
66 033000 Placing concrete 48 cy 45.00 2,160
67 033000 Finishing and curing concrete 2,925 sf 1.50 4,388
68 033000 Control joints - saw cut 2,925 sf 0.10 293
69
70 312000 EARTHWORK
71 312000 Slab on grade
72 312000 Compacted gravel, 12"108 cy 40.00 4,320
73 312000 Compact existing sub-grade 2,925 sf 0.50 1,463
74 SUBTOTAL 31,494
75
76 TOTAL - FOUNDATIONS $147,777
77
78
79 B10 SUPERSTRUCTURE
80
81 B1020 ROOF CONSTRUCTION
82
83 061000 ROUGH CARPENTRY
84 61000 Engineered wood beams w/ steel posts 3,604 sf 15.00 54,060
85 SUBTOTAL 54,060
86
87 TOTAL - SUPERSTRUCTURE $54,060
88
89
90 B20 EXTERIOR CLOSURE
91
92 B2010 EXTERIOR WALLS 2,830 SF -
93
94 042000 MASONRY
95 040001 CMU, insulated, smooth face, 12", patterned/banding,
reinforced
2,050 sf 35.00 71,750
96 040001 CMU back up at metal panel, insulated, 12",
reinforced
780 sf 28.00 21,840
97
98 052000 MISC. METALS
99 050001 Miscellaneous metals at CMU for lintels etc.2,830 sf 1.50 4,245
100
101 070001 WATERPROOFING, DAMPPROOFING AND CAULKING
102 070001 Air and vapor barrier 2,830 sf 5.00 NR
103 070001 AVB at window openings 63 lf 5.00 315
104 070001 Miscellaneous sealants 2,830 sf 0.50 1,415
105
106 074200 WALL PANEL
107 074200 Insulated metal panel, Alucobond 780 sf 70.00 54,600
108 SUBTOTAL 154,165
109
110 B2020 WINDOWS 180 SF
111
112 061000 ROUGH CARPENTRY
113 061000 Wood blocking at openings 63 lf 11.00 693
114
115 070001 WATERPROOFING, DAMPPROOFING AND CAULKING
116 070001 Backer rod & double sealant 63 lf 9.00 567
117
118 080001 METAL WINDOWS 180 sf
119 080001 Windows 180 sf 90.00 16,200
120 080001 Premium for operable opening 57 ea 250.00 14,250
121 SUBTOTAL 31,710
122
Bertram Field Estimate 7.18.18 Page 11 PMC - Project Management Cost
BERTRAM FIELD 18-Jul-18
IMPROVEMENTS PHASE II
Salem, MA
Schematic Design Estimate GFA 2,925
CSI UNIT EST'D SUB TOTAL
CODE DESCRIPTION QTY UNIT COST COST TOTAL COST
CHANGING FACILITY
123 B2030 EXTERIOR DOORS
124
125 061000 ROUGH CARPENTRY
126 061000 Wood blocking at openings 144 lf 11.00 1,584
127
128 079200 JOINT SEALANTS
129 070001 Backer rod & double sealant 144 lf 9.00 1,296
130
131 081110 HOLLOW METAL
132 081113 HM door, frames and hardware - single 7 ea 2,000.00 14,000
133
134 083300 OVERHEAD DOORS
135 083400 OH coiling door, 8' x 8'-6"1 ea 4,080.00 4,080
136
137 090007 PAINTING
138 090007 Finish doors and frames 7 ea 200.00 1,400
139 SUBTOTAL 22,360
140
141 TOTAL - EXTERIOR CLOSURE $208,235
142
143
144 B30 ROOFING
145
146 B3010 ROOF COVERINGS
147
148 070002 ROOFING AND FLASHING
149 Sloped roofing
150 070002 Standing seam metal roof, insulated panel w/
perforated underside
2,829 sf 30.00 84,870
151 070002 Membrane roof 775 sf 18.00 13,950
152 Miscellaneous Roofing
153 070002 Metal fascia 250 lf 40.00 10,000
154 070002 Roof edge 220 lf 22.00 4,840
155 061000 Wood blocking at roof edge 1,880 lf 6.00 11,280
156 SUBTOTAL 124,940
157
158 TOTAL - ROOFING $124,940
159
160
161 C10 INTERIOR CONSTRUCTION
162
163 C1010 PARTITIONS
164
165 042000 MASONRY
166 040001 6" CMU 1,860 sf 23.00 42,780
167 040001 6" CMU, double plumbing chase 250 sf 46.00 11,500
168
169 055000 MISCELLANEOUS METALS
170 050001 Seismic clips 59 ea 120.00 7,080
171 050001 Misc. metals to CMU 2,110 sf 1.00 2,110
172 SUBTOTAL 63,470
173
174 C1020 INTERIOR DOORS
175
176 061000 ROUGH CARPENTRY
177 061000 Wood blocking at openings 102 lf 4.00 408
178
179 070001 WATERPROOFING, DAMPPROOFING AND CAULKING
180 070001 Backer rod & double sealant 102 lf 2.50 255
181
182 081110 DOORS AND FRAMES
183 081113 Door, frame and hardware 6 ea 1,800.00 10,800
Bertram Field Estimate 7.18.18 Page 12 PMC - Project Management Cost
BERTRAM FIELD 18-Jul-18
IMPROVEMENTS PHASE II
Salem, MA
Schematic Design Estimate GFA 2,925
CSI UNIT EST'D SUB TOTAL
CODE DESCRIPTION QTY UNIT COST COST TOTAL COST
CHANGING FACILITY
184
185 090007 PAINTING
186 090007 Finish doors and frames 6 ea 200.00 1,200
187 SUBTOTAL 12,663
188
189 C1030 SPECIALTIES / MILLWORK
190
191 064020 INTERIOR ARCHITECTURAL WOODWORK
192 064100 Locker room benches 175 lf 90.00 15,750
193 064100 Wood trim w/ coat hooks 175 lf 15.00 2,625
194
195
196 070001 WATERPROOFING, DAMPPROOFING AND CAULKING
197 070001 Miscellaneous sealants throughout building 2,925 sf 1.25 3,656
198
199 101100 VISUAL DISPLAY SURFACES
200 101100 Marker boards 72 sf 20.00 1,440
201
202 101400 SIGNAGE
203 101400 Room Signs 6 loc 120.00 720
204
205 102110 TOILET COMPARTMENTS
206 102100 ADA 2 ea 1,800.00 3,600
207 102100 Standard 2 ea 1,400.00 2,800
208 102100 Urinal screen 2 ea 650.00 1,300
209
210 102800 TOILET ACCESSORIES
211 102800 Gang bathroom 2 rms 3,000.00 6,000
212 102800 Individual bathroom 2 rm 750.00 1,500
213 SUBTOTAL 39,391
214
215 TOTAL - INTERIOR CONSTRUCTION $115,524
216
217
218 C30 INTERIOR FINISHES
219
220 C3010 WALL FINISHES
221
222 090007 PAINTING
223 090007 Epoxy paint to CMU 7,050 sf 1.75 12,338
224 SUBTOTAL 12,338
225
226 C3020 FLOOR FINISHES
227
228 033000 CONCRETE
229 033000 Sealed concrete 2,134 sf 1.50 3,201
230 SUBTOTAL 3,201
231
232 C3030 CEILING FINISHES
233
234 090007 PAINTING
235 090007 Paint to GWB ceilings 2,351 sf 1.00 2,351
236 090007 Paint to exposed structure - soffit 610 sf 1.50 915
237
238 092900 GYPSUM BOARD ASSEMBLIES
239 092900 GWB ceiling 2,351 sf 12.00 28,212
240 SUBTOTAL 31,478
241
242 TOTAL - INTERIOR FINISHES 47,017
243
244 D20 PLUMBING
245
Bertram Field Estimate 7.18.18 Page 13 PMC - Project Management Cost
BERTRAM FIELD 18-Jul-18
IMPROVEMENTS PHASE II
Salem, MA
Schematic Design Estimate GFA 2,925
CSI UNIT EST'D SUB TOTAL
CODE DESCRIPTION QTY UNIT COST COST TOTAL COST
CHANGING FACILITY
246 D20 PLUMBING, GENERALLY
247
248 220000 PLUMBING
249 220000 Plumbing Fixtures & Specialties; includes all piping connections etc.
