7 Carpenter Street Harry Fraser- Downspoutsoutlets
DOWNSPOUT PROPOSAL
Harry Fraser May 1, 2020
7 Carpenter St
Salem, MA 01970
Dear Mr. Fraser,
The below quote includes all labor, material, fabrication, equipment, disposal, and
insurance costs.
As requested, we are quoting you on the following work:
Install 3 new sections of 4” downspouts:
• Working off roof ladders to install 2 new sections of 4” downspouts at the above address
• Install one 4” copper corrugated downspout from the gutter, to the ground next to the
deck in the courtyard
• Install one 4” copper corrugated downspout from the gutter to the ground next to the bay
window on the left side of the house
• Install one 4” copper corrugated downspout on the front of the house. The downspout
will come down the center of the building and split into two downspouts above the front
portico roof to continue down each side of the front portico roof
• Adding downspouts will help get rid of the water that is sitting in the low sections of the
gutters
• All debris will be cleaned up at the end of each day, any metal removed will be recycled
at the time of removal
Cost to do this work will be FOUR THOUSAND EIGHT HUNDRED FIFTY ($4,850.00)
DOLLARS
Replace all of the outlets that drain the water from the gutter to the downspouts:
• Working off roof ladders to replace all the outlets in the gutter at the above address
• Currently there is a 1½” diameter outlet draining the gutters at each downspout. I am
proposing to remove the 1½’’outlets and replace with a 3¾” outlets. This will get rid of
the water in the gutter quicker to achieve less standing water in the gutters
• All debris will be cleaned up at the end of each day, any metal removed will be recycled
at the time of removal
Cost to do this work will be TWO THOUSAND FOUR HUNDRED SIXTY ($2,460.00)
DOLLARS
Clean up debris upon completion of the work and furnish workmen’s compensation and public
liability insurance to protect the owner in case of an accident while work is in progress.
If you have any questions on the information detailed above please contact us. We look forward
to working with you.
Any rotted roof boards/wood must be replaced on a time and material basis before work can
continue.
The above quote includes all labor, material, fabrication, equipment, disposal, and insurance
costs.
If this proposal is accepted, we will send you a contract detailing a payment schedule to be
signed and a copy returned to us.
Sincerely,
J.B. Kidney & CO. Inc
___________________
Scott Kidney