Salem Intermodal Station Public Meeting - November 13, 2012Salem Station Improvements and Parking Garage, Bridge Street, Salem, MA
Public Meeting- Project Update November 13, 2012
SALEM INTERMODAL STATION
November 13, 2012
Public Meeting
Salem Station Improvements and Parking Garage, Bridge Street, Salem, MA
Public Meeting- Project Update November 13, 2012
NOVEMBER 13, 2012 PUBLIC DESIGN PRESENTATION
Purpose of Feb 16 discussion: input on project function & features
Purpose of April 9 discussion: input on building design strategies
Purpose of June 26 discussion: input on suggested design proposal
Purpose of tonights discussion: input on refined design proposal
Salem Station Improvements and Parking Garage, Bridge Street, Salem, MA
Public Meeting- Project Update November 13, 2012
•Progress update
•Design refinements
•Looking ahead
Discussion Topics:
Salem Station Improvements and Parking Garage, Bridge Street, Salem, MA
Public Meeting- Project Update November 13, 2012
Fall/Winter 2011: Subsurface investigations
Feb 16, 2012: Initial public meeting - planning
April 9, 2012: Second public meeting – design strategies
June 26, 2012: Third public meeting – 30% design
Design Progress:
Salem Station Improvements and Parking Garage, Bridge Street, Salem, MA
Public Meeting- Project Update November 13, 2012
Fall/Winter 2011: Subsurface investigations
Feb 16, 2012: Initial public meeting - planning
April 9, 2012: Second public meeting – design strategies
June 26, 2012: Third public meeting – 30% design
o November 2012: Fourth public meeting – 60% design
o March 2013: Fifth public meeting – 90% design
o Late Spring 2013: 100% design, construction begins
Design Progress:
Salem Station Improvements and Parking Garage, Bridge Street, Salem, MA
Public Meeting- Project Update November 13, 2012
June 15, 2012: MEPA EENF filing
June 28, 2012: MEPA public meeting
August 2012: MEPA EIR waiver granted
MEPA process complete
Permitting Progress:
Salem Station Improvements and Parking Garage, Bridge Street, Salem, MA
Public Meeting- Project Update November 13, 2012
June 15, 2012: MEPA EENF filing
June 28, 2012: MEPA public meeting
August 2012: MEPA EIR waiver granted
October 11, 2012: Chapter 91 public meeting
November 8, 2012: Chapter 91 public comment period closed
o Winter 2012-13: Chapter 91 comment review & response
October 25, 2012 Archeology permit received
o December 2012: Archeology fieldwork scheduled for completion
o Winter 2012-13: Salem Conservation Commission filing & review
o Winter 2013-13: MA Historic – signal tower rehab. review
Permitting Progress:
Salem Station Improvements and Parking Garage, Bridge Street, Salem, MA
Public Meeting- Project Update November 13, 2012
November 9, 2012: Construction Manager selected –
Welcome to the team, Consigli Construction!
Construction Progress:
Salem Station Improvements and Parking Garage, Bridge Street, Salem, MA
Public Meeting- Project Update November 13, 2012
November 9, 2012: Construction Manager selected –
Welcome to the team, Consigli Construction!
November 5, 2012: Archeological excavation commences
o December 2012: Archeology fieldwork scheduled for completion
Construction Progress:
Salem Station Improvements and Parking Garage, Bridge Street, Salem, MA
Public Meeting- Project Update November 13, 2012
November 9, 2012: Construction Manager selected –
Welcome to the team, Consigli Construction!
November 5, 2012: Archeological excavation commences
o December 2012: Archeology fieldwork complete
o Winter 2012-13: Construction phasing plan development
o *March 2013* *Public meeting – construction phasing*
o Spring 2013: Preparation of alternative parking lot
o May-June 2013: New temporary traffic patterns in effect
o Early summer 2013: Construction start
o Fall 2014: Substantial completion, garage & station open
o Winter 2014-15: Final completion, project complete
Construction Progress:
Salem Station Improvements and Parking Garage, Bridge Street, Salem, MA
Public Meeting- Project Update November 13, 2012
Design refinement
•Waiting area
•Exterior expression
•Subsurface conditions
Salem Station Improvements and Parking Garage, Bridge Street, Salem, MA
Public Meeting- Project Update November 13, 2012
Site plan – PRIMARY FUNCTIONAL ELEMENTS
Project overview
KISS & RIDE TRAFFIC
BUS TRAFFIC
GARAGE TRAFFIC
BICYCLE TRAFFIC
PEDESTRIAN TRAFFIC
Salem Station Improvements and Parking Garage, Bridge Street, Salem, MA
Public Meeting- Project Update November 13, 2012
Waiting areas
Original design June 2012
Developed design Sept 2012
Salem Station Improvements and Parking Garage, Bridge Street, Salem, MA
Public Meeting- Project Update November 13, 2012
Enlarged plans
GROUND FLOOR PLAN
2ND FLOOR PLAN
(upper floors sim.)
LEVEL CARS TOTAL
G 99 99
2ND 161 260
3RD 162 422
4TH 159 581
5TH 108 689
CAR COUNT TABLE
CIRCULATION DIAGRAM
TARGETED TOTAL PARKING SPACES: 700
Salem Station Improvements and Parking Garage, Bridge Street, Salem, MA
Public Meeting- Project Update November 13, 2012
Enlarged plans - WAITING AREA
GROUND FLOOR PLAN
2ND FLOOR PLAN 3RD, 4TH, 5TH FLOOR PLAN
Salem Station Improvements and Parking Garage, Bridge Street, Salem, MA
Public Meeting- Project Update November 13, 2012
Project schedule
Salem Station Improvements and Parking Garage, Bridge Street, Salem, MA
Public Meeting- Project Update November 13, 2012
Enlarged plans - WAITING AREA
GROUND FLOOR PLAN
2ND FLOOR PLAN
3RD, 4TH, 5TH FLOOR PLAN
Salem Station Improvements and Parking Garage, Bridge Street, Salem, MA
Public Meeting- Project Update November 13, 2012
Project schedule
Salem Station Improvements and Parking Garage, Bridge Street, Salem, MA
Public Meeting- Project Update November 13, 2012
Project schedule
Salem Station Improvements and Parking Garage, Bridge Street, Salem, MA
Public Meeting- Project Update November 13, 2012
Project schedule
Salem Station Improvements and Parking Garage, Bridge Street, Salem, MA
Public Meeting- Project Update November 13, 2012
Project schedule
Salem Station Improvements and Parking Garage, Bridge Street, Salem, MA
Public Meeting- Project Update November 13, 2012
Project schedule
Salem Station Improvements and Parking Garage, Bridge Street, Salem, MA
Public Meeting- Project Update November 13, 2012
Project schedule
Salem Station Improvements and Parking Garage, Bridge Street, Salem, MA
Public Meeting- Project Update November 13, 2012
Looking ahead
•Next public meeting March 2013
–90% design
–Phasing during construction
•Permitting continues this winter
•Challenges remain
–Subsurface conditions
–Temporary inconveniences during construction
•On-track for early-summer 2013 construction start