250 220000 Water closet 2 ea 3,200.00 6,400
251 220000 Water closet; handicap 4 ea 3,200.00 12,800
252 220000 Urinal 2 ea 3,100.00 6,200
253 220000 Lavatory; wall hung 6 ea 3,000.00 18,000
254 SUBTOTAL 43,400
255
256 TOTAL - PLUMBING $43,400
257
258
259 D30 HVAC
260
261 D30 HVAC, GENERALLY
262 230000 HVAC allowance; VRF System 2,925 sf 35.00 102,375
263 SUBTOTAL 102,375
264
265 TOTAL - HVAC $102,375
266
267 D40 FIRE PROTECTION
268
269 D40 FIRE PROTECTION, GENERALLY
270 Fire Sprinkler system and misc accessories N.I.C.
271 SUBTOTAL -
272
273 TOTAL - FIRE PROTECTION
274
275
276 D50 ELECTRICAL
277
278 260000 ELECTRICAL
279 260000 Electrical systems allowance 2,925 sf 35.00 102,375
280 260000 SUBTOTAL 102,375
281
282 TOTAL - ELECTRICAL $102,375
Bertram Field Estimate 7.18.18 Page 14 PMC - Project Management Cost
BERTRAM FIELD 18-Jul-18
IMPROVEMENTS PHASE II
Salem, MA
Schematic Design Estimate GFA 600
CSI UNIT EST'D SUB TOTAL
CODE DESCRIPTION QTY UNIT COST COST TOTAL COST
CONCESSIONS
1 GROSS FLOOR AREA CALCULATION
2
3 Concessions 600
4
5 TOTAL GROSS FLOOR AREA (GFA)600 sf
6
7
8 A10 FOUNDATIONS
9
10 A1010 STANDARD FOUNDATIONS
11
12 033000 CONCRETE
13 033000 Strip Footings to retaining wall; 3' wide x 12" deep
14 033000 Formwork 212 sf 12.00 2,544
15 033000 Re-bar 650 lbs. 1.32 858
16 033000 Concrete material; 3,000 psi 13 cy 132.00 1,716
17 033000 Placing concrete 13 cy 90.00 1,170
18 033000 Foundation wall; 16" thick
19 033000 Formwork 636 sf 14.00 8,904
20 033000 Re-bar 1,272 lbs. 1.32 1,679
21 033000 Concrete material; 3,000 psi 16 cy 132.00 2,112
22 033000 Placing concrete 16 cy 90.00 1,440
23
24 070001 WATERPROOFING, DAMPPROOFING AND CAULKING
25 070001 Dampproofing foundation wall and footing 318 sf 3.00 NR
26
27 072100 THERMAL INSULATION
28 072100 Insulation 318 sf 3.00 954
29
30 312000 EARTHWORK
31 Continuous footings
32 312000 Excavation 79 cy 10.00 790
33 312000 Store on site for reuse 79 cy 8.00 632
34 312000 Backfill with existing 50 cy 9.00 450
35 SUBTOTAL 23,249
36
37 A1020 SPECIAL FOUNDATIONS
38 No work in this section
39 SUBTOTAL
40
41 A1030 LOWEST FLOOR CONSTRUCTION
42
43 033000 CONCRETE
44 033000 New Slab on grade, 5" thick
45 033000 Rigid insulation 600 sf 2.25 1,350
46 033000 Vapor barrier 600 sf 1.00 600
47 033000 Mesh reinforcing 15% lap 690 sf 1.00 690
48 033000 Concrete - 5" thick; 4,000 psi 10 cy 125.00 1,250
49 033000 Placing concrete 10 cy 45.00 450
50 033000 Finishing and curing concrete 600 sf 1.50 900
51 033000 Control joints - saw cut 600 sf 0.10 60
52
53 312000 EARTHWORK
54 312000 Slab on grade
55 312000 Compacted gravel, 12"22 cy 40.00 880
56 312000 Compact existing sub-grade 600 sf 0.50 300
57 SUBTOTAL 6,480
58
59 TOTAL - FOUNDATIONS $29,729
60
61
62 B10 SUPERSTRUCTURE
Bertram Field Estimate 7.18.18 Page 15 PMC - Project Management Cost
BERTRAM FIELD 18-Jul-18
IMPROVEMENTS PHASE II
Salem, MA
Schematic Design Estimate GFA 600
CSI UNIT EST'D SUB TOTAL
CODE DESCRIPTION QTY UNIT COST COST TOTAL COST
CONCESSIONS
63
64 B1020 ROOF CONSTRUCTION
65
66 061000 ROUGH CARPENTRY
67 61000 Engineered wood beams w/ steel posts 1,307 sf 15.00 19,605
68 SUBTOTAL 19,605
69
70 TOTAL - SUPERSTRUCTURE $19,605
71
72
73 B20 EXTERIOR CLOSURE
74
75 B2010 EXTERIOR WALLS 1,360 SF -
76
77 042000 MASONRY
78 040001 CMU, insulated, smooth face, 12", patterned/banding,
reinforced
1,060 sf 35.00 37,100
79 040001 CMU back up at metal panel, insulated, 12",
reinforced
300 sf 28.00 8,400
80 040001 Brick and backup at columns 360 sf 45.00 16,200
81
82 052000 MISC. METALS
83 050001 Miscellaneous metals at CMU for lintels etc.1,720 sf 1.50 2,580
84
85 070001 WATERPROOFING, DAMPPROOFING AND CAULKING
86 070001 Air and vapor barrier 1,360 sf 5.00 NR
87 070001 AVB at window openings 9 lf 5.00 NR
88 070001 Miscellaneous sealants 1,360 sf 0.50 680
89
90 074200 WALL PANEL
91 074200 Insulated metal panel, Alucobond 300 sf 70.00 21,000
92 SUBTOTAL 85,960
93
94 B2020 WINDOWS 5 SF
95
96 061000 ROUGH CARPENTRY
97 061000 Wood blocking at openings 9 lf 11.00 99
98
99 070001 WATERPROOFING, DAMPPROOFING AND CAULKING
100 070001 Backer rod & double sealant 9 lf 9.00 81
101
102 080001 METAL WINDOWS 5 sf
103 080001 Windows 5 sf 90.00 450
104 SUBTOTAL 630
105
106 B2030 EXTERIOR DOORS
107
108 061000 ROUGH CARPENTRY
109 061000 Wood blocking at openings 51 lf 11.00 561
110
111 079200 JOINT SEALANTS
112 070001 Backer rod & double sealant 51 lf 9.00 459
113
114 081110 HOLLOW METAL
115 081113 HM door, frames and hardware - single 3 ea 2,000.00 6,000
116
117 083300 OVERHEAD DOORS
118 083400 OH coiling counter doors, 6' x 3'-4"1 ea 1,188.00 1,188
119 083400 OH coiling counter doors, 14' x 3'-4"1 ea 2,772.00 2,772
120
121 090007 PAINTING
122 090007 Finish doors and frames 3 ea 200.00 600
Bertram Field Estimate 7.18.18 Page 16 PMC - Project Management Cost
BERTRAM FIELD 18-Jul-18
IMPROVEMENTS PHASE II
Salem, MA
Schematic Design Estimate GFA 600
CSI UNIT EST'D SUB TOTAL
CODE DESCRIPTION QTY UNIT COST COST TOTAL COST
CONCESSIONS
123 SUBTOTAL 11,580
124
125 TOTAL - EXTERIOR CLOSURE $98,170
126
127
128 B30 ROOFING
129
130 B3010 ROOF COVERINGS
131
132 070002 ROOFING AND FLASHING
133 Sloped roofing
134 070002 Standing seam metal roof, insulated panel w/
perforated underside
855 sf 30.00 25,650
135 070002 Membrane roof 452 sf 18.00 8,136
136 Miscellaneous Roofing
137 070002 Metal fascia 145 lf 40.00 5,800
138 070002 Roof edge 118 lf 22.00 2,596
139 061000 Wood blocking at roof edge 1,052 lf 6.00 6,312
140 SUBTOTAL 48,494
141
142 TOTAL - ROOFING $48,494
143
144
145 C10 INTERIOR CONSTRUCTION
146
147 C1010 PARTITIONS
148
149 042000 MASONRY
150 040001 6" CMU 540 sf 23.00 12,420
151
152 055000 MISCELLANEOUS METALS
153 050001 Seismic clips 14 ea 120.00 1,680
154 050001 Misc. metals to CMU 540 sf 1.00 540
155 SUBTOTAL 14,640
156
157 C1020 INTERIOR DOORS
158
159 061000 ROUGH CARPENTRY
160 061000 Wood blocking at openings 34 lf 4.00 136
161
162 070001 WATERPROOFING, DAMPPROOFING AND CAULKING
163 070001 Backer rod & double sealant 34 lf 2.50 85
164
165 081110 DOORS AND FRAMES
166 081113 Door, frame and hardware 2 ea 1,800.00 3,600
167
168 090007 PAINTING
169 090007 Finish doors and frames 2 ea 200.00 400
170 SUBTOTAL 4,221
171
172 C1030 SPECIALTIES / MILLWORK
173
174 064020 INTERIOR ARCHITECTURAL WOODWORK
175 064100 Base cabinet and countertop in Officials 5 lf 380.00 1,900
176 064100 16" wide stainless steel shelving, assume 5 rows 24 lf 300.00 7,200
177 064100 Stainless steel counter 33 lf 300.00 9,900
178 064100 Stainless steel counter, exterior 33 lf 300.00 9,900
179
180 070001 WATERPROOFING, DAMPPROOFING AND CAULKING
181 070001 Miscellaneous sealants throughout building 600 sf 1.25 750
182
Bertram Field Estimate 7.18.18 Page 17 PMC - Project Management Cost
BERTRAM FIELD 18-Jul-18
IMPROVEMENTS PHASE II
Salem, MA
Schematic Design Estimate GFA 600
CSI UNIT EST'D SUB TOTAL
CODE DESCRIPTION QTY UNIT COST COST TOTAL COST
CONCESSIONS
183 101400 SIGNAGE
184 101400 Room Signs 2 loc 120.00 240
185
186 102800 TOILET ACCESSORIES
187 102800 Individual bathroom 1 rm 750.00 750
188
189 105000 LOCKERS
190 105000 Full height lockers at custodian office; single tier - 15"
x 12"
