UTS Job 23418 Report 79 Soil Inspection Report 10-22-2019 Page 1
5 Richardson Lane, Stoneham, MA 02180 781-438-7755 (Voice) 781-438-6216 (Fax)
Report Date 10-22-2019Soil Inspection Report
Report No.79
Distribution Copy Job Number 23418
Project Halstead Salem Station, 72 Flint Street
Salem, MA
Contractor Fulcrum Associates
WEATHER:Partly cloudy 50-60°
TIME:7:00 AM
CONTACT:Bob Levesque of Fulcrum Associates
PURPOSE:Observe earthwork construction
EQUIPMENT:Deere 450C, 380G, 75G & 992E Excavator, Wacker DPU 6555 & 200Lb. Plate
Compactors, CAT 980 & 950 Loaders & IR Pro Pac 110 Series 10 ton Drum
Roller
TEST METHOD:Sand Cone Nuclear Densometer
TITLE:Inspector Staff Engineer EngineerX
OBSERVATIONS:
This report follows a site visit to observe/test the earthwork for: Footing trench excavation.
Footing excavation continued within the Southeastern limits of building 1. The trench was
excavated to design elevation utilizing the Deere 450 excavator equipped with a flat cutting edge
(flared teeth) to minimize sub grade disturbance. Ground improvements were previously completed in this
area by installing GCC deep foundation elements. The elements were previously excavated to design
cutoff elevation. The area was over excavated a minimum 6" below design BOF elevation to provide a
cushion/base of material between the elements and the footing. All GCC elements were carefully located
and exposed during excavation. The sub grade soil in this area is existing loamy urban fill generally
consisting of F - M sand, little gravel, little silt containing wood, organic silt, ash, slag etc. A 6 -
12" thick layer of ¾" crushed stone was placed and graded. Mirafi filter fabric was placed between the
sub grade and crushed stone footing base material. The surface of the stone was compacted utilizing the
heavy plate compactor exhibiting stable/firm conditions.
Placement of slab base course materials was initiated within the Western limits of building 1. The
material used is imported 1 ½" reprocessed material from the Lorusso Pit in Revere, MA. A single 15"
thick lift was placed and graded utilizing the Deere bulldozer. An access ramp was constructed at the
permanent ramp location for building access using the same material described above. The material was
compacted employing several passes of coverage utilizing the wacker ½ ton plate compactor and IR 10 ton
drum roller exhibiting stable/firm conditions. Some of the existing in place material was allowed to
remain as base course material on a case by case basis depending on consistency.
Page 2
5 Richardson Lane, Stoneham, MA 02180 781-438-7755 (Voice) 781-438-6216 (Fax)
Report Date 10-22-2019Soil Inspection Report
Report No.79
Distribution Copy Job Number 23418
Project Halstead Salem Station, 72 Flint Street
Salem, MA
Contractor Fulcrum Associates
Inspector Premium Travel
Name Time Hours Time
M. Chace No 8.00 1 Hr(s)
REVIEWED BY:Chuck Fraser
Our reports are available in PDF form via email. Please email us at reports@utsofmass.com for more information.
cc:Fulcrum Associates Pat Madden
Fulcrum Associates Brad Scott
Fulcrum Associates Darrin Standish
DMS Design Sid Silveira
DMS Design Dan Skolski
City of Salem Steve Cummings
Veitas & Veitas Linas Dabrila
DSF Group Paul Bowie
DSF Group Benjamin Greene
Fulcrum Group Patricia Dwyer
UTS Matt Chace
DSF Flint Salem LLC Dimitri Kourtis
Fulcrum Associates Bob Levesque
DSF Advisors Thomas Mazza
UTS of Massachusetts, Inc. Page 3
5 Richardson Lane, Stoneham, MA 02180 781-438-7755 (Voice) 781-438-6216 (Fax)
Report Date 10-22-2019
Report No.79
Job Number 23418
Project Halstead Salem Station, 72 Flint Street
Salem, MAAttachment