UTS Job 23418 Report 80 Soil Inspection Report 10-23-2019 Page 1
5 Richardson Lane, Stoneham, MA 02180 781-438-7755 (Voice) 781-438-6216 (Fax)
Report Date 10-23-2019Soil Inspection Report
Report No.80
Distribution Copy Job Number 23418
Project Halstead Salem Station, 72 Flint Street
Salem, MA
Contractor Fulcrum Associates
WEATHER:Partly cloudy 50-60°
TIME:7:00 AM
CONTACT:Bob Levesque of Fulcrum Associates
PURPOSE:Observe earthwork construction
EQUIPMENT:Deere 450C, 380G, 75G & 992E Excavator, Wacker DPU 6555 & 200Lb. Plate
Compactors, CAT 980 & 950 Loaders & IR Pro Pac 110 Series 10 ton Drum
Roller
TEST METHOD:Sand Cone Nuclear Densometer
TITLE:Inspector Staff Engineer EngineerX
OBSERVATIONS:
This report follows a site visit to observe/test the earthwork for: Footing trench excavation.
Footing excavation continued along the Southern perimeter of building 1. The trench was excavated
to design elevation utilizing the Deere 450 excavator equipped with a flat cutting edge (flared teeth)
to minimize sub grade disturbance. Ground improvements were previously completed in this area by
installing GCC deep foundation elements. The elements were previously excavated to design cutoff
elevation. The area was over excavated a minimum 6" below design BOF elevation to provide a
cushion/base of material between the elements and the footing. All GCC elements were carefully located
and exposed during excavation. The sub grade soil in this area is existing loamy urban fill generally
consisting of F - M sand, little gravel, little silt containing wood, organic silt, ash, slag etc. In
some areas, organic tannin bark sub grade conditions were present. A 6 - 12" thick layer of ¾" crushed
stone was placed and graded. Mirafi filter fabric was placed between the sub grade and crushed stone
footing base material. The surface of the stone was compacted utilizing the heavy plate compactor
exhibiting stable/firm conditions.
Plumbing utility trench excavation was initiated within the SW limits of building 1 (pet wash).
The trench was carried down to design elevation utilizing the Deere 75 excavator. Organic soil was
segregated from inorganic material during excavation for possible re use as structural backfill.
Taps were performed on the recently installed water main at both ends of the loop (near Flint St
and Mason St). The main was excavated and exposed utilizing the Deere 75 excavator. Corporations and
valves were installed to facilitate pressure testing and chlorination. The excavations were temporarily
Page 2
5 Richardson Lane, Stoneham, MA 02180 781-438-7755 (Voice) 781-438-6216 (Fax)
Report Date 10-23-2019Soil Inspection Report
Report No.80
Distribution Copy Job Number 23418
Project Halstead Salem Station, 72 Flint Street
Salem, MA
Contractor Fulcrum Associates
backfilled as they will need to be re excavated at a later date to close and cap the corporations.
Inspector Premium Travel
Name Time Hours Time
M. Chace No 8.00 1 Hr(s)
REVIEWED BY:
Chuck Fraser
Our reports are available in PDF form via email. Please email us at reports@utsofmass.com for more information.
cc:Fulcrum Associates Pat Madden
Fulcrum Associates Brad Scott
Fulcrum Associates Darrin Standish
DMS Design Sid Silveira
DMS Design Dan Skolski
City of Salem Steve Cummings
Veitas & Veitas Linas Dabrila
DSF Group Paul Bowie
DSF Group Benjamin Greene
Fulcrum Group Patricia Dwyer
UTS Matt Chace
DSF Flint Salem LLC Dimitri Kourtis
Fulcrum Associates Bob Levesque
DSF Advisors Thomas Mazza
UTS of Massachusetts, Inc. Page 3
5 Richardson Lane, Stoneham, MA 02180 781-438-7755 (Voice) 781-438-6216 (Fax)
Report Date 10-23-2019
Report No.80
Job Number 23418
Project Halstead Salem Station, 72 Flint Street
Salem, MAAttachment