Loading...
22 Beckford St - lead abatement proposaltoll-free: 877-527-4040 | fax: 978-250-0565 275 Billerica Rd., Suite #2B, Chelmsford, MA 01824 Page 1 of 8 alpine@alpine-environmental.com | www.alpine-environmental.com 2/7/2019 Christopher M. Sallah Jocelyn E. Levin February 7, 2019 22 Beckford St. #1 Salem, MA RE: 22 Beckford Street #1, Salem, MA (“Subject Property”) PROPOSAL FOR SERVICES Alpine Environmental, Inc. (“Alpine”) is pleased to submit the following proposal for Lead Paint Abatement regarding the Subject Property. This proposal is based on the interpretation of the Inspection Report dated December 6, 2018 provided by Lisa Rosario. I. GUARANTEES A) Alpine Guarantees the scheduled date for completion of interior deleading. Exterior deleading completion date is also guaranteed, weather permitting. B) Work area will be sealed and decontaminated in accordance with Massachusetts regulations. C) All work is guaranteed to pass an inspection and wipe tests according to the above referenced Inspection Report and Scope of Work. Alpine will pay for any additional inspection costs incurred due to a failure. D) All work will be done in compliance with Mass. General Laws, Chapter 111, Sections 190 – 199 (Also known as the Mass. Lead Paint Statute”) and its associated regulation 105 CMR 460.000 and 454 CMR 22.00. E) Alpine’s work will be done with the highest level of care and craftsmanship. All stripped surfaces will be finish sanded. F) Alpine guarantees the quality and fit of all installed doors, windows and associated hardware. G) Alpine guarantees that the quality of carpentry will equal or exceed the quality of the existing carpentry. H) Unless specifically noted herein, painting services are not included within the scope of this proposal. I) Alpine will pay a completion penalty of $100 per day if Occupancy is delayed due to an inspection failure by Alpine or Alpine’s failure to complete the Contracted Work according to the Contracted Schedule. It is assumed that Owner will provide 24-hour wipe test results. Alpine is not responsible for delays caused by Owners, inspectors, laboratories or other circumstances beyond Alpine’s control. J) All waste will be properly disposed of off-site by Alpine. II. SAFETY Alpine’s practices meet or exceed the standards specified by the current Massachusetts regulations on Lead Paint Abatement. Quality and safety are of the highest importance to Alpine. Experienced and fully trained professionals who will environmentally isolate and decontaminate the work area will complete all work. All carpentry is performed by skilled carpenters, ensuring you a quality-finished product. No interior air will be exhausted outside the work area without having been HEPA filtered. All waste will be properly disposed of by Alpine. III. INSURANCE Alpine maintains appropriate Workers Compensation and General Liability coverage. Alpine maintains one million dollars in Occurrence Based Environmental Liability coverage and a two million dollar Environmental and General Liability Umbrella Policy. Lead Paint & Mold Removal Experts toll-free: 877-527-4040 | fax: 978-250-0565 275 Billerica Rd., Suite #2B, Chelmsford, MA 01824 Page 2 of 8 alpine@alpine-environmental.com | www.alpine-environmental.com 2/7/2019 IV. BASE PROPOSAL Area Description Qty Interior Room 1 Prepare occupied room for lead abatement. 1 Dip a standard door. Remove and reinstall existing hardware. Entire door will be stripped to bare wood. Prime door with oil based primer. 3 Strip all surfaces of a door jamb, including the header. 3 Strip an interior window sill. 3 Replace interior side stops, including head stop where applicable. 3 Chemically hand-strip off site, re-glaze, re-rope and reinstall a set of double hung sashes. Replace parting bead with Spanish Cedar, strip blind stops, wells, and jamb. Install brass V-groove weatherstripping at jambs, and vinyl bulb weatherstripping at sill and header. Re-use existing pulleys. Apply 1 coat of oil based primer after visual inspection by the Licensed Lead Inspector. Apply 2 coats finish paint. Vertical edges of windows must not be primed or painted. Sashes will be off-site for 25-30 days. $50/set sash repair allowance. 3 Install Harvey Tru-Channel aluminum triple-track storm window (black). 3 Scrape loose and flaking lead paint. Spot prime. 1 Clean room by HEPA vacuuming and TSP wash. 1 Room 2 Prepare occupied room for lead abatement. 