UTS Job 23418 Report 1 C.M.U. Mortar Summary Report 10-23-2019 Page 1
5 Richardson Lane, Stoneham, MA 02180 781-438-7755 (Voice) 781-438-6216 (Fax)
Report Date 10-23-2019C.M.U. Mortar Summary Report
Report No.1
Distribution Copy Job Number 23418
Project Halstead Salem Station, 72 Flint Street
Salem, MA
Contractor Fulcrum Associates
Mortar
Strength (psi.):O - 350 N - 750 S - 1800 M - 2500
Other:
On Site Mix:Pre-Mix (brand):Quikrete Spec-Mix Masonry Cement (brand):
Admixture(s):Type:Brand:
Type:Brand:
Pigment(s):Type:Brand:Dye Lot:
Type:Brand:Dye Lot:
Block
Block Type:X Standard Glazed Split Faced
Other:
Block Size:4"6"8"10"X 12"
Other:
Horizontal Joint Reinforcement
Wire Size (#):9
Type:Truss X Ladur Tri-Rod Hook and Eye Prefab "Ells"Prefab "Tees"
Other:
Spacing:8" o.c.X 16" o.c.24" o.c.
Other:
Wall Ties:Adjustable Trap Triangle Corrugated
Other:
Flashing
Material:
Location:Thruwall Base Sill Head Jamb Cap
Other:
Joints
Type:Struck X Tooled Raked
Other:
GENERAL REMARKS:Total wall construction this date. Building #1, Elevator Shaft, Courses 8-16. *All
vertical reinforcement was wet set after grout placement.
Inspector Premium Travel
Name Time Hours Time
M. Chace No
Page 2
5 Richardson Lane, Stoneham, MA 02180 781-438-7755 (Voice) 781-438-6216 (Fax)
Report Date 10-23-2019C.M.U. Mortar Summary Report
Report No.1
Distribution Copy Job Number 23418
Project Halstead Salem Station, 72 Flint Street
Salem, MA
Contractor Fulcrum Associates
REVIEWED BY:William P. Crabtree
Our reports are available in PDF form via email. Please email us at reports@utsofmass.com for more information.
cc:Fulcrum Associates Pat Madden
Fulcrum Associates Brad Scott
Fulcrum Associates Darrin Standish
DMS Design Sid Silveira
DMS Design Dan Skolski
City of Salem Steve Cummings
Veitas & Veitas Linas Dabrila
DSF Group Paul Bowie
DSF Group Benjamin Greene
Fulcrum Group Patricia Dwyer
UTS Matt Chace
DSF Flint Salem LLC Dimitri Kourtis
Fulcrum Associates Bob Levesque
DSF Advisors Thomas Mazza