6 ea 400.00 2,400
191 SUBTOTAL 33,040
192
193 TOTAL - INTERIOR CONSTRUCTION $51,901
194
195
196 C30 INTERIOR FINISHES
197
198 C3010 WALL FINISHES
199
200 090007 PAINTING
201 090007 Epoxy paint to CMU 2,440 sf 1.75 4,270
202 SUBTOTAL 4,270
203
204 C3020 FLOOR FINISHES
205
206 033000 CONCRETE
207 033000 Sealed concrete 483 sf 1.50 725
208 SUBTOTAL 725
209
210 C3030 CEILING FINISHES
211
212 090007 PAINTING
213 090007 Paint to GWB ceilings 483 sf 1.00 483
214 090007 Paint to exposed structure - soffit 690 sf 1.50 1,035
215
216 092900 GYPSUM BOARD ASSEMBLIES
217 092900 GWB ceiling 483 sf 12.00 5,796
218 SUBTOTAL 7,314
219
220 TOTAL - INTERIOR FINISHES 12,309
221
222 D20 PLUMBING
223
224 D20 PLUMBING, GENERALLY
225
226 220000 PLUMBING
227 220000 Plumbing Fixtures & Specialties
228 220000 Water closet 1 ea 3,200.00 3,200
229 220000 Lavatory; wall hung 1 ea 3,200.00 3,200
230 220000 Shower 1 ea 4,500.00 4,500
231 220000 Stainless steel sink 3 ea 3,600.00 10,800
232 SUBTOTAL 21,700
233
234 TOTAL - PLUMBING $21,700
235
236
237 D30 HVAC
238
239 D30 HVAC, GENERALLY
240 230000 HVAC allowance; VRF System 600 sf 30.00 18,000
241 SUBTOTAL 18,000
242
243 TOTAL - HVAC $18,000
Bertram Field Estimate 7.18.18 Page 18 PMC - Project Management Cost
BERTRAM FIELD 18-Jul-18
IMPROVEMENTS PHASE II
Salem, MA
Schematic Design Estimate GFA 600
CSI UNIT EST'D SUB TOTAL
CODE DESCRIPTION QTY UNIT COST COST TOTAL COST
CONCESSIONS
244
245 D40 FIRE PROTECTION
246
247 D40 FIRE PROTECTION, GENERALLY
248 Fire Sprinkler system and misc accessories N.I.C.
249 SUBTOTAL -
250
251 TOTAL - FIRE PROTECTION
252
253
254 D50 ELECTRICAL
255
256 260000 ELECTRICAL
257 260000 Electrical systems allowance 600 sf 20.00 12,000
258 260000 SUBTOTAL 12,000
259
TOTAL - ELECTRICAL $12,000
Bertram Field Estimate 7.18.18 Page 19 PMC - Project Management Cost
BERTRAM FIELD
IMPROVEMENTS PHASE II
Salem, MA
Schematic Design Estimate
CSI UNIT EST'D SUB TOTAL
CODE DESCRIPTION QTY UNIT COST COST TOTAL COST
SITEWORK
1
2 G SITEWORK
3
4 G10 SITE PREPARATION & DEMOLITION
5
6 311000 SITE PREPARATION & DEMOLITION
7 311000 Site construction fence/barricades
8 311000 Construction gates
9 311000 Construction entrance
10 311000 Saw cut and remove paving 33,300 sf 1.00 33,300
11 312000 Demolish existing Field House 3,325 sf 8.00 26,600
12
13 312000 EARTH MOVING
14 Site Earthwork
15 312000 Cut/Fill, assume balanced 1,356 cy 12.00 16,272
16 312000 Rock removal allowance 1 ls 50,000.00 50,000
17 312000 Fine grading 3,744 sy 1.00 3,744
18 Hazardous Waste Remediation
19 Dispose/treat contaminated soils/water NIC
20 SUBTOTAL 129,916
21
22 G20 SITE IMPROVEMENTS
23
24 BITUMINOUS PAVING
25 Asphalt Paving 14,200 sf
26 320000 gravel base; 12" thick 526 cy 38.80 20,409
27 320000 asphalt; 4.5" thick 1,578 sy 27.00 42,606
28 320000 premium for High Solar Reflective Index 16,424 sf 1.00 16,424
29 320000 Widen existing access road 1,000 sf 10.00 10,000
30 320000
31 320000 CONCRETE PAVING
32 320000 Concrete Paving
33 320000 gravel base; 8" thick 484 cy 38.80 18,779
34 320000 concrete; 4" thick 19,500 sf 6.50 126,750
35
36 CURBING
37 320000 Granite curb 700 lf 38.00 26,600
38 320000 HC curb cuts 1 loc 1,500.00 1,500
39
40 PAVEMENT MARKINGS
41 320000 Road markings 1 ls 2,500.00 2,500
42 320000 Single solid lines, 4" thick 49 space 25.00 1,225
43 320000 Wheelchair Parking 2 space 75.00 150
44
45 323000
46 323000 SITE IMPROVEMENTS
47 323000 Ticket booth 1 ea 15,000.00 15,000
48 323000 Field fence - assume existing ETR
49 323000 Fence at ticket booth 105 lf 60.00 6,300
50 323000 Gate, double 1 pr 1,600.00 1,600
51 323000 New 20' NSMC service gate 1 pr 3,500.00 3,500
52 323000 New 20' BAA service gate 1 pr 3,500.00 3,500
53
54 329200 TURF AND GRASSES
55 Lawn
56 329000 Topsoil - Import new topsoil; Av 6"37 cy 90.00 3,330
57 329000 Loam and seed 2,000 sf 0.30 600
58 329000 Tree 11 ea 1,200.00 13,200
59 SUBTOTAL 313,973
60
61 G30 CIVIL MECHANICAL UTILITIES
62
63 WATER UTILITIES
Bertram Field Estimate 7.18.18 Page 20 PMC - Project Management Cost
BERTRAM FIELD
IMPROVEMENTS PHASE II
Salem, MA
Schematic Design Estimate
CSI UNIT EST'D SUB TOTAL
CODE DESCRIPTION QTY UNIT COST COST TOTAL COST
SITEWORK
64 331000 Water to Toilet building 200 lf 120.00 24,000
65 331000 Water to Changing building 560 lf 150.00 84,000
66 331000 Water to Concessions building 200 lf 120.00 24,000
67
68 SANITARY SEWERAGE UTILITIES
69 331000 Sanitary to Toilet building 200 lf 90.00 18,000
70 331000 Sanitary to Changing building 560 lf 120.00 67,200
71 331000 Sanitary to Concessions building 200 lf 90.00 18,000
72
73 334000 STORM DRAINAGE UTILITIES
74 334000 New storm drainage systems 33,700 sf 3.00 101,100
75 334000
76 334000 Gas service - excavation and backfill only
77 334000 Gas to Toilet building 200 lf 22.00 4,400
78 334000 Gas to Changing building 560 lf 60.00 33,600
79 334000 Gas to Concessions building 200 lf 22.00 4,400
80 334000 Gas service by Utility
81 SUBTOTAL 378,700
82
83 G40 ELECTRICAL UTILITIES
84 260000 Utility company charges (allow) By Owner
85 260000 Connect to existing riser pole, Toilet building 1 ea 2,000.00 2,000
86 260000 Connect to existing riser pole, Changing 1 ea 10,000.00 10,000
87 260000 Connect to existing riser pole, Concessions 1 ea 2,000.00 2,000
88 260000 Connect to existing riser pole, Pressbox 1 ea 2,000.00 2,000
89 260000 Site lighting allowance 1 ea 15,000.00 15,000
90 SUBTOTAL 31,000
91
TOTAL - SITE DEVELOPMENT $853,589
Bertram Field Estimate 7.18.18 Page 21 PMC - Project Management Cost
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN 63COST ESTIMATEAPPENDIX
BERTRAM FIELD PHASE 2 RENOVATION SCHEMATIC DESIGN64
145 South Street, Third Floor, Boston, Massachusetts 02111
www.beaconarch.com | 617.357.7171
MEETING MINUTES
Meeting Minutes No. 1
Project Name: Bertram Field improvements phase 2
Project No.: 18-877
Project Location: Salem, Massachusetts
Date: 5-15--2018
Attendees:
☒ J. Michael Sullivan, Beacon
☒ Jenna Ide – City of Salem
☒ Michael E. Lutrzykowski – City of Salem Building
Inspector
☒ Michael Guida – Plumbing Inspector, City of Salem
☒ Paul L’Heureux – Salem School Department
☒ Ryan Monks – Salem School Department
The purpose of the meeting was to review the plumbing and toilet design proposed for the improvements to Bertram
Field, Salem Massachusetts.
Beacon Architectural reviewed the existing, code requirements, and the proposed toilet fixture count. See attached
programming information.
All parties agreed that a variance should be applied for.
Michael Guida offered to write a letter supporting the variance.
Beacon will apply for the variance as soon as possible.
We believe these minutes accurately reflect the discussion of this meeting. Please notify the author if there are any
comments, corrections, or additions within three (3) days of receipt.
Sincerely,
BEACON ARCHITECTURAL ASSOCIATES
J. Michael Sullivan
Attached: Space Criteria for Public Toilets
Bertram Field Improvements Phase 2
Criteria and Questions
March 5, 2018
BAA# 18-677 1
Space Criteria
Public Toilets
• Baby Changing Station
• Universal Accessibility
• Water efficient fixtures
• Waste Water
• Indoor Air Quality
Toilet Fixture Calculation based on a 5,000-seat grandstand ( existing).
Toilet Requirements based on 5,000 Spectators
2,500 men and 2,500 women
Fixture Existing Code Ratio Code
Requirement
Recommendations
with Variance
Men's Toilets 3 1 per 60 13 7
Men's Lavatories 6 1 per 150 17 9
Men's Urinals 4 50% of toilets 13 7
Women's Toilets 5 1 per 30 49 25
Women's Lavatories 6 1 per 150 17 9
The Commonwealth of Massachusetts Plumbing Code 248 CMR for A-5, Stadium occupancies
requires toilets at 1:30 females and 1:60 males for the first 2,000 occupants, above 2,000 the
fixture ratios increase to 1:100 women and 1:200 men.