1 Dip a standard door. Remove and reinstall existing hardware. Entire door will be stripped to bare wood. Prime door with oil based primer. Note: Owner to remove mounted shelf unit on stairway door. 2 Dip a 9 lite door and reglaze. Remove and reinstall existing hardware. Entire door will be stripped to bare wood. Prime door with oil based primer. 1 Strip all surfaces of a door jamb, including the header. 3 Strip an interior window sill. 3 Replace interior side stops, including head stop where applicable. 3 Chemically hand-strip off site, re-glaze, re-rope and reinstall a set of double hung sashes. Replace parting bead with Spanish Cedar, strip blind stops, wells, and jamb. Install brass V-groove weatherstripping at jambs, and vinyl bulb weatherstripping at sill and header. Re-use existing pulleys. Apply 1 coat of oil based primer after visual inspection by the Licensed Lead Inspector. Apply 2 coats finish paint. Vertical edges of windows must not be primed or painted. Sashes will be off-site for 25-30 days. $50/set sash repair allowance. 3 Install Harvey Tru-Channel aluminum triple-track storm window (black). 3 Scrape loose and flaking lead paint. Spot prime. 1 Scrape loose and flaking lead paint from plaster surfaces. Patch and leave ready for repainting by others. 3 Clean room by HEPA vacuuming and TSP wash. 1 toll-free: 877-527-4040 | fax: 978-250-0565 275 Billerica Rd., Suite #2B, Chelmsford, MA 01824 Page 3 of 8 alpine@alpine-environmental.com | www.alpine-environmental.com 2/7/2019 Stairs to Room 7 Prepare occupied room for lead abatement. 1 Dip a standard door. Remove and reinstall existing hardware. Entire door will be stripped to bare wood. Prime door with oil based primer. 1 Scrape loose and flaking lead paint. Spot prime. 1 Clean room by HEPA vacuuming and TSP wash. 1 Room 3 Prepare occupied room for lead abatement. 1 Dip a standard door. Remove and reinstall existing hardware. Entire door will be stripped to bare wood. Prime door with oil based primer. 1 Strip all surfaces of a door jamb, including the header. 1 Scrape loose and flaking lead paint. Spot prime. 1 Clean room by HEPA vacuuming and TSP wash. 1 Room 4 Prepare occupied room for lead abatement. 1 Dip a standard door. Remove and reinstall existing hardware. Entire door will be stripped to bare wood. Prime door with oil based primer. 3 Strip all surfaces of a door jamb, including the header. 3 Strip an interior window sill. 3 Replace interior side stops, including head stop where applicable. 3 Chemically hand-strip off site, re-glaze, re-rope and reinstall a set of double hung sashes. Replace parting bead with Spanish Cedar, strip blind stops, wells, and jamb. Install brass V-groove weatherstripping at jambs, and vinyl bulb weatherstripping at sill and header. Re-use existing pulleys. Apply 1 coat of oil based primer after visual inspection by the Licensed Lead Inspector. Apply 2 coats finish paint. Vertical edges of windows must not be primed or painted. Sashes will be off-site for 25-30 days. $50/set sash repair allowance. 3 Install Harvey Tru-Channel aluminum triple-track storm window (black). 3 Remove and dispose of all shelves, supports, lower cabinet doors, lower cabinet frame and any other misc wood surfaces. Leave closet ready for owner to install new shelves. 1 Scrape loose and flaking lead paint. Spot prime. 1 Scrape loose and flaking lead paint from plaster surfaces. Patch and leave ready for repainting by others. 1 Clean room by HEPA vacuuming and TSP wash. 1 Room 5 Prepare occupied room for lead abatement. 1 Dip a standard door. Remove and reinstall existing hardware. Entire door will be stripped to bare wood. Prime door with oil based primer. 2 Strip all surfaces of a door jamb, including the header. 2 Strip an interior window sill. 3 Replace interior side stops, including head stop where applicable. 3 toll-free: 877-527-4040 | fax: 978-250-0565 275 Billerica Rd., Suite #2B, Chelmsford, MA 01824 Page 4 of 8 alpine@alpine-environmental.com | www.alpine-environmental.com 2/7/2019 Chemically hand-strip off site, re-glaze, re-rope and reinstall a set of double hung sashes. Replace parting bead with Spanish Cedar, strip blind stops, wells, and jamb. Install brass V-groove weatherstripping at jambs, and vinyl bulb weatherstripping at sill and header. Re-use existing pulleys. Apply 1 coat of oil based primer after visual inspection by the Licensed Lead Inspector. Apply 2 coats finish paint. Vertical edges of windows must not be primed or painted. Sashes will be off-site for 25-30 days. $50/set sash repair allowance. 