CON CON DOC Initial Construction Control Document
To be submitted with the building permit application by a
Registered Design Professional
for work per the 8'h edition of the
Massachusetts State Building Code, 780 CMR, Section 107
Project Title: YMCA Lynch Van Otterloo-Renovations Date: April 4,2017
Property Address: Leggs Hill,Salem,MA
Project: Check(x)one or both as applicable: - New construction X Existing Construction
Project description: Interior renovations for approx.8,000 sf of floor area to include new partition walls,finishes,
toilet room, and interfloor.
I John A. Seger MA Registration Number: 30105 Expiration date: August 31,2017 , am a registered
design professional, and I have prepared or directly supervised the preparation of all design plans, computations and
specifications concerning':
X Architectural Structural Mechanical
Fire Protection Electrical _ Other:
for the above named project and that to the best of my knowledge,information, and belief such plans, computations and
specifications meet the applicable provisions of the Massachusetts State Building Code, (780 CMR),and accepted
engineering practices for the proposed project. I understand and agree that I(or my designee) shall perform the necessary
professional services and be present on the construction site on a regular and periodic basis to:
1. Review, for conformance to this code and the design concept, shop drawings, samples and other submittals by the
contractor in accordance with the requirements of the construction documents. -
2. Perform the duties for registered design professionals in 780 C.N4R Chapter 17, as applicable.
3. Be present at intervals appropriate to the stage of construction to become generally familiar with the progress and
quality of the work and to determine if the work is being performed in a manner consistent with the approved
construction documents and this code.
Nothing in this document relieves the contractor of its responsibility regarding the provisions of 780 CMR 107.
When required by, the building official,I shall submit field/progress reports(see item 3.)together with pertinent
comments, in a form acceptable to the building official.
Upon completion of the work, I shall submit to the building official a`Fin Control Document'.
Enter in the space to the right a"wet" or
electronic signature and seal: ' 0Z
Phone number: 978-744-0208 Email: iohnaseger(a)segerarchitects.com
Building Official Use Only
Building Official Na-e: Permit No.: Date:
Note 1.Indicate with an`x'project design plans,computations and specifications that you prepared or directly supervised.If`other'is chosen,
provide a description.
r
Version 06 11 2013