Men’s Toilet/urinal
Calculation
occupants Code Ratio Code
Requirement
1000 60 16.67
1500 200 7.50
total 2,500 24.17
Bertram Field Improvements Phase 2
Criteria and Questions
March 5, 2018
BAA# 18-677 2
women Toilet Calculation occupants Code Ratio Code
Requirement
1000 30 33.33
1500 100 15.00
total 2,500 48.33
Based on a 4,000-seat grand stand :
Toilet Requirements based on 4,000 Spectators
2,000 men and 2,000 women
Fixture Existing Code Ratio Code
Requirement
Recommendations
with Variance (50%)
Men's Toilets 3 1 per 60 12 6
Men's Lavatories 6 1 per 150 8 4
Men's Urinals 4 50% of toilets 10 5
Women's Toilets 5 1 per 30 44 22
Women's Lavatories 6 1 per 150 8 8
Men’s Toilet/urinal
Calculation
occupants Code Ratio Code
Requirement
1000 60 16.67
1000 200 5.00
total 2,000 21.67
women Toilet
Calculation
occupants Code Ratio Code
Requirement
1000 30 33.33
1000 100 10.00
total 2,000 43.33
Project Goal:SilverY + ?Y:66Project Tracking:GoldY?Y?NN01001Integrative ProcessRequirements/EligibilityNotes11c1Integrative ProcessIdentify opportunities to achieve synergies across building systems and disciplines, throughout the design process. Perform simple-box energy modeling and water budget analysis in schematic design.Perform analysis during SD.088016Location and TransportationRequirements/EligibilityNotes1616c1LEED for Neighborhood Development LocationLocate project in a LEED ND location.Site is not in a LEED ND location.11c2Sensitive Land ProtectionLocate development footprint on previously developed land.Locate development away from farmland, floodplains, priority habitat, water bodies and wetlands.Land is previously developed.22c3High Priority SiteLocate development in a historic district or in an area with priority designation (1 pt), or on a brownfield (2 pt).Site is not in a historic district or on a brownfield.235c4Surrounding Density and Diverse UsesLocate project on a site whose surrounding existing density within a 1/4-mile radius meets requirements. (2-3 pt)Locate project within 1/2-mile of 4-8 diverse uses. (1-2 pt)325c5Access to Quality TransitLocate project within 1/4-mile of bus network or within 1/2 mile of rapid transit network.2 bus routes nearby. Need to determine if daily trips are frequent enough.11c6Bicycle FacilitiesProvide bike storage and shower facilities for users and locate project within 200 yards of a bicycle network.A bike network is planned near the site.11c7Reduced Parking FootprintDo not exceed code requirements for parking capacity.Provide a parking capacity reduction 20% below base ratios.Provide preferred parking for carpools for 5% of total spaces.11c8Green VehiclesDesignate 5% of all parking spaces as preferred for green vehicles.Provide EV charging or alternative fueling in 2% of parking spaces, in addition to preferred parking.064010Sustainable SitesRequirements/EligibilityNotesYReqp1Construction Activity Pollution PreventionImplement erosion & sedimentation control plan that conforms to EPA CGP.11c1Site AssessmentComplete a site assessment the surveys topography, hydrology, climate, vegetation, soils, human use & health effects.22c2Site Development - Protect or Restore HabitatRestore 30% of the previously developed portion of the site.Provide financial support to a land or conservation trust equivalent to at $0.40/sf site area.11c3Open Space30% of site area must be pedestrian- or recreation-focused open space. 25% of open space area must be vegetated (turf grass does not count).Consider garden of some sort to meet 25% requirement.213c4Rainwater ManagementUse LID to manage runoff onsite to 95th percentile (2 pt) or 98th percentile (3 pt).112c5Heat Island ReductionMeet minimum SRI requirements for all hardscape. (2 pt)Place 75% of parking under cover. (1 pt)11c6Light Pollution ReductionSelect site lighting that meets minimum BUG ratings.Field lighting is not exempted.RDK Engineers, an NV5 CompanyLEED v4 for BD+C: New Construction and Major Renovation04/18/18Salem, MABertram Field
056011Water EfficiencyRequirements/EligibilityNotesYReqp1Outdoor Water Use ReductionDo not install permanent irrigation, or reduce the landscape water requirement by 30% from calculated baseline.Must be achieved from plantings alone.YReqp2Indoor Water Use ReductionReduce aggregate water consumption by 20% from the baseline.Toilets, urinals and showerheads must be WaterSense labeled.YReqp3Building-Level Water MeteringInstall permanent whole-building & grounds water meter to measure consumption monthly & annually.Share whole-project water usage for 5 years.112c1Outdoor Water Use ReductionDo not install permanent irrigation, or reduce the landscape water requirement by 50% from calculated baseline.336c2Indoor Water Use Reduction1 point for every additional 5% reduction above prerequisite.22c3Cooling Tower Water UseConduct one-time potable water analysis to measure 5 identified parameters.Limit cooling tower cycles to avoid exceeding maximum parameter concentrations.No cooling tower anticipated.11c4Water MeteringInstall permanent water meters for two or more subsystems.Consider meters for irrigation & potable water use.02211033Energy and AtmosphereRequirements/EligibilityNotesYReqp1Fundamental Commissioning and VerificationHire CxA to perform fundamental commisioning activities.YReqp2Minimum Energy PerformanceDemonstrate 5% energy cost improvement compared with the 90.1-2010 Appendix G baseline building.Current building code is IECC 2015YReqp3Building-Level Energy MeteringInstall meters (utility meters are acceptable) that track building-level energy consumption.Share whole-project energy use with USGBC for 5 years.YReqp4Fundamental Refrigerant ManagementDo not use CFCs in HVAC or refrigeration.426c1Enhanced CommissioningHire independent CxA to perform enhanced commissioning activities.Three scopes of work: enhanced, monitoring-based and envelope.12618c2Optimize Energy Performance1 point for 6% energy cost improvement and increased points above that.Project has NZE goal.11c3Advanced Energy MeteringInstall permanent networked meters that track both consumption and demand hourly for all whole-building energy sources and any end use that represents 10% or more of the total annual consumption of the building.22c4Demand ResponseParticipate in qualifying utility DR program, or install equipment for eventual participation for DR program.33c5Renewable Energy ProductionInstall onsite renewable systems to meet a percentage of annual energy costs.Community solar is acceptable if a contract is signed for 10 years.Project has NZE goal.11c6Enhanced Refrigerant ManagementOnly use refrigerants that have ODP = 0 and GWP < 50.22c7Green Power and Carbon OffsetsPurchase carbon offsets or RECs to meet a percentage of annual energy costs.049013Materials and ResourcesRequirements/EligibilityNotesYReqp1Storage and Collection of RecyclablesProvide dedicated areas accessible to occupants and waste haulers for collection and storage of recyclables.YReqp2Construction and Demolition Waste Management PlanningDevelop and implement a construction and demolition waste management plan. Establish waste diversion goals for the project and describe divesion strategies.55c1Building Life-Cycle Impact ReductionRenovate historic building or reuse blighted building. (5 pt)Perform whole-building life cycle assessment and achieve 10% reduction compared to baseline building. (3 pt)112c2BPDO - Environmental Product DeclarationsUse at least 20 products from 5 manufacturers that meet disclosure criteria. (1 pt)Use products that comply with listed criteria for 50% by cost of all products on the project. (1 pt)112c3BPDO - Sourcing of Raw MaterialsUse at least 20 products from 5 manufacturers that publicly report raw material suppliers. (1 pt)Use products that comply with listed criteria for 25% by cost of all products on the project. (1 pt)22c4BPDO - Material Ingredients Use at least 20 products from 5 manufacturers that demonstrate chemical inventory to at least 1000 ppm. (1 pt)Use products that comply with listed criteria for 25% by cost of all products on the project. (1 pt)22c5Construction and Demolition Waste Management Divert 50% of materials and 3 material streams (1 pt) or divert 75% and four streams (2 pt)
0106016Indoor Environmental QualityRequirements/EligibilityNotesYReqp1Minimum Indoor Air Quality PerformanceMeet the requirements of ASHRAE Standard 62.1-2010.Provide outdoor air AFMS that alarms when OA varies by 15% or more from the setpoint.YReqp2Environmental Tobacco Smoke ControlProhibit smoking inside the building and within 25ft of entries, windows and air intakes. Include signage.22c1Enhanced Indoor Air Quality StrategiesInstall permanent entryway systems >10ft long at all regularly used exterior entrances.Negatively pressurize any spaces that may contain hazardous chemicals or gases, and provide self-closing doors and deck-to-deck partitions or a hard-lid ceiling.Provide MERV 13 filters on all ventilation systems.Monitor CO2 concentration in all densely occupied spaces.33c2Low-Emitting MaterialsMeet VOC level requirements paints, adhesives/sealants, flooring, ceilings & walls, and furniture.11c3Construction Indoor Air Quality Management PlanDevelop an IAQ management plan that addresses material storage, HVAC systems, and tobacco use.22c4Indoor Air Quality AssessmentPerform flush-out prior to occupancy or during occupancy.Conduct baseline IAQ testing after construction and before occupancy.11c5Thermal ComfortProvide personal thermal comfort controls for all building occupants, and design project to meet requirements of ASHRAE 55.-2010.112c6Interior LightingProvide individual lighting controls for occupants. (1 pt)Meet requirements for lighting quality. (1 pt)33c7DaylightPerform simulation to analyse spatial daylight autonomy.11c8Quality ViewsAchieve a direct line of sight to the outdoors for 75% of regularly occupied building floor area.11c9Acoustic PerformanceMeet requirements, as applicable, for HVAC background noise, sound isolation, reverberation time, and sound reinforcement and masking.Acoustic engineer required to confirm compliance.06006InnovationRequirements/EligibilityNotes11c1Innovation 11c2Innovation 11c3Innovation 11c4Innovation 11c5Innovation 11c6LEED Accredited ProfessionalHave a LEED AP work on the project.04204Regional PriorityRequirements/EligibilityNotes11c1Renewable Energy Productionpoint threshold: 211c2Optimize Energy Performancepoint threshold: 8113Building Life-Cycle Impact Reductionpoint threshold: 211c4Rainwater Managementpoint threshold: 211c5Cooling Tower Water Usepoint threshold: 211c6Indoor Water Use Reductionpoint threshold: 2066460110TOTALSCertified: 40 to 49 points, Silver: 50 to 59 points, Gold: 60 to 79 points, Platinum: 80 to 110 Can be achieved by pursuing Pilot credits, Innovation credits or by earning Exemplary Performance on project credits.Determine innovation strategies to pursue.
70 Fargo Street | Boston, MA 02210 | www.NV5.com | Office 617.345.9885 | Fax 617.345.4226
CONSTRUCTION QUALITY ASSURANCE - INFRASTRUCTURE - ENERGY - PROGRAM MANAGEMENT - ENVIRONMENTAL
MEMORANDUM
Date: June 11, 2018
To: J. M. Sullivan (BAA)
From: V. Rybl (RDK/NV5)
Subject: Captain John Bertram Field – LEED Discovery Phase Summary
Project No.: 20180118.00
The City of Salem (Owner) is interested in pursuing LEED certification for the new athletic facilities at Captain
John Bertram Field. RDK Engineers, an NV5 Company (RDK/NV5) has been contracted by the project
architect, Beacon Architectural Associates (BAA) to facilitate the LEED “Discovery Phase” of the project.
RDK/NV5 has met with BAA and Owner’s team to identify sustainability targets for the project, establish LEED
certification goals and to create a plan for achieving LEED certification.
RDK/NV5’s analysis of a path to LEED certification is based on the architectural schematic design (SD) site
plan and enlarged building drawings, dated May 23, 2018. The project consists of a changing facility,
concession stand, toilet building and press box totaling approximately 5,300 square feet (sf) of interior floor
area. The project has a net-zero annual energy use (NZE) goal. This goal may be achieved through installation
of a high-efficiency electric HVAC system to reduce energy demands and a solar PV system to provide onsite
generation.
The project has a goal of LEED Gold certification, which requires the project to achieve between 60 and 79
points. It is RDK/NV5’s recommendation that the project pursue certification under LEED for Building Design
and Construction, version 4 (LEED v4 BD+C). The BD+C rating system is designed for new construction
projects and addresses the environmental impact of building design, site design and construction activities.
Due to the decentralized nature of the project and multiple buildings onsite, the project should consider
pursuing LEED certification through a Campus approach.
The table below summarizes the results of RDK/NV5’s analysis with the expected number of points in each
LEED credit category that would need to be captured to achieve Gold certification. A detailed LEED scorecard,
including specific prerequisite and credit requirements, is provided with this memorandum.
