CONST. OBSERVATION #3, 12/02/19 PITMAN & WARDLEy
ASSOCIATES
Architecture & Design
32 Church Street • Salem. MA • 978.744.8982
CONSTRUCTION OBSERVATION#3
December 2,2019,2019
Tom St.Pierre
Inspectional Services Director
City of Salem Inspectional Services
Salem,Massachusetts 01970
Project: RCG 33 Upham Street
Re: Construction Observation
Dear Tom,
The following observations are based on a periotic site visits by Michel Beheshti,of my staff.
Observations:
Note: First floor units,exterior work and exterior stairs are done by others and are not part of our scope of
design work or construction observations/control.We take no responsibility,and are not associated with this
work.These are repairs done directly by the building Ownership.
General areas:
• The front stair up to 2°d floor is being painted.
• The new doors with hardware leading to the 2°d floor common porch are installed.
• All units' first coat of paint is complete.
UNIT#3:
• All partitions and demising walls as well as ceilings are completed.
• All partitions and ceilings have G.W.B.,plaster and first coat of paint.
• New doors in 2'&3"floors are installed and have hardware.
• The new windows have built-in limiting devices.
• All smoke detectors,carbon monoxides and life safety devices are installed.
• The 95%of light fixtures are installed.
• All doors and windows have trims and painted.
• All electrical panels are installed.
• The MEP items,registers and grills,etc.are installed and are operational.
• The kitchen cabinets and appliances are installed.
• The new egress skylight has been installed on 3'floor roof.The porch roof railing is next.
• The 95%of bathroom fixture such as vanity,toilets and shower/tubs are installed.
• The hatch room floors have tiles as well as the shower/tub walls.
• The new hard wood floors are installed.
• The new access panel for attic is installed.
• The railing at stair to 3"floor has been installed and need paint.
• The stack washer and dryer are being installed.
• The heating system and hot water heater are installed.
Unit#4:
• All partitions and demising walls as well as ceilings are completed.
• All partitions and ceilings have G.W.B.,plaster and first coat of paint.
• New doors in 2°d&3`d floors are installed and have hardware.
• The new windows have built-in limiting devices.
• All smoke detectors,carbon monoxides and life safety devices are installed.
• The 95%of light fixtures are installed.
• All doors and windows have trims and painted.
• All electrical panels are installed.
• The MEP items,registers and grills,etc.are installed and are operational.
• The kitchen cabinets and appliances are installed.
• The new egress skylight has been installed on 3`d floor roof.The porch roof railing is next.
• The 95%of bathroom fixture such as vanity,toilets and shower/tubs are installed.
• The hatch room floors have tiles as well as the shower/tub walls.
• The new hard wood floors are installed.
• The new access panel for attic is installed.
• The railing at stair to 3`d floor has been installed and need paint.
• The stack washer and dryer are being installed.
• The heating system and hot water heater are installed.
Roof:
• The skylights for both units#3 and#4 are installed and are operational.
• The mechanical units are installed on the porch.
• The mechanical equipment for the units on porch roof are being installed.
Recommendations or Actions:
1-The Structural Engineer will be submitting independent reports.
2-The MEP,fire protection,civil reports are not part of this report.
Please do not hesitate to be in touch with this office should you have any further questions and or concerns.
Respe i lly
Peter F.Pitman,Architect
Massachusetts Registration No.8749