GROVE STREET ROADWORK - MACK PARK NEIGHBORHOOD ASSOCIATION PRESENTATIONGrove Street
City of Salem, Massachusetts
MassWorks
Infrastructure
Grant Program
City of Salem, Massachusetts
Kimberley Driscoll, Mayor
Department of Planning & Community Development
Engineering Department
Mack Park Neighborhood Presentation
April 8, 2014
Local Context – Grove St
City of Salem, Massachusetts
Kimberley Driscoll, Mayor
Department of Planning & Community Development
Engineering Department
Mack Park Neighborhood Presentation
April 8, 2014
Grove St Area - New Developments
Mack Park Neighborhood Presentation
April 8, 2014
Grove St - 100 Yr Flood Plain Areas
City of Salem, Massachusetts
Kimberley Driscoll, Mayor
Department of Planning & Community Development
Engineering Department
Mack Park Neighborhood Presentation
April 8, 2014
Grove St – Nearby Transit System
City of Salem, Massachusetts
Kimberley Driscoll, Mayor
Department of Planning & Community Development
Engineering Department
Mack Park Neighborhood Presentation
April 8, 2014
Gateway
Center Site
Riverview
Place
Site
North
River
Site
PAGS
Site
Redevelopment
Site
LEGEND
Legacy
Park
Site
Grove/Mason Street Enhancements
Grove Street
‘Complete Street’
w/sidewalks,
bike lanes, new
green spaces
Mason Street Traffic
Calming
Harmony Grove Road
Buffered Bike Lanes
Mack Park Neighborhood Presentation
April 8, 2014
Mason Street Traffic Calming
Coming Spring 2014
City of Salem, Massachusetts
Kimberley Driscoll, Mayor
Department of Planning & Community Development | Engineering Department
Mack Park Neighborhood Presentation
April 8, 2014
Mason Street Traffic Calming – Spring 2014
City of Salem, Massachusetts
Kimberley Driscoll, Mayor
Department of Planning & Community Development | Engineering Department
Mack Park Neighborhood Presentation
April 8, 2014
•New MAAB/ADA concrete sidewalks
•New wheelchair ramps
•Flint/Mason Streets all-way stop
reconfigured
•Tremont/Mason Streets all-way stop
w/crosswalks
•New pavement/markings/crosswalks with
motorist & pedestrian visual cues
Mack Park Neighborhood Presentation
April 8, 2014
Advancing Grove Street
MassWorks Enhancements
To a Preferred Alternative
City of Salem, Massachusetts
Kimberley Driscoll, Mayor
Department of Planning & Community Development | Engineering Department
Grove/Harmony Grove/Mason Street
Roundabout Strategy - Problematic
City of Salem, Massachusetts
Kimberley Driscoll, Mayor
Department of Planning & Community Development | Engineering Department
Need to move
northwest and
shrink; tough for
trucks; school buses
Mack Park Neighborhood Presentation
April 8, 2014
Grove/Harmony
Grove/Mason Street
Roundabout Strategy
- Problematic Grove Street City of Salem, Massachusetts
Kimberley Driscoll, Mayor
Department of Planning & Community Development
Engineering Department
Mack Park Neighborhood Presentation
April 8, 2014
Mason Street
City of Salem, Massachusetts
Kimberley Driscoll, Mayor
Department of Planning & Community Development | Engineering Department
Grove/Harmony Grove/Mason Street
Preferred Strategy –Aerial Concept
Mack Park Neighborhood Presentation
April 8, 2014
Grove/Harmony Grove/Mason Street
Preferred Strategy - Before
Looking West on Mason Street to Harmony Grove Road
City of Salem, Massachusetts
Kimberley Driscoll, Mayor
Department of Planning & Community Development | Engineering Department
Mack Park Neighborhood Presentation
April 8, 2014
Mack Park Neighborhood Presentation
April 8, 2014
Grove/Harmony Grove/Mason Street
Preferred Strategy - After
Looking West on Mason Street to Harmony Grove Road
City of Salem, Massachusetts
Kimberley Driscoll, Mayor
Department of Planning & Community Development | Engineering Department
City of Salem, Massachusetts
Kimberley Driscoll, Mayor
Department of Planning & Community Development | Engineering Department
Mack Park Neighborhood Presentation
April 8, 2014
Grove/Harmony Grove/Mason Street
Preferred Strategy - Before
Looking East on Harmony Grove Road to Mason Street
New larger
Harkin Square
City of Salem, Massachusetts
Kimberley Driscoll, Mayor
Department of Planning & Community Development | Engineering Department
Mack Park Neighborhood Presentation
April 8, 2014
Grove/Harmony Grove/Mason Street
Preferred Strategy - After
Looking East on Harmony Grove Road to Mason Street
Mack Park Neighborhood Presentation
April 8, 2014
City of Salem, Massachusetts
Kimberley Driscoll, Mayor
Department of Planning & Community Development | Engineering Department
Looking North on Grove Street to Mason Street
Grove/Harmony Grove/Mason Street
Preferred Strategy - Before
New larger
Harkin Square
Mack Park Neighborhood Presentation
April 8, 2014
City of Salem, Massachusetts
Kimberley Driscoll, Mayor
Department of Planning & Community Development | Engineering Department
Looking North on Grove Street to Mason Street
Grove/Harmony Grove/Mason Street
Preferred Strategy
Harmony Grove Road Preferred Strategy
Looking East on Harmony Grove Road
5’ 11’
2’
Grove/Harmony
Grove/Mason
Street Preferred
Strategy – Design
Progress Print
Mack Park Neighborhood Presentation
April 8, 2014
City of Salem, Massachusetts
Kimberley Driscoll, Mayor
Department of Planning & Community Development
Engineering Department
Mason Street
Grove/Goodhue/Beaver Streets
