HOTEL GARAGE SLAB POUR SLABS CORRECTED Stephen Cummings 3 - U�4 0`'
From: Jeff Daigneault <jeffd@opechee.com>
Sent: Thursday,January 23, 2020 4:01 PM
To: 'Mike Cabral (mcabral@ccsconcrete.com)'
Cc: Jason Blais; Dennis Prescott; 'Derek Doherty'; Stephen Cummings
Subject: Garage Slab Pours Corrected version
Mike,
Please confirm the following Schedule:
2nd Floor Garage Slab 2/3 and 2/6 Approx 300 Cy per pour
3rd Floor Garage Slab 2/10 and 2/13 Approx 280 Cy per Pour
Vt Floor Garage slab 2/17 and 2/20 Approx 230 Cy per Pour
With the Towns Permission ( Steve we discussed this and Tom is aware ) we will Start at 430 am to be pumped out by
7:OOa m
Anyone has any questions feel free to call
Thanks
Jeff Daigneault
Project Manager
Opechee Construction Corporation
11 Corporate Drive I Belmont I NH 03220
C (603) 848-9575 10 (603) 527-9090
jeffd@opechee.com I www.opechee.com