UTS Job 23418 Report 98 Soil Inspection Report 11-15-2019 Page 1
5 Richardson Lane, Stoneham, MA 02180 781-438-7755 (Voice) 781-438-6216 (Fax)
Report Date 11-15-2019Soil Inspection Report
Report No.98
Distribution Copy Job Number 23418
Project Halstead Salem Station, 72 Flint Street
Salem, MA
Contractor Fulcrum Associates
WEATHER:Partly cloudy, 30°-40°
TIME:7:00 AM
CONTACT:Pat Madden of Fulcrum
PURPOSE:To observe earthwork construction and perform field density testing
EQUIPMENT:Deere 450C, 380G, 75G & 992E excavators; Wacker DPU 6555 & 200Lb. plate
compactors; CAT 980 & 950 loaders; and Ingersoll Rand pro pac 110 series
10 ton drum roller
TEST METHOD:Sand Cone Nuclear Densometer
TITLE:Inspector Staff Engineer EngineerX
OBSERVATIONS:
Installation of light pole bases was performed at the North side of building 1. The excavation was
performed utilizing the Deere 27 mini excavator. The Precast structures were set atop a base of 3/4"
crushed stone. The bases were backfilled using the same urban fill material generated during excavation
generally consisting of F-C sand, some gravel, little silt. The material was compacted utilizing the
Wacker 1/2 ton plate compactor exhibiting stable/firm conditions. In some areas (adjacent to the
proposed site retaining wall) were elevated to accommodate installation of the light pole bases. The
material used is the aforementioned onsite generated common fill (urban fill). Controlled 12"-18" thick
lifts were placed and graded. Each lift was compacted utilizing the small IR drum roller or Wacker
plate compactor exhibiting stable/firm conditions. Minimal backfilling was performed as necessary.
Inspector Premium Travel
Name Time Hours Time
M. Chace No 8.00 1 Hr(s)
REVIEWED BY:Chuck Fraser
Our reports are available in PDF form via email. Please email us at reports@utsofmass.com for more information.
Page 2
5 Richardson Lane, Stoneham, MA 02180 781-438-7755 (Voice) 781-438-6216 (Fax)
Report Date 11-15-2019Soil Inspection Report
Report No.98
Distribution Copy Job Number 23418
Project Halstead Salem Station, 72 Flint Street
Salem, MA
Contractor Fulcrum Associates
cc:Fulcrum Associates Pat Madden
Fulcrum Associates Brad Scott
Fulcrum Associates Darrin Standish
DMS Design Sid Silveira
DMS Design Dan Skolski
City of Salem Steve Cummings
Veitas & Veitas Linas Dabrila
DSF Group Paul Bowie
DSF Group Benjamin Greene
Fulcrum Group Patricia Dwyer
UTS Matt Chace
DSF Flint Salem LLC Dimitri Kourtis
Fulcrum Associates Bob Levesque
DSF Advisors Thomas Mazza
UTS of Massachusetts, Inc. Page 3
5 Richardson Lane, Stoneham, MA 02180 781-438-7755 (Voice) 781-438-6216 (Fax)
Report Date 11-15-2019
Report No.98
Job Number 23418
Project Halstead Salem Station, 72 Flint Street
Salem, MAAttachment