95 Federal St - C of NA application - replace slate roof sections inkind Date Stamp
RECEIVED
- - AUG 28 2018
DEPT. OF PLANNING
Salem Historical Commission COMMUNITY DEVELOPMENT
i 20 was = For Office Use Only
APPLICATION FOR A CERTIFICATE OF NON-APPLICABILITY
Pursuant to the Historic District's Act (M.G.L. Chapter 40C) and the Salem Historical Commission Ordinance,
application is hereby made for issuance of a Certificate of Non-Applicability as described below for:
New Construction Moving D? Reconstruction Alteration
Demolition Painting Sign Other
District: DDerby Street Lafayette Street OMclntire Washington Square
Address of Property: `'T� r�1L0.V4J S d vxX 5Z4�._ 1 AA f
Name of Record Owner(s): 01 ia- 0,2-0 at&!fa , R+T Va4 4(1, 6, ro- c . 9 Le--C L, Z_&4y4_
Owner Mailing Address: `� ��d `/ C_.zle4j. b( 916
Description of Work Proposed
Please type or punt clearly.Attach additiona
l sheets,as necessary. 1
Val'Lo u S 1r"o E-f C l ohs a i�� l�t+�r4 r (sue S�a [�e esJ.
Wa'jC �.t-.c w.�a is t/►to e crt. a Y r
Name of Applicant: Ao ��V_�_1E, V-4li �,t ROwner[]Contractor[]Tenant E]Other:
Signature: V U0f% Date: z W1 f-
Tel.#:_ `'1g (7 14 z 14 _ E-mail Address: Val�k@-h Q 11 6) �-���. -t e.
Certificate will be mailed to the owner unless otherwise ind' at d he 1
Certificate should be mailed to: Nome r- L62 I
Mailing address: 1_9" fle e I 0 U�t� � City: -C State:&Zip: Q�j
B, KIDNEY & CO, INC* Roofers Metal Workers
41 OSBORNE STREET • TELEPHONE(978)744-2875 • FAX(978)744-2252 • SALEM,MA 01970 • jbkidney@verizon.net
ROOF WORK
Mia Dellarusso August 22,2018
95 Federal St.
Salem,MA 01970
Dear Ms.Dellarusso,
The below quote includes all labor,material,fabrication,equipment,disposal,and
insurance costs.
As requested we are quoting you on the following work:
Replace(2)valley and asphalt/slate roofing that abut valley on driveway side:
• Set a roof staging to replace the Valley and shingles on the West side towards the
back at the above address.
• Remove all the shingles that abut the valley on left side
• The left side of the valley will be replaced with asphalt shingles,and the right side
of this valley will be replaced with slate.Material will be replaced with"inkind"
materials
• Replace shingles with"Certainteed 3-tab shingles"to match the remainder of the
roof.Slate will be reused with what is salvageable,remainder will be replaced
with the same color and size as the remainder of the valley
• Ice and water shield will be applied to the roof boards at the bottom 3' and up the
entire valley,synthetic paper to the remainder of the roof expose
• Cut valley will be the finish product with a clean straight line going up the valley
on both valleys
• Remove all material at the end of each day
• Clean up debris at the end of each day
Cost to do this work will be TWO THOUSAND THREE HUNDRED SIXTY
($2,360.00)DOLLARS.
New rubber membrane roofs(2)to upper barrel vault roof on the west side:
• Strip the existing roof down to the roof boards.Dispose of material properly
• Furnish and install new .060 EPDM rubber membrane roof over a mechanically
fastened 1/2"insulation board
• Rubber membrane is fully adhered to the insulation board
• Terminate the outside edge with 16oz custom copper edge cleat.Matching the
existing metal profile.Keeping the edge metal detail the same as the existing,or
"In kind".
• All flashing and seams will be done to the manufacturers specifications.
• Terminate the wall by removing existing wood fascia and ornamental scrolls to
allow the rubber membrane to turn up behind the wood fascia.Membrane will
turn up the wall a minimum of 6".
• Clean up debris upon completion of the work each day.
Cost to do this work will be TWO THOUSAND THREE HUNDRED FIFTY FIVE
($2,355.00)DOLLARS per dormer.2-barrel vault dormers on the roof,cost to do both
will be$4,710.00.
Re-flash 2 open slate valleys,Front gable roof:
• Set a roof stage at the bottom of each valley
• Remove the existing slate on both sides of the valley,2 slate wide on both sides of
the valley and remove the old copper flashings
• Ice and water shield will be installed in the valley with 18"coverage on both sides
of the valley.This will be the underlayment for the valley
• Fabricate and install new 16oz custom copper valley flashings,bent to the pitch of
both roofs
• Copper valleys will lock together at the top of the valley forming a flat seamed lock
• 4"lap under both sides of the slate
• Slate will be reused and put back together in the order they came out,replacing any
broken or cracked slate with new slate,same color and size
• Any broken slate in the area of these valleys will be replaced at this time
• Copper nails will fasten the slate and valley stock to the roof
• Clean up debris and dispose of material properly
Cost to do each slate valley will be TWO THOUSAND ONE HUNDRED SEVENTY
($2,170.00)DOLLARS per valley.2 Valleys will be$4,340.00.
Clean up debris upon completion of the work and furnish workmen's compensation and
public liability insurance to protect the owner in case of an accident while work is in
progress.
If you have any questions on the information detailed above please contact us.We look
forward to working with you.
Any rotted roof boards/wood must be replaced on a time and material basis before work
can continue.
The above quote includes all labor,material,fabrication,equipment,disposal,and
insurance costs.
If this proposal is accepted we will send you a contract detailing a payment schedule to
be signed and a copy returned to us.
Sincerely,
J.B.Kidney&CO.Inc
Scott Kidney
A
44