UTS Job 23418 Report 2 Asphalt Inspection Report 10-21-2019-Page 1
5 Richardson Lane, Stoneham, MA 02180 781-438-7755 (Voice) 781-438-6216 (Fax)
Report Date 10-21-2019Asphalt Inspection Report
Report No.2
Distribution Copy Job Number 23418
Project Halstead Salem Station, 72 Flint Street
Salem, MA
Contractor Fulcrum Associates
WEATHER:
TIME:
CONTACT:
TEST METHOD:Field Nuclear Densometer
OBSERVATIONS:
The following are the results of the extraction and Marshall density tests performed on a Sample #103
of asphalt binder course placed at the above referenced project.
SIEVE SIZE % PASSING JOB MIX
1" 100.0 100.0-
3/4" 98.6 80-100
1/2" 70.9 55-75
3/8" 48.3
No. 4 33.8 28-50
No. 8 24.4 20-38
No. 16 17.8
No. 30 13.0 8-22
No. 50 8.5 5-15
No. 100 4.8
No. 200 2.6 0-5
Asphalt Content - 5.1%
Marshall Density - 149.8 PCF
Asphalt Content JMF Range 4.5-5.5
Inspector Premium Travel
Name Time Hours Time
R. Granada No
Page 2
5 Richardson Lane, Stoneham, MA 02180 781-438-7755 (Voice) 781-438-6216 (Fax)
Report Date 10-21-2019Asphalt Inspection Report
Report No.2
Distribution Copy Job Number 23418
Project Halstead Salem Station, 72 Flint Street
Salem, MA
Contractor Fulcrum Associates
REVIEWED BY:William P. Crabtree
Our reports are available in PDF form via email. Please email us at reports@utsofmass.com for more information.
cc:Fulcrum Associates Pat Madden
Fulcrum Associates Brad Scott
Fulcrum Associates Darrin Standish
DMS Design Sid Silveira
DMS Design Dan Skolski
City of Salem Steve Cummings
Veitas & Veitas Linas Dabrila
DSF Group Paul Bowie
DSF Group Benjamin Greene
Fulcrum Group Patricia Dwyer
UTS Matt Chace
DSF Flint Salem LLC Dimitri Kourtis
Fulcrum Associates Bob Levesque