0311 HIGHLAND AVENUE, TOWN FAIR TIRE MILLIKEN ASSOCIATES
ARCHITECTURE• PLANNING
44 TOP O HILL ROAD WAPPINGERS FALLS NEW YORK 12590-2234
TEL 845 463 3030 FAX 845 463 321 0
Steve Cummings
Building Office - Inspectional Services
98 Washington Street
2nd Floor
Salem, MA 01970
RE: Town Fair Tire Center, 311 Highland Avenue, Salem, MA
April 8, 2019
Mr. Cummings,
Based on observations of the referenced project, we submit the following:
The subsurface drainage work has been completed. The Service Area
floor drains are installed. The connections have been made to the oil
separation tank and sewer system. The rough grading has been done on the
site. The bollards at the Service Area overhead doors are in place.
The new wall openings at the Service Areas have been created. The piers
between the overhead doors been constructed with reinforcing, and the steel
lintels are in place as shown on the drawings. The overhead doors have been
installed. The upper fascias have been framed and sheathed. The wall
openings no longer needed have been framed in and sheathed.
The interior C.M.U. wall has been opened up and the new column and
steel lintels are in place. The interior partitions at the Service Areas and the
Office area have been framed. The electrical work has been roughed in. The
gypsum board work is being completed. The old finish flooring has been
removed, and the floor trenches have been filled with concrete. The roof drain
lines have been moved as necessary and reconnected to the storm drain system.
At this stage the construction has progressed in accordance to the
drawings.
Sincerely,
.yS4�nE4 ARC�ij
��• �� G. Rgj�\r
t`
. r.
�v:'r. �2 •
of fk Nva''
Andrew Milliken
Massachusetts Registered Architect #10899