UTS Job 23418 Report 104 Soil Inspection Report 11-22-2019 Page 1
5 Richardson Lane, Stoneham, MA 02180 781-438-7755 (Voice) 781-438-6216 (Fax)
Report Date 11-22-2019Soil Inspection Report
Report No.104
Distribution Copy Job Number 23418
Project Halstead Salem Station, 72 Flint Street
Salem, MA
Contractor Fulcrum Associates
WEATHER:Cloudy, moderate wind, showers, 40's
TIME:7:00 AM
CONTACT:Pat Madden of Fulcrum
PURPOSE:To observe earthwork construction and perform field density testing
EQUIPMENT:Deere 450C, 380G, 75G & 992E excavator; Wacker DPU 6555 & 200Lb. plate
compactors, Cat 980 & 950 loaders and Ingersoll Rand pro pac 110 seried
10 ton drum roller
TEST METHOD:Sand Cone Nuclear Densometer
TITLE:Inspector Staff Engineer EngineerX
OBSERVATIONS:
Backfilling was performed for site lighting utilities along the west side of building 1. The conduit
was bedded in clean imported sand. The shallow trench was backfilled placing a single lift of the
select gravel generated during excavation generally consisting of F-C gravel and sand, trace silt. The
surface of the backfill material was compacted utilizing the Wacker 1/2 ton plate compactor exhibiting
stable/firm conditions.
Formwork was performed for the duct bank located at the North side of buildings 1 & 2. The power supply
conduits were separated from the low voltage conduits and encased in concrete. Low voltage utilities
within landscape areas were bedded in clean imported sand. No backfilling was performed on this date.
Drainage utility installation was performed near the North river adjacent to the Southeast corner of
building 2. DMH 7 and DMH 8 were installed on this date and connected to previously installed STC 4800.
The structures were set atop an approximately 12" thick base of 3/4" crushed stone. Existing timber
piles were encountered below the structures and remained in place. The structures were connected using
24" diameter HDPE. The piping was bedded and covered in 3/4" crushed stone. Backfilling operations were
not witnessed.
Inspector Premium Travel
Name Time Hours Time
M. Chace No 8.00 1 Hr(s)
Page 2
5 Richardson Lane, Stoneham, MA 02180 781-438-7755 (Voice) 781-438-6216 (Fax)
Report Date 11-22-2019Soil Inspection Report
Report No.104
Distribution Copy Job Number 23418
Project Halstead Salem Station, 72 Flint Street
Salem, MA
Contractor Fulcrum Associates
REVIEWED BY:Chuck Fraser
Our reports are available in PDF form via email. Please email us at reports@utsofmass.com for more information.
cc:Fulcrum Associates Pat Madden
Fulcrum Associates Brad Scott
Fulcrum Associates Darrin Standish
DMS Design Sid Silveira
DMS Design Dan Skolski
City of Salem Steve Cummings
Veitas & Veitas Linas Dabrila
DSF Group Paul Bowie
DSF Group Benjamin Greene
Fulcrum Group Patricia Dwyer
UTS Matt Chace
DSF Flint Salem LLC Dimitri Kourtis
Fulcrum Associates Bob Levesque
DSF Advisors Thomas Mazza
UTS of Massachusetts, Inc. Page 3
5 Richardson Lane, Stoneham, MA 02180 781-438-7755 (Voice) 781-438-6216 (Fax)
Report Date 11-22-2019
Report No.104
Job Number 23418
Project Halstead Salem Station, 72 Flint Street
Salem, MAAttachment