HOTEL GARAGE SLAB POUR SLABS CORRECTED Stephen Cummings 3 - U�4 0`' From: Jeff Daigneault <jeffd@opechee.com> Sent: Thursday,January 23, 2020 4:01 PM To: 'Mike Cabral (mcabral@ccsconcrete.com)' Cc: Jason Blais; Dennis Prescott; 'Derek Doherty'; Stephen Cummings Subject: Garage Slab Pours Corrected version Mike, Please confirm the following Schedule: 2nd Floor Garage Slab 2/3 and 2/6 Approx 300 Cy per pour 3rd Floor Garage Slab 2/10 and 2/13 Approx 280 Cy per Pour Vt Floor Garage slab 2/17 and 2/20 Approx 230 Cy per Pour With the Towns Permission ( Steve we discussed this and Tom is aware ) we will Start at 430 am to be pumped out by 7:OOa m Anyone has any questions feel free to call Thanks Jeff Daigneault Project Manager Opechee Construction Corporation 11 Corporate Drive I Belmont I NH 03220 C (603) 848-9575 10 (603) 527-9090 jeffd@opechee.com I www.opechee.com 1