Roundabout Strategy – Also Problematic
City of Salem, Massachusetts
Kimberley Driscoll, Mayor
Department of Planning & Community Development | Engineering Department
Mack Park Neighborhood Presentation
April 8, 2014
Results in
unacceptably steep
cross slopes at 11%;
significant adverse
driveway impacts to
North River Site
North
River Site
PAGS Site
(Under Review)
Legacy Park Site
City of Salem, Massachusetts
Kimberley Driscoll, Mayor
Department of Planning & Community Development
Engineering Department
Mack Park Neighborhood Presentation
April 8, 2014
Grove/Goodhue/
Beaver Streets
Roundabout Strategy
also Problematic
North
River
Site
PAGS Site
Legacy Park Site
City of Salem, Massachusetts
Kimberley Driscoll, Mayor
Department of Planning & Community Development | Engineering Department
Grove/Goodhue/Beaver Streets
Preferred Strategy – Aerial Concept
Mack Park Neighborhood Presentation
April 8, 2014
Allows retention of
current road
directionalities;
Creates usable
neighborhood green
spaces; retains North
River Site on street
parking configurations Grove Street North River
Site
PAGS Site
Legacy Park Site
City of Salem, Massachusetts
Kimberley Driscoll, Mayor
Department of Planning & Community Development
Engineering Department
Grove/Goodhue/
Beaver Streets
Preferred Strategy
Design Progress Print
Mack Park Neighborhood Presentation
April 8, 2014
North
River Site
PAGS Site
Legacy Park Site
Grove/Goodhue/Beaver Streets
Preferred Strategy - Before
Looking South on Grove Street to Goodhue Street
City of Salem, Massachusetts
Kimberley Driscoll, Mayor
Department of Planning & Community Development | Engineering Department
Mack Park Neighborhood Presentation
April 8, 2014
Grove/Goodhue/Beaver Streets
Preferred Strategy - After
Looking South on Grove Street to Goodhue Street
City of Salem, Massachusetts
Kimberley Driscoll, Mayor
Department of Planning & Community Development | Engineering Department
Mack Park Neighborhood Presentation
April 8, 2014
Grove/Goodhue/Beaver Streets
Preferred Strategy - Before
Looking Northwest on Goodhue Street to Beaver Street
Mack Park Neighborhood Presentation
April 8, 2014
City of Salem, Massachusetts
Kimberley Driscoll, Mayor
Department of Planning & Community Development | Engineering Department
Grove/Goodhue/Beaver Streets
Preferred Strategy - After
Looking Northwest on Goodhue Street to Beaver Street
Mack Park Neighborhood Presentation
April 8, 2014
City of Salem, Massachusetts
Kimberley Driscoll, Mayor
Department of Planning & Community Development | Engineering Department
Grove Street
MassWorks
Enhancements
Preferred Strategy
Overview
Potential tree
opportunities for
Grove Street
will be explored City of Salem, Massachusetts
Kimberley Driscoll, Mayor
Department of Planning & Community Development
Engineering Department
Mack Park Neighborhood Presentation
April 8, 2014
Thanks
Questions/Comments?
City of Salem, Massachusetts
Kimberley Driscoll, Mayor
Department of Planning & Community Development | Engineering Department
Mack Park Neighborhood Presentation
April 8, 2014
Extra Slides
City of Salem, Massachusetts
Kimberley Driscoll, Mayor
Department of Planning & Community Development | Engineering Department
Mack Park Neighborhood Presentation
April 8, 2014
Mack Park Neighborhood Presentation
April 8, 2014
Mason Street Traffic Calming – Spring 2014
City of Salem, Massachusetts
Kimberley Driscoll, Mayor
Department of Planning & Community Development | Engineering Department
Mack Park Neighborhood Presentation
April 8, 2014
Mason Street Traffic Calming – Spring 2014
City of Salem, Massachusetts
Kimberley Driscoll, Mayor
Department of Planning & Community Development | Engineering Department
Mack Park Neighborhood Presentation
April 8, 2014
Mason Street Traffic Calming – Spring 2014
City of Salem, Massachusetts
Kimberley Driscoll, Mayor
Department of Planning & Community Development | Engineering Department
Mack Park Neighborhood Presentation
April 8, 2014
Mason Street Traffic Calming – Spring 2014
City of Salem, Massachusetts
Kimberley Driscoll, Mayor
Department of Planning & Community Development | Engineering Department
Mack Park Neighborhood Presentation
April 8, 2014
Mason Street Traffic Calming – Spring 2014
City of Salem, Massachusetts
Kimberley Driscoll, Mayor
Department of Planning & Community Development | Engineering Department
Mack Park Neighborhood Presentation
April 8, 2014
Grove/Harmony Grove/Mason St
Roundabout Auto-turn Sketch
City of Salem, Massachusetts
Kimberley Driscoll, Mayor
Department of Planning & Community Development | Engineering Department
Mack Park Neighborhood Presentation
April 8, 2014
Mason St
Profiles Existing vs Roundabout
City of Salem, Massachusetts
Kimberley Driscoll, Mayor
Department of Planning & Community Development | Engineering Department
Mack Park Neighborhood Presentation
April 8, 2014
Grove/Beaver/Goodhue Streets
Preferred Strategy Profiles
City of Salem, Massachusetts
Kimberley Driscoll, Mayor
Department of Planning & Community Development | Engineering Department
Regional Context
City of Salem, Massachusetts
Kimberley Driscoll, Mayor
Department of Planning & Community Development
Engineering Department
Grove Street
Enhancements
Salem
Boston
Mack Park Neighborhood Presentation
April 8, 2014