CONSTRUCTION QUALITY ASSURANCE - INFRASTRUCTURE - ENERGY - PROGRAM MANAGEMENT - ENVIRONMENTAL
Category Design Features Yes Maybe No
Integrative Process Project will perform early-stage energy modeling and water
budget analysis to establish goals. 1 0 0
Location and
Transportation
Project is located in dense suburban area with some access
to nearby services via public transit and bicycle networks. 7 9 0
Sustainable Sites Project will utilize high-SRI* hardscape and LID** rainwater
management strategies. 7 3 0
Water Efficiency Project will utilize high-efficiency interior fixtures and will plant
native species to reduce irrigation water use. 4 5 2
Energy and
Atmosphere
Project has NZE goal and will pursue enhanced
commissioning tasks. 26 5 1
Materials and
Resources
Project will reduce material life-cycle impact and will divert
construction waste from landfill. 4 9 0
Indoor Environmental
Quality
Project will reduce interior VOC*** content, provide
mechanical ventilation and adequate lighting. 9 7 0
Innovation Project will pursue green building innovation strategies. 6 0 0
Regional Priority Project will attempt credits that address regional
environmental issues. 4 1 1
Total 68 39 4
* Solar Reflectance Index
** Low-Impact Development
***Volatile Organic Compound
At this time, Gold certification remains an attainable goal for the Bertram Field project. The majority of points
will result from achieving NZE. Further study is required to determine how building material selections and site
design will impact the certification. RDK/NV5 recommends pursuing a minimum of 70 points to allow for
potential point losses as part of the LEED review process.
RDK/NV5 recommends performing energy modeling to determine the project’s annual energy consumption
and to further evaluate the feasibility of achieving NZE. As the design progresses it is critical to continue to
engage all trades within the design team to ensure that LEED prerequisite and credit requirements are being
met.
SCHEMATIC DESIGN
MECHANICAL BASIS OF DESIGN
Bertram Field Improvements Phase 2
Salem, Massachusetts
June 1, 2018
Table of Contents
Section
1 Introduction and Project Overview
2 Plumbing Systems
3 HVAC Systems
1 Introduction and Project Overview
A. Introduction
This document describes the mechanical systems concepts for Bertram Field located in
Grafton, Massachusetts. This Schematic Design Narrative is prepared by Weston &
Sampson Engineers, Inc. and shall be used in conjunction with the Architectural, Civil,
Electrical, and Structural documents.
B. Narrative Overview
This narrative is a schematic level basis of design for the planning of the improvements
for the Bertram Field facility located in Salem, Massachusetts. This document includes
existing information and anticipated scope for the project as understood at the
Schematic Design level.
This document addresses systems to 10 feet outside the building. It does not address
site utilities (civil engineering), surface layout and finishes, grading, planting and
irrigation.
C. General
All systems will be designed in accordance with the Massachusetts State Building Code
9th edition (including the 2015 International Energy Conservation Code mandatory as of
January 1, 2018) and any local regulations.
This Basis of Design document is based upon the floor plans developed by Beacon
Architects.
2 Plumbing Systems
General
· Provide new domestic water service. Domestic water service shall be extended
from the city water main and enter the toilet building. A domestic water booster
pump will be required if available water pressure cannot support the demand for
the three buildings.
· Provide new backflow preventer, water meter, and remote meter reader. Water
meter and remote reader manufacturer and model number to be coordinated with
the City Water Department.
· New domestic cold, hot, and hot water return piping system will be provided
throughout the buildings. Isolation and drain valves shall be provided at the base of
each riser.
· Domestic hot water shall be generated via electric hot water heaters. Each building
shall feature its own electric hot water heater and distribution piping.
· Domestic water connections will be provided to all fixtures and equipment as
required.
· 120-degree F water shall be delivered throughout each building. Water temperature
at lavatories and showers shall be limited to a maximum 110 degrees F.
· Sanitary waste and vent branch connections will be provided for all plumbing
fixtures. All toilet room waste/vent stacks must be coordinated to avoid exposed
waste piping at the finished ceiling.
· Vent stacks shall start at the lowest level and exit the facility at the highest point of
elevation.
· A single sanitary main will collect all sanitary waste stacks, exit the facility at the
lowest level and discharge into City sanitary collection system. Any drains that
cannot drain by gravity to the City system will be drained to a sewage ejector and
pumped to the building sanitary drainage system.
· Floor drains shall be provided with automatic trap priming devices. Drains shall be
provided in the following areas: Toilet rooms, Changing rooms.
· Condensate discharge from HVAC equipment will be provided.
· Rain leaders / conductors to be provided as required.
Domestic Water Piping
· Domestic water piping shall be hard copper tube, Type L, ASTM B88 with pressure
fittings.
Sanitary and Vent Piping
· Aboveground, soil and waste piping NPS 4 (DN 100) and smaller shall be hubless
cast-iron soil pipe and fittings; heavy-duty shielded, stainless-steel couplings; and
hubless-coupling joints.
· Aboveground, soil and waste piping NPS 5 (DN 125) and larger shall be hubless cast-
iron soil pipe and fittings; heavy-duty shielded, stainless-steel couplings; and
hubless-coupling joints.
· Underground, soil, waste, and vent piping NPS 4 (DN 100) and smaller shall
be service class, cast-iron soil piping; gaskets; and gasketed joints.
· Underground, soil and waste piping NPS 5 (DN 125) and larger shall be service class,
cast-iron soil piping; gaskets; and compression joints.
· Aboveground sanitary-sewage force mains NPS 2-1/2 to NPS 6 (DN 65 to DN 150)
shall be steel pipe, pressure fittings, and threaded joints.
Storm Water Piping
· Aboveground, storm water piping NPS 4 (DN 100) and smaller shall be hubless cast-
iron soil pipe and fittings; heavy-duty shielded, stainless-steel couplings; and
hubless-coupling joints.
· Aboveground, storm water piping NPS 5 (DN 125) and larger shall be hubless cast-
iron soil pipe and fittings; heavy-duty shielded, stainless-steel couplings; and
hubless-coupling joints.
· Underground, storm water piping NPS 4 (DN 100) and smaller shall be service class,
cast-iron soil piping; gaskets; and gasketed joints.
· Underground, storm water piping NPS 5 (DN 125) and larger shall be service class,
cast-iron soil piping; gaskets; and compression joints.
· Aboveground storm water force mains NPS 2-1/2 to NPS 6 (DN 65 to DN 150) shall
be steel pipe, pressure fittings, and threaded joints.
Domestic Water Heaters
· Electric hot water heater.
· Acceptable Manufacturers: PVI, EEMAX, Chronomite.
· Piping distribution loop to include circulator, air separator, and expansion tank.
Valves
· Valves rated for and suitable for system temperature and pressures involved.
Domestic water pipes valves shall be:
· Size 2” and Less - Two-Piece, Copper-Alloy Ball Valves: Brass or bronze body
with full-port, chrome-plated bronze ball; PTFE or TFE seats; and 600-psig
(4140-kPa) minimum CWP rating and blowout-proof stem.
· Size 2-1/2” and Larger - Two Type 2, Class 125, 150, 200, Bronze Gate Valves:
Bronze body with rising stem and bronze solid wedge and union-ring bonnet.
System Service Valve Type
Domestic Water Shutoff Up to 2” Ball
2½” and Larger Gate
Hot Water Recirculation Balancing Calibrated Plug Valve
(Circuit Setter)
Natural gas NPS 2 and smaller Shutoff 2 piece full-port bronze ball valve
with bronze trim
Natural gas larger than NPS 2 Shutoff Cast iron lubricated plug valve
3 HVAC Systems
General:
Ventilation Requirements will be in accordance with IMC-2015, ASHARE 621. and
IECC-2015 as amended by 780 CMR 13. The minimum ventilation requirements
are as follows:
Space Classification OA
CFM/Person
OA CFM/SF Exhaust
CFM/SF
Changing Rooms 0.25
Toilet Rooms 50/70 per
fixture
Press Box 5 0.06
Training First Aid 5 0.06
High Efficiency Multizone Heat Pump System:
High efficiency multizone heat pumps shall serve each building for both heating and
cooling. Each room shall feature its own dedicated indoor unit. A wall mounted, recessed
ceiling cassette or floor standing cabinet heater will be provided as required based on room
configurations.
The recommended configuration will be to locate the outdoor units on the roof of each
building. These units shall be piped to the individual indoor evaporators located in the
respective spaces. Low ambient condensers shall not be required as field buildings shall not
be operational during winter months, the set point temperature during this period shall be
50°F (condensers shall not provide heat when temperatures are below -4°f, and will supply
65% capacity at 0°F).
Toilet Building:
The Men’s and Women’s restrooms will be provided heating and cooling by a high
efficiency multizone split system. The restrooms shall be ventilated by an energy recovery
ventilator capable of supplying 1,150 cfm to the Women’s restroom and 850 cfm to the
Men’s restroom. The ERV-1 shall be equipped with packaged-dx cooling and electric
heating coil to treat the incoming out door air. The restrooms shall also be equipped with
wall mount indoor evaporator units and multizone outdoor condensing unit to offset
building losses. ERV-1 shall be controlled via occupancy senor.
Changing Facility:
The changing facility shall be provided space heating and cooling by a high efficiency
multizone split system. Each area shall be provided a wall mount indoor evaporator. The
changing room building shall be ventilated by an energy recovery ventilator (ERV-2). ERV-2
shall be capable of exhausting 835 cfm. The energy recovery ventilator shall be controlled
via occupancy sensor and shall run post occupancy for 120 min (adj.). Storage room shall be
ventilated with a small exhaust fan, exhaust fan shall run continuously (50 cfm).
Concessions Building:
The concessions building shall be heated and cooled by a high efficiency multizone split
system. The officials room, storage room 2, concessions, and toilet area shall be ventilated
by an ERV-5 capable of providing 200 cfm. ERV-5 shall be controlled via occupancy sensor
and shall run for an additional 60 min post occupancy.
Press Box:
The press box shall be heated and cooled by a high efficiency split system. The press box
shall feature an indoor evaporator. The press box shall be heated to 50°(adj) during
unoccupied winter months.
