ARCH. FIELD RPT 01/08/2018 the
architectural
ARCHITECT'S FIELD REPORT tatteam
PROJECT NAME: Pequot Highlands Interior Mod-Rehab
PROJECT LOCATION: 12 First Street Salem,MA United States
ARCHITECT'S PROJECT#: 16068.00 FIELD REPORT: 00018
DATE: 1/8/2018
WEATHER DESCRIPTION:
TIME TEMP WIND SPEED HUMIDITY REMARKS
11:00 AM 28°F 13.8 mph 47% Overcast
EST.%COMPLETION&CONFORMANCE WITH SCHEDULE:60%Complete
PRESENT ON-SITE:
Michelle King The Silver Street Group,LLC
Eric Clory The Silver Street Group,LLC
Carpenters,Plumbers,Electricians,Elevator Techs
Chris Poulin Silver Street Development
Mike Swiatek Port Harbor Construction, INC.
Brenda Paradis The Silver Street Group
Joan Russell WinnCompanies
TOTAL: 7
OBSERVATIONS:
ITEM CATEGORY REMARKS PHOTOS
1 Work in Unit punchlist work is ongoing in North and South
Progress buildings.
2 Work in Fire Alarm installation testing in the South building is
Progress waiting for fire department scheduling after the
recent holiday season.
3 Work in Corridor scope of work is ongoing.
Progress
4 Work in South Building roof replacement ongoing.90%
Progress complete.Roof parapet installation is on hold until
temperatures allow work to continue.
5 Work in North Building roof replacement is ongoing.90%
Progress complete.Cell phone equipment relocation is
ongoing.
6 Work in Elevator#2 scope of work is ongoing.
Progress
The Architectural Team, Inc, 50 Commandants Way at Admiral's Hill Chelsea MA 02150 T 617.889.4402 F 617.884.4329 W"."v.architecturalteam.com
Page 1 of 4
ARCHITECT'S FIELD REPORT a
DATE: 1/8/2018
FR: 00018
ITEM CATEGORY REMARKS PHOTOS
7 Work in Brick demolition on the building link between North
Progress and South buildings.
8 Work in Old boiler room insulation installation is ongoing in
Progress North building.
9 Work in South building lobby work is ongoing.
Progress
10 Observations Unit work in the South building is complete.
11 Observations ADA and AV unit work is complete.
12 Observations Panel installation on South building is complete.
Trim and parapet outstanding.
13 Observations Window installation on South building is complete.
Trim outstanding.
14 Observations New Cogen unit installation is complete.Overflow
valve repairs are complete.
15 Observations Swingstage work on 12 story building is on hold due
to cell antennae coordination.Work will begin when
temperatures allow.
16 Items to Verify PHC must verify CoGen exhaust location complies
with engineer's response to RFI#30.
17 Observations Photos
m
2
s
I he Architectural Team, Inc, 50 Commandants Way at Admiral s Hill Chelsea NIA 02150 T 617.880.4402 F 617.884.4520 ivww.architecturaiteam.ccrn
Page 2 of 4
ARCHITECT'S FIELD REPORT
DT: 1mm8
F: «@a
EE CATEGORY RMRS PHOTOS
: » . / ~
The
Architectural Teas Inc. w Commandant Way at gnaw Hill Chelsea v;mly lezam*m: Feza+ga w waw.umltea»om
Page 3¥4
� f
ARCHITECT'S FIELD REPORT
DATE: 1/8/2018
FR: 00018
ITEM CATEGORY REMARKS PHOTOS
i
fl i
1
ATTACHMENTS:
Report By: The Architectural Team,Inc./Lamarr Rollins II
Distribution:
Phil Renzi The Architectural Team,Inc. prenzi@architecturalteam.com
Chris Poulin Silver Street Development cpoulin@thesilverstreetgroup.com
Eric Clory The Silver Street Group,LLC eclory@thesilverstreetgroup.com
Mike Swiatek Port Harbor Construction, INC. mswiatek@portharborconstruction.co
m
The Architectural team, Inc. 50 Commandants Way at Admiral's Hi Chelsea MA 02150 T 617.889.4402 F 617.884.4329 arch itecturaltearn.com
Page 4 of 4