3 Install Harvey Tru-Channel aluminum triple-track storm window (black). 3 Remove and dispose of existing carpet, pad and tack strips and install wall to wall carpet and pad in rooms 5 and 6. (Carpet and installation allowance of $900) 1 Scrape loose and flaking lead paint. Spot prime. 1 Clean room by HEPA vacuuming and TSP wash. 1 Room 6 Prepare occupied room for lead abatement. 1 Dip a standard door. Remove and reinstall existing hardware. Entire door will be stripped to bare wood. Prime door with oil based primer. 2 Strip all surfaces of a door jamb, including the header. 2 Strip an interior window sill. 4 Replace interior side stops, including head stop where applicable. 4 Chemically hand-strip off site, re-glaze, re-rope and reinstall a set of double hung sashes. Replace parting bead with Spanish Cedar, strip blind stops, wells, and jamb. Install brass V-groove weatherstripping at jambs, and vinyl bulb weatherstripping at sill and header. Re-use existing pulleys. Apply 1 coat of oil based primer after visual inspection by the Licensed Lead Inspector. Apply 2 coats finish paint. Vertical edges of windows must not be primed or painted. Sashes will be off-site for 25-30 days. $50/set sash repair allowance. 4 Install Harvey Tru-Channel aluminum triple-track storm window (black). 4 Scrape loose and flaking lead paint. Spot prime. 1 Scrape loose and flaking lead paint from plaster surfaces. Patch and leave ready for repainting by others. 3 Clean room by HEPA vacuuming and TSP wash. 1 Room 7 Prepare occupied room for lead abatement. 1 Dip a standard door, including A-side built-in cabinet door. Remove and reinstall existing hardware. Entire door will be stripped to bare wood. Prime door with oil based primer. 3 Strip all surfaces of a door jamb, including the header. Include A-side built-in cabinet door jamb. 2 Scrape loose and flaking lead paint. Spot prime. 1 Clean room by HEPA vacuuming and TSP wash. 1 Room 8 Prepare occupied room for lead abatement. 1 toll-free: 877-527-4040 | fax: 978-250-0565 275 Billerica Rd., Suite #2B, Chelmsford, MA 01824 Page 5 of 8 alpine@alpine-environmental.com | www.alpine-environmental.com 2/7/2019 Dip a standard door. Remove and reinstall existing hardware. Entire door will be stripped to bare wood. Prime door with oil based primer. 1 Strip all surfaces of a door jamb, including the header. 1 Strip an interior window sill. 2 Replace interior side stops, including head stop where applicable. 2 Chemically hand-strip off site, re-glaze, re-rope and reinstall a set of double hung sashes. Replace parting bead with Spanish Cedar, strip blind stops, wells, and jamb. Install brass V-groove weatherstripping at jambs, and vinyl bulb weatherstripping at sill and header. Re-use existing pulleys. Apply 1 coat of oil based primer after visual inspection by the Licensed Lead Inspector. Apply 2 coats finish paint. Vertical edges of windows must not be primed or painted. Sashes will be off-site for 25-30 days. $50/set sash repair allowance. 2 Install Harvey Tru-Channel aluminum triple-track storm window (black). 2 Scrape loose and flaking lead paint. Spot prime. 1 Clean room by HEPA vacuuming and TSP wash. 1 Hall 1 Prepare occupied room for lead abatement. 1 Dip a standard door. Remove and reinstall existing hardware. Entire door will be stripped to bare wood. Prime door with oil based primer. 1 Strip all surfaces of a door jamb, including the header. 1 Strip an interior window sill. 1 Replace interior side stops, including head stop where applicable. 1 Chemically hand-strip off site, re-glaze, re-rope and reinstall a set of double hung sashes. Replace parting bead with Spanish Cedar, strip blind stops, wells, and jamb. Install brass V-groove weatherstripping at jambs, and vinyl bulb weatherstripping at sill and header. Re-use existing pulleys. Apply 1 coat of oil based primer after visual inspection by the Licensed Lead Inspector. Apply 2 coats finish paint. Vertical edges of windows must not be primed or painted. Sashes will be off-site for 25-30 days. $50/set sash repair allowance. 1 Install Harvey Tru-Channel aluminum triple-track storm window (black). 1 Scrape loose and flaking lead paint. Spot prime. 