Project Name:Bertram Field
Project Number:2180180
Comment:
5/31/2018 12:00:00 AM
Table of Contents
Quotation .......................................................................................1
Manually Inserted By Distributor
Unit Quantities .......................................................................................2
System Images .......................................................................................3
Centralized System - 1, Concession
Centralized System - 1, Mens Room
Centralized System - 1, Womens Room
Centralized System - 1, Changing Facility - Visitor
Centralized System - 1, Changing Facility - Home
Centralized System - 1, Press Box
Equipment Detailed Schedules .......................................................................................4
Outdoor Unit Schedules
Indoor Unit Schedules
Lossnay Unit Schedules
BC Controller Schedules
Input/Output Device Schedules
Equipment Submittals .......................................................................................5
Manually Attached Via Compile Project Documents Function
Quantities
Qty Model Description Price
16 stock controller Wireless remote controller Included with Indoor Unit
1 PAC-YT53CRAU-J Simple MA controller
2 PZ-43SMF-E Lossnay
1 MXZ-3C24NA2-U1 R410A MXZ Series Outdoor Unit
1 MXZ-3C30NA2-U1 R410A MXZ Series Outdoor Unit
1 MXZ-8C48NA-U1 R410A MXZ Series Outdoor Unit
2 MXZ-5C42NA2-U1 R410A MXZ Series Outdoor Unit
1 PUZ-A12NKA7 R410A P Series Outdoor Unit
1 MSZ-GL09NA-U1 Wall mounted type Indoor Unit
4 MSZ-GL06NA-U1 Wall mounted type Indoor Unit
6 MSZ-GL15NA-U1 Wall mounted type Indoor Unit
3 MSZ-GL18NA-U1 Wall mounted type Indoor Unit
2 MSZ-GL12NA-U1 Wall mounted type Indoor Unit
1 PKA-A12HA7 Wall mounted type Indoor Unit
1 LGH-F1200RX5-E1 Lossnay
1 LGH-F300RX5-E1 Lossnay
1 PAC-SC51KUA-J Power Supply
6 PAC-SC51KUA-J Power Supply Unit
1 ERV-1 PremiSys Unit
1 PAC-MKA31BC Branch Box
Refrigerant Piping Materials
Pipe Size
(inch)Total Length (feet) Number of Bends
1/4 0 0
3/8 0 0
1/2 0 0
5/8 0 0
5/31/2018 12:00:00 AM
Centralized System - 1 : Concession
Piping Diagram Image (Design View)
5/31/2018 12:00:00 AM
Centralized System - 1 : Concession
Piping Diagram Image(Piping View)
5/31/2018 12:00:00 AM
Centralized System - 1 : Mens Room
Piping Diagram Image (Design View)
5/31/2018 12:00:00 AM
Centralized System - 1 : Mens Room
Piping Diagram Image(Piping View)
5/31/2018 12:00:00 AM
Centralized System - 1 : Womens Room
Piping Diagram Image (Design View)
5/31/2018 12:00:00 AM
Centralized System - 1 : Womens Room
Piping Diagram Image(Piping View)
5/31/2018 12:00:00 AM
Centralized System - 1 : Changing Facility - Visitor
Piping Diagram Image (Design View)
5/31/2018 12:00:00 AM
Centralized System - 1 : Changing Facility - Visitor
Piping Diagram Image(Piping View)
5/31/2018 12:00:00 AM
Centralized System - 1 : Changing Facility - Home
Piping Diagram Image (Design View)
5/31/2018 12:00:00 AM
Centralized System - 1 : Changing Facility - Home
Piping Diagram Image(Piping View)
5/31/2018 12:00:00 AM
Centralized System - 1 : Press Box
Piping Diagram Image (Design View)
5/31/2018 12:00:00 AM
Centralized System - 1 : Press Box
Piping Diagram Image(Piping View)
Concession Mens Room Womens Room Changing Facility - Visitor Changing Facility - Home Press Box
ODU-A1 ODU-B1 ODU-C1 ODU-D1 ODU-E1 ODU-F1
M-Net Address N/A N/A N/A N/A N/A N/A
Model Number MXZ-3C24NA2-U1 MXZ-3C30NA2-U1 MXZ-8C48NA-U1 MXZ-5C42NA2-U1 MXZ-5C42NA2-U1 PUZ-A12NKA7
Modules
Nominal Cooling Capacity (BTU/h) 22,000.0 28,400.0 48,000.0 40,500.0 40,500.0 12,000.0
Nominal Heating Capacity (BTU/h) 25,000.0 28,600.0 54,000.0 45,000.0 45,000.0 14,000.0
Cooling Efficiency IEER/EER [SEER] [20(Non-Ducted), 18(Mix), 16(Ducted)] [19(Non-Ducted), 17.6(Mix), 16.2(Ducted)] [18.8999996185303] [19.7(Non-Ducted), 17.5(Mix), 15.2(Ducted)] [19.7(Non-Ducted), 17.5(Mix), 15.2(Ducted)] [20.8]
Heating COP @ 47°F [HSPF] [9.8(Non-Ducted), 9.5(Mix), 9.2(Ducted)] [10.6(Non-Ducted), 10.1(Mix), 9.6(Ducted)] [11.4] [10.3(Non-Ducted), 9.7(Mix), 9.1(Ducted)] [10.3(Non-Ducted), 9.7(Mix), 9.1(Ducted)] [10.2]
Nom System Connected Capacity (% of NOM) 87.5%100.0% 112.5% 114.3%114.3% 100.0%
Design Cooling Outdoor Temp DB (°F) 91.0 91.0 91.0 91.0 91.0 91.0
Design Heating Outdoor Temp WB (°F) 5.0 5.0 5.0 5.0 5.0 5.0
Max Pipe Length from BC or 1st Joint (feet) 0.0 0.0 0.0 0.0 0.0 0.0
Refrig Pipe Dim High/Low Pressure (inch) (See Note 4)1/4 / 1/2 1/4 / 3/8 3/8 / 5/8 0 / 0 0 / 0 1/4 / 1/2
Corrected Cooling Total Capacity (BTU/h) 22,354.4 28,857.6 48,940.2 41,152.5 41,152.5 12,279.0
Corrected Heating Capacity (BTU/h) 10,898.6 12,468.0 30,663.9 19,617.5 19,617.5 8,726.7
Sound Pressure (dBA) 51/55 52/56 51/54 56/58 56/58 44/46
Compressor Type
Compressor Quantity
Preliminary Added Field Charge (See Note 5)0.0 0.0 5.5 0.0 0.0 0.0
Voltage / Phase 208/230V / 1-phase 208/230V / 1-phase 208/230V / 1-phase 208/230V / 1-phase 208/230V / 1-phase 208/230V / 1-phase
MCA 208/230 or [460V]22.1 22.1 37 32.5 32.5 11
Recommended Fuse Size (RFS) 25 25 40 40 40 15
MOCP 25 25 52 40 40 28
Notes / OptionsApplicable System Notes - See Notes Below 1, 2, 3, 4, 5 1, 2, 3, 4, 5 1, 2, 3, 4, 5 1, 2, 3, 4, 5 1, 2, 3, 4, 5 1, 2, 3, 4, 5, 6
Notes & Options:
1
2
3
4
5
6
7Compressor DataElectrical DataMITSUBISHI CITY MULTI VRF OUTDOOR UNIT SCHEDULE
Include low ambient hood kit with associated wind baffles for 100% low ambient cooling down to minus (-) 10°F.
Corrected capacities shown are based on lowest guaranteed outdoor temperature, temperatures below this are not guaranteed.
Added field charge listed is in addition to factory charge, this must be updated based upon final as-built piping layout.
For systems with multiple modules, refrigerant pipe dimensions indicate total system combined piping downstream of module twinning.
Efficiency values for EER, IEER, COP are based on AHRI 1230 test method for mixture of ducted & non-ducted indoor units.
Nominal heating capacities are based on indoor coil EAT of 70°F (DB), outdoor of 43°F (WB)
Nominal cooling capacities are based on indoor coil EAT of 80/67°F (DB/WB), outdoor of 95°F (DB)
System Tag
Tag Reference
Nominal DataDesign ConditionsPerformance Data
Concession Concession Concession Mens Room Mens Room Womens Room Womens Room Womens Room Changing Facility - Visitor Changing Facility - Visitor Changing Facility - Visitor Changing Facility - Visitor Changing Facility - Home Changing Facility - Home Changing Facility - Home Changing Facility - Home Press Box
IDU-A1 IDU-A2 IDU-A3 IDU-B1 IDU-B2 IDU-C1 IDU-C2 IDU-C3 IDU-D1 IDU-D2 IDU-D3 IDU-D4 IDU-E1 IDU-E2 IDU-E3 IDU-E4 IDU-F1
Room Name Concession Storage Officials
M-Net Address N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A
Model MSZ-GL09NA-U1 MSZ-GL06NA-U1 MSZ-GL06NA-U1 MSZ-GL15NA-U1 MSZ-GL15NA-U1 MSZ-GL18NA-U1 MSZ-GL18NA-U1 MSZ-GL18NA-U1 MSZ-GL15NA-U1 MSZ-GL15NA-U1 MSZ-GL06NA-U1 MSZ-GL12NA-U1 MSZ-GL15NA-U1 MSZ-GL15NA-U1 MSZ-GL06NA-U1 MSZ-GL12NA-U1 PKA-A12HA7
Type Wall mounted type Wall mounted type Wall mounted type Wall mounted type Wall mounted type Wall mounted type Wall mounted type Wall mounted type Wall mounted type Wall mounted type Wall mounted type Wall mounted type Wall mounted type Wall mounted type Wall mounted type Wall mounted type Wall mounted type
Nominal Cooling Capacity (BTU/h) 9,000.0 6,000.0 6,000.0 13,600.0 13,600.0 16,000.0 16,000.0 16,000.0 11,600.0 11,600.0 5,000.0 9,900.0 11,600.0 11,600.0 5,000.0 9,900.0 12,000.0
Nominal Heating Capacity (BTU/h) 10,600.0 7,100.0 7,100.0 13,800.0 13,800.0 18,000.0 18,000.0 18,000.0 11,800.0 11,800.0 4,900.0 9,500.0 11,800.0 11,800.0 4,900.0 9,500.0 14,000.0
Cooling Design Entering Temp DB/WB (°F) / [Water in temp]80.0/67.0 80.0/67.0 80.0/67.0 80.0/67.0 80.0/67.0 80.0/67.0 80.0/67.0 80.0/67.0 80.0/67.0 80.0/67.0 80.0/67.0 80.0/67.0 80.0/67.0 80.0/67.0 80.0/67.0 80.0/67.0 80.0/67.0
Heating Design Entering Temp DB/WB (°F) / [Water in temp]70.0 70.0 70.0 70.0 70.0 70.0 70.0 70.0 70.0 70.0 70.0 70.0 70.0 70.0 70.0 70.0 70.0
Cooling Diversity Full/Partial (See Note 5, 6) FULL DEMAND FULL DEMAND FULL DEMAND FULL DEMAND FULL DEMAND FULL DEMAND FULL DEMAND FULL DEMAND FULL DEMAND FULL DEMAND FULL DEMAND FULL DEMAND FULL DEMAND FULL DEMAND FULL DEMAND FULL DEMAND FULL DEMAND
Heating Diversity Full/Partial (See Note 5, 6) FULL DEMAND FULL DEMAND FULL DEMAND FULL DEMAND FULL DEMAND FULL DEMAND FULL DEMAND FULL DEMAND FULL DEMAND FULL DEMAND FULL DEMAND FULL DEMAND FULL DEMAND FULL DEMAND FULL DEMAND FULL DEMAND FULL DEMAND
Refrig Pipe Dim Liquid/Suction (inch) 1/4 / 3/8 1/4 / 3/8 1/4 / 3/8 1/4 / 1/2 1/4 / 1/2 1/4 / 1/2 1/4 / 1/2 1/4 / 1/2 1/4 / 1/2 1/4 / 1/2 1/4 / 3/8 1/4 / 3/8 1/4 / 1/2 1/4 / 1/2 1/4 / 3/8 1/4 / 3/8 1/2 / 1/4
Cooling Total Capacity (BTU/h) 9,145.0 6,096.7 6,096.7 13,819.1 13,819.1 16,313.4 16,313.4 16,313.4 11,786.9 11,786.9 5,080.6 10,059.5 11,786.9 11,786.9 5,080.6 10,059.5 12,279.0
Cooling Sensible Capacity (BTU/h) 8,853.9 6,096.7 6,096.7 12,293.0 12,293.0 14,737.0 14,737.0 14,737.0 11,543.7 11,543.7 5,080.6 9,190.3 11,543.7 11,543.7 5,080.6 9,190.3 10,276.7
Heating Capacity (BTU/h) 4,621.0 3,095.2 3,095.2 6,016.0 6,016.0 10,221.3 10,221.3 10,221.3 5,144.1 5,144.1 2,136.1 4,141.5 5,144.1 5,144.1 2,136.1 4,141.5 8,726.7
Estimated Cooling Coil LAT (°F) / [LWT]59.4 65.8 65.8 58.2 58.2 58.5 58.5 58.5 59.5 59.5 68.2 58.6 59.5 59.5 68.2 58.6 57.2
Estimated Heating Coil LAT (°F) / [LWT]80.6 77.1 77.1 80.5 80.5 84.7 84.7 84.7 78.9 78.9 74.9 79.5 78.9 78.9 74.9 79.5 89.0
Peak Fan Airflow (cfm) / [Design gpm]406 406 406 533 533 646 646 646 533 533 406 406 533 533 406 406 425
Max Fan ESP Setting 208V/230V (IN WG)
Sound Pressure Per Fan Speed 208V/230V (dBA) 19-22-30-37-43/19-22-30-37-43 19-22-30-37-43/19-22-30-37-43 19-22-30-37-43/19-22-30-37-43 26-32-38-44-49/26-30-35-40-46 26-32-38-44-49/26-30-35-40-46 28-33-38-44-49/28-33-38-43-48 28-33-38-44-49/28-33-38-43-48 28-33-38-44-49/28-33-38-43-48 26-32-38-44-49/26-30-35-40-46 26-32-38-44-49/26-30-35-40-46 19-22-30-37-43/19-22-30-37-43 19-22-30-37-45/19-22-30-37-43 26-32-38-44-49/26-30-35-40-46 26-32-38-44-49/26-30-35-40-46 19-22-30-37-43/19-22-30-37-43 19-22-30-37-45/19-22-30-37-43 36 - 40 - 43
Voltage / Phase 208/230V/1-phase 208/230V/1-phase 208/230V/1-phase 208/230V/1-phase 208/230V/1-phase 208/230V/1-phase 208/230V/1-phase 208/230V/1-phase 208/230V/1-phase 208/230V/1-phase 208/230V/1-phase 208/230V/1-phase 208/230V/1-phase 208/230V/1-phase 208/230V/1-phase 208/230V/1-phase 208/230V/1-phase
Power Cooling 208V/230V (kW)1
Power Heating 208V/230V (kW)0.95
Electrical MCA/MFS Powered by Outdoor Powered by Outdoor Powered by Outdoor Powered by Outdoor Powered by Outdoor Powered by Outdoor Powered by Outdoor Powered by Outdoor Powered by Outdoor Powered by Outdoor Powered by Outdoor Powered by Outdoor Powered by Outdoor Powered by Outdoor Powered by Outdoor Powered by Outdoor Powered by Outdoor
Applicable System Notes - See Notes Below 1, 2, 3, 4, 5, 6 1, 2, 3, 4, 5, 6 1, 2, 3, 4, 5, 6 1, 2, 3, 4, 5, 6 1, 2, 3, 4, 5, 6 1, 2, 3, 4, 5, 6 1, 2, 3, 4, 5, 6 1, 2, 3, 4, 5, 6 1, 2, 3, 4, 5, 6 1, 2, 3, 4, 5, 6 1, 2, 3, 4, 5, 6 1, 2, 3, 4, 5, 6 1, 2, 3, 4, 5, 6 1, 2, 3, 4, 5, 6 1, 2, 3, 4, 5, 6 1, 2, 3, 4, 5, 6 1, 2, 3, 4, 5, 6
Notes & Options:
1
2
3
4
5
6Fan / Water Flow DataElectrical DataNotes / OptionsMITSUBISHI CITY MULTI VRF INDOOR UNIT SCHEDULE
It is recommended to always base heating corrected capacity on full demand.
Full demand corrected capacity includes de-rate associated with indoor vs. outdoor connected capacity indicated on outdoor unit schedule for associated system. Partial corrected capacity assumes sufficient diversity exists such that the connected capacity de-rate does not
apply. It is the designer's responsibility to ensure "Diamond System Builder" is set in the appropriate output capacity setting (full demand/partial demand) prior to generating this schedule.
See schematic piping/control diagram for indication of required indoor unit remote controllers, system controllers, and integration devices.
See outdoor unit schedule for outdoor ambient conditions, connected capacity, and other factors associated with corrected capacities
Nominal heating capacities are based on indoor coil EAT of 70°F (DB), outdoor of 43°F (WB)
Nominal cooling capacities are based on indoor coil EAT of 80/67°F (DB/WB), outdoor of 95°F (DB)
System Tag
Tag Reference
Nominal DataDesign ConditionsPerformance Data
LSN1 LSN2
LGH-F1200RX5-E1 LGH-F300RX5-E1
Stand-Alone Stand-Alone
1 2
Fixed Permeable Cross Plate Fixed Permeable Cross Plate
1200 300
0.75 0.78
Temperature Recovery 67.0% 65.5%
Enthalpy Cooling 50.0% 50.0%
Enthalpy Heating 64.0% 63.0%
208-230V/1-phase 208-230V/1-phase
7.1/15 1.7/15
1, 2, 3 1, 2, 3
Notes & Options:
1
2
3
Notes / Options
LOSSNAY ENERGY RECOVERY VENTILATOR
SCHEDULE
Washable factory standard pre-filter on return and O/A intake side of cross plate core.
See schematic piping/control diagram for indication of required lossnay local remote controller (stand alone operation) and M-Net connection points of associated systems.
Max external static pressure is at airflow listed with fan set on extra high speed.
Airflow (cfm)
Max ESP (INWG)
Nominal
Recovery
Effectiven
ess (Extra
High Fan
Speed)
Voltage / Phase
MCA / MOCP
Lossnay Tag
Model Number
Interlocked or Stand Alone
M-Net Address
Core Type
LSN1 LSN2 ERV-1
1 2
No No No
Yes Yes Yes
835 200 2000
835 200 2000
0 0 0
Dry Bulb Cooling (FDB) 79.5 79.6 80.0
Wet Bulb Cooling (FWB) 68.8 69.0 67.0
Dry Bulb Heating (FDB) 51.9 51.5 70.0
Dry Bulb Cooling (FDB)
Wet Bulb Cooling (FWB)
Dry Bulb Heating (FDB)
Model
Type
Airflow (CFM)
Mixed Air
Conditions
VENTILATION UNITS
Zone Airflow (CFM)
Indoor Unit Airflow (CFM)
Leaving
Air
Conditions
Served By Unit Tag
M-Net Address
Ventilation Unit Tag
M-Net Address
Serving IUs
Zone Supply
Supply Airflow (CFM)
M-Net Address
Model Number
Type (double / Main / Sub)
Number of Ports
Connected Capacity to BC
Voltage / Phase
Power Cooling 208V/230V (kW)
Power Heating 208V/230V (kW)
MCA 208/230
Notes / OptionsApplicable System Notes - See Notes Below
Notes & Options:
1
2 For sub BC controller CMB-P-NU-GB1 or -GB, the total connectable indoor unit capacity can be 126,000 BTUs or less. If two sub BC controllers are used, the total
indoor unit capacity connected to BOTH sub BC controllers also cannot exceed 126,000 BTUs. For sub BC controller CMB-P1016NU-HB1 the total connectable
indoor unit capacity can be 126,000 BTUs or less. However, if two sub controllers are used, and one of them is CMB-1016NU-HB1, the total indoor unit capacity
connected to BOTH sub controllers must NOT exceed 168,000 BTUs.
Include Diamondback Ball Valves BV-Series, 700PSIG working pressure, full port, 410A rated.
System Tag
Tag Reference
Nominal DataElectrical DataVRF HEAT RECOVERY BRANCH CIRCUIT
CONTROLLER
Womens Room
PAC-MKA31BC
3
208/230 / 1-phase
60
0.003
0.05
Galvanized Sheets
Width - in(mm) 17-23/32 (450)
Depth - in(mm) 11-1/32 (280)
Height - in(mm) 6-11/16 (170)
15 (6.7)
to ODU Liquid - in(mm) 3/8 (9.52)
to ODU Gas- in(mm) 5/8 (15.88)
to IDU Liquid - in(mm) 1/4 (6.35) x 3 {A, B, C}
to IDU Gas- in(mm) 3/8 (9.52) x 3 {A, B, C}
1
Notes & Options:
1Piping ConnectionNotes / Options
MXZ Branch Box
The piping connection size differs according to the type and capacity of indoor units. Match the piping connection size for indoor and branch box. If
the piping connection size of branch box does not match the piping connection size of indoor units, use optional different-diameter (deformed) joints
to the branch box side. (Connected deformed joint directly to the branch box side.)
Power Input - kW
Running Current - A
External Finish
Unit DimensionWeight - lb(kg)
System Tag
Model Number
Connectable number of Indoor unit
(Maximum)
Voltage / Phase
Frequency - Hz
AI Channel 1
AI Channel 2
AI Channel 3
AI Channel 4
PI Channel 1
PI Channel 2
DIDO Channel 1
DIDO Channel 2
DIDO Channel 3
DIDO Channel 4
Notes & Options:
1
Notes / Options
INPUT/OUTPUT DEVICE
SCHEDULE
See schematic piping/control diagram for indication of connection points and associated M-Net bus.