1 Clean room by HEPA vacuuming and TSP wash. 1 Kitchen Clean room by HEPA vacuuming and TSP wash. 1 Bath 1 Clean room by HEPA vacuuming and TSP wash. 1 Bath 2/Laundry Prepare occupied room for lead abatement. 1 Clean room by HEPA vacuuming and TSP wash. 1 Rear Stairs1- 2 and Hall 2 Prepare occupied room for lead abatement. 1 toll-free: 877-527-4040 | fax: 978-250-0565 275 Billerica Rd., Suite #2B, Chelmsford, MA 01824 Page 6 of 8 alpine@alpine-environmental.com | www.alpine-environmental.com 2/7/2019 Dip a standard door. Remove and reinstall existing hardware. Entire door will be stripped to bare wood. Prime door with oil based primer. 2 Strip all surfaces of a door jamb, including the header. 2 Strip handrail. 1 Strip entire stair tread, including stripping or replacing cove molding at lower edge. 10 Scrape loose and flaking lead paint. Spot prime. 1 Clean room by HEPA vacuuming and TSP wash. 1 Rear Stairs 2- 3 and 3rd Floor Hall Prepare occupied room for lead abatement. 1 Strip edge of landing floor back to first flooring board seam. 1 Strip handrail. 1 Strip entire stair tread, including stripping or replacing cove molding at lower edge. 10 Scrape loose and flaking lead paint. Spot prime. 1 Clean room by HEPA vacuuming and TSP wash. 1 Front Stairs 1-2 and Common Hall Prepare occupied room for lead abatement. 1 Dip an exterior door with no lites. Remove and reinstall existing hardware. Entire door will be stripped to bare wood. Prime door with oil based primer. 1 Strip all surfaces of a door jamb, including the header. 1 Strip an interior window sill. 2 Strip handrail. 1 Scrape loose and flaking lead paint. Spot prime. 1 Clean room by HEPA vacuuming and TSP wash. 1 Front 2nd Floor Common Hall Prepare occupied room for lead abatement. 1 Strip an interior window sill. 4 Replace interior side stops. 4 Chemically hand-strip off site, re-glaze, re-rope and reinstall a set of double hung sashes. Replace parting bead with Spanish Cedar, strip blind stops, wells, and jamb. Install brass V-groove weatherstripping at jambs, and vinyl bulb weatherstripping at sill and header. Re-use existing pulleys. Apply 1 coat of oil based primer after visual inspection by the Licensed Lead Inspector. Vertical edges of windows must not be primed or painted. Sashes will be off-site for 25- 30 days. 4 toll-free: 877-527-4040 | fax: 978-250-0565 275 Billerica Rd., Suite #2B, Chelmsford, MA 01824 Page 7 of 8 alpine@alpine-environmental.com | www.alpine-environmental.com 2/7/2019 Install Harvey Tru-Channel aluminum triple-track storm window (black). 4 Scrape loose and flaking lead paint. Spot prime. 1 Clean room by HEPA vacuuming and TSP wash. 1 Total Interior $79,375 Exterior B-side Strip window sill below 5' from ground level. 1 Scrape loose and flaking lead paint. Spot prime. 1 Seal off exterior work area for lead abatement per Mass. regulations. 1 D-side Strip window sill below 5' from ground level. 3 Scrape loose and flaking lead paint. Spot prime. 1 Total Exterior $990 Project Total: $ 80,365 I. INTERIOR PAINTING OPTION Apply 1 coat primer and 2 coats finish paint (good quality Benjamin Moore or Sherwin Williams latex) to all woodwork that was stripped or replaced during this project. Alpine is happy to provide you with additional pricing if your plans involve more painting. Additional Cost: $14,560 If you have any questions regarding this proposal, please do not hesitate to contact me. Sincerely, Todd Drew Client Services Alpine Environmental, Inc. The interior work of this project will take 21 working days to complete. The exterior work of this project will take 2 working days to complete. The painting option work of this project will take 10 working days to complete. This Proposal is valid for 90 days from the date of submission toll-free: 877-527-4040 | fax: 978-250-0565 275 Billerica Rd., Suite #2B, Chelmsford, MA 01824 Page 8 of 8 alpine@alpine-environmental.com | www.alpine-environmental.com 2/7/2019 Notice Deleading Contractors operating in the Commonwealth of Massachusetts are required to be licensed. Any inquiry concerning the same should be directed to: Department of Labor Standards 19 Staniford Street, 2nd Floor Boston, MA 02114 Phone: 617-626-6975 Deleading Contractor Lic. No. DC663 Home Improvement Contractor Reg. No. 117689 For more information on Alpine Environmental, please visit our website at www.alpine-environmental.com