Device Type
M-Net Address
Model Number
Point DescriptionsPower Supply
SCHEMATIC DESIGN
STRUCTURAL BASIS OF DESIGN
Bertram Field Improvements Phase 2
Salem, Massachusetts
June 21, 2018
Table of Contents
Section
1 Project Overview and Code Requirements
2 Building Structures
3 Existing Grandstand and New Press Box
1 Project Overview and Code Requirements
A. Schematic Design Narrative Overview
The structural schematic design narrative has been developed for the Phase II
improvements to Bertram Field in Salem, Massachusetts. The narrative is based on
plans developed by Beacon Architectural Associates dated June 14, 2018.
The structural scope includes:
• New Toilet Building
• New Changing Facility
• New Concessions Building
• New Press Box, with ADA Ramp and Lift Access
• New Canopy Roof over Existing Grandstand (Project Alter nate)
The narrative was developed for schematic level planning and cost estimating.
Geotechnical information was not considered and will be necessary to advance the
design to bid or construction level documents.
B. Structural Code Requirements
• New structures will be designed in accordance with the Massachusetts State
Building Code 9th edition (i.e. the 2015 International Building Code (IBC) with
MA amendments). Work at the existing grandstand will be designed per the
2015 International Existing Building Code (IEBC) with MA amendments and ICC
300-2007 Standard for Bleachers, Folding and Telescopic Seating, and
Grandstands. Structures at Bertram Field will be considered Building Category
III. All exposed steel (both interior and exterior) will be hot-dipped galvanized.
The following load criteria will be used:
Dead Load:
Actual weight of framing and attached components.
Live Load:
Slabs-on-grade________________________100 psf
Grandstand___________________________100 psf *
Press Box_____________________________50 psf*
*Other loading requirements per ICC 300 Table 303.2 to be included
Snow Load:
Ground Snow Load, Pg__________________50 psf
Min. Flat Roof Snow Load, Pf____________30 psf
Exposure Factor, Ce___________________1.0
Thermal Factor, Ct____________________1.2
Importance Factor, Is__________________1.1
Wind Load:
Basic Wind Speed, Vult_________________127 mph
Exposure Category_____________________B
Seismic Load:
Ss_________________________________0.240
S1_________________________________0.073
Importance Factor, Ie_________________1.25
Site Class____________________________D (assumed)*
*Pending geotechnical investigation.
2 Building Structures
General
• Buildings are seasonal (i.e. will be closed in winter after football season and re -
opened in early spring).
• Buildings are assumed to have shallow foundations: reinforced concrete
foundations, piers, and footings. Concrete will have a minimum compressive
strength, f’c, of 4,000 psi. Vertical p erimeter rigid insulation is recommended
due to seasonal use to reduce potential frost damage.
• Slabs-on-grade will be 5-inches thick and reinforced with welded wire
reinforcing. Concrete will have a minimum compressive strength, f’c, of 3,000
psi. Under-slab rigid insulation for the entire area is recommended due to
seasonal use to reduce potential frost damage.
• Building bearing wall systems, except for the press box, will be a pre-insulated
concrete masonry product such as Korfil Hi-R and Hi-R H. Reinforcing is similar
to conventional concrete masonry construction. The minimum load-bearing
masonry wall width is 10 inches.
• Wood exposed to weather will be preservative treated. Connection materials,
both interior and exterior, will be hot -dipped galvanized, zinc-coated galvanized
Type G185, or stainless steel.
• Structural steel, both interior and exterior, will be hot-dipped galvanized.
Toilet Building
• The Toilet Building is a one-story structure. The roof framing will consist of sawn
and engineered lumber with plywood sheathing. The roof framing will bear on
pre-insulated reinforced concrete masonry wall. Interior bearing lines will be
engineered wood beams and steel posts (HSS4x4). Interior non -loadbearing
concrete masonry partition will be reinforced and have a 6-inch minimum width
and be anchored to the roof diaphragm.
Changing Facility
• The Concessions Building is a one-story structure. The roof framing will consist
of sawn and engineered lumber with plywood sheathing. The roof framing will
bear on pre-insulated reinforced concrete masonry wall. Interior bearing lines
will be engineered wood beams and steel posts (HSS4x4). Interior non -
loadbearing concrete masonry partition will be reinforced and have a 6-inch
minimum width and be anchored to the roof diaphragm.
Concessions Building
• The Concessions Building is a one-story structure. The roof framing will consist
of sawn and engineered lumber with plywood sheathing. Alternatively, the
sloped roof sheathing can be pre-fabricated wood trusses. The roof framing will
bear on pre-insulated reinforced concrete masonry wall. Interior bearing lines
will be engineered wood beams and steel posts (HSS4x4). Interior non -
loadbearing concrete masonry partition will be reinforced and have a 6-inch
minimum width and be anchored to the roof diaphragm.
3 Existing Grandstand and New Press Box
A new press box is proposed at the existing grandstand. Note that modifying the
existing grandstand to accommodate the new press box will require analyzing the
existing structure and providing upgrades to meet the current code requirements. At a
minimum modification and/or reinforcing will be required adjacent to the new press
box structure.
The new press box will be a conventional wood -framed or cold-formed steel structure
supported on a hot-dipped galvanized structural steel lattice frame. Access to the
ramp will be provided by stairs from the top of the existing grandstand or by an ADA
compliant ramp and lift. The ramp will be steel-framed. Steel will be hot-dipped
galvanized. The lift will be a pre-fabricated assembly including the shaft walls. Steel
exposed to weather will be hot-dipped galvanized. New grandstand structures will bear
on reinforced concrete shallow foundations (pending the geotechnical evaluation).
The canopy alternate will shelter the grandstand in front of the new press box. The
canopy will be constructed in hot-dipped galvanized structural steel. Columns will be 8-
inch diameter steel pipes founded on reinforced concrete piers and footing s. Wind
uplift forces will be a significant factor in the canopy design. Note that portions of the
existing grandstand will need to be removed and reassembled to construct the canopy
framing and foundations.
OPTION ‘B’:
NEW 12” PVC TO
NEW OUTLET POINT
AT WOODED SLOPE
DOUBLE-CB
AT LOW POINT
W/ HOODED OUTLET OIL
AND WATER SEPARATION
AND DEEP-SUMP
OPTION ‘A’:
NEW 12” PVC TO EXIST.
OUTLET POINT
BERTRAM FIELD, SALEM, MA
SCHEMATIC STORMWATER
N
145 South Street, Third Floor, Boston, Massachusetts 02111
www.beaconarch.com | 617.357.7171
Operations and Maintenance Recommendations
This report recommends the following strategy for the Operations and Maintancence of Bertram Field.
In summary; Heating and Air conditioning will be provided by electricity to the Public Amenities, Concession
and Changing Facility. It is anticipated the facilities will shut down for period from December to March. A
small family changing area will be heated during those times to provide facilities to the limited public year
round. The electrical cost is estimated to be between $1,500 and$2,000 dollars yearly for all the buildings.
Water will also be shut down during the winter months except to the family room.
Goal 1. Provide coordinated management and supervision with the City through regular meetings with
users and selected departments within city government.
The management of Bertram Field is currently the responsibility of the Salem School Facility Department. The
scheduling, determination of fees and the concession stands are duties shared between the Department of
Public Works, Department of Public Safety, and the School Department.
The operational responsibilities of Bertram Field need to be clearly defined by the City of Salem. The
maintenance of the facility, scheduling of events, administering revenue, and monitoring the use of the
concession’s facilities are specific base line responsibilities which need to be discussed and assigned as soon
as possible.
It is important one entity be responsible for supervising the operations and scheduling of Bertram Field.
Other towns we have visited assign this responsibility to either the Parks and Recreation Department or the
Community Development office. An individual will be designated to monitor the operations of the field on a
daily basis. This is not a full-time responsibility, rather 10 to 15 percent of this person’s time should be
allocated to Bertram Field.
Goal 2. Determine the scheduling of events and the hours of operations.
The Department of Parks and Recreation should schedule all events at the field. It is
recommended that a web-based calendar be available to confirm the event time is known to all
users.
The park should not be open 24 hours, 7 days a week. Typically, facilities in neighboring
communities are open from 6:00 a.m. till dusk, unless there are scheduled evening events.
Goal 3. Establish a capital improvement fund and seek resources through user’s fees, grants,
and other.
The City of Salem budget for the DPR should establish a dollar amount for the DPR to manage
with. This will define the financing of maintenance and upkeep. To supplement the budget, the
DPR should see alternative resources for capital improvements and major equipment
replacement such as grants and private corporate donations.
Setting fees for the use of the field should be considered. The concessions and ticket sales
should be managed by the DPR and the revenues from each can be shared with the respective
users.
Goal 4. Coordinate necessary improvements, repairs and upkeep.
The Department of Public Works or the parks department should be in charge with the maintenance of the
field, the buildings and the capital improvements associated with the overall facility.
A committee of users and representatives of city departments will be assembled to assist
and monitor specific areas of operations. Suggested participants (not to exceed 8 members)
of this committee are:
• Salem High School Athletic Director
• Salem High School Field Coaches
• Representatives from the Department
of Public Works
• Representatives from the Parks and
Recreation Department
• Representative from the Youth Sports
programs
Goal 5. Measure success by surveying visitors and users. Modify the operations as needed to always
be sensitive to the community’s expectations.
Monitoring the opinions of users and visitors establishes a good metric with which to decide
how to improve the care of Bertram Field. The survey should be done at the end of the fall
season.
145 South Street, Third Floor, Boston, Massachusetts 02111
www.beaconarch.com | 617.357.7171
Municipal and State Agencies to be included in the design review of
the Bertram Field Renovations
The following agencies and/or departments have reviewed the schematic design for Phase 2 of the Bertram
Field Renovations.
• City of Salem School Department
• City of Salem Plumbing Department
• City of Salem Fire Department
• City of Salem Police Department
• City of Salem School Committee Sub Committee on Parking
• City of Salem Parks and Recreation Department
• City of Salem Conservation and Preservation Authority
• City of Salem Public Health Department
• Commonwealth of Massachusetts Board of Gas Fitters and Plumbers
The following agencies will be involved in the Design Development for Phase 2 of the Bertram Field
Renovations.
• City of Salem School Department
• City of Salem Public Works Department
• City of Salem Engineering department
• City of Salem Parking Department
The City of Salem Conservation Commission has been notified about the project, and have indicated they do